Do I need a permit to build a new home in Cary, NC? Review time, the three fee parts, the owner rule and the CO

Yes. Building a new house in Cary needs a Town building permit, which the Town says normally clears plan review in one to two weeks, and a certificate of occupancy one to two business days after the final. 79 builders filed 1,087 new home permits in Cary from October 2023 to September 2026, at a usual value of $359,500, and 99.0% of those a year or more old reached final.

By Contractor Records · data through October 16, 2026

What the Town requires

From the Town's Residential Permits & Inspections FAQ (read 26 October 2026):

Step What Cary says
Permit "A permit is required anytime work is done on a building or structure, or the systems serving the structure."
Where to apply The Town's electronic plan review site; first-time applicants set up an account
Plans "Upload your complete set of plans and a plot plan in a readable scale"
Survey "An as-built survey is required if the proposed construction is within 5' of a setback, easement or buffer"
Contractors "include all of your contractors' names, addresses and state license numbers"
Plan review "normally takes one to two weeks" for one- and two-family homes; you are contacted to pick up the permit
Inspections Scheduled in Building Permits Online "24 hours a day, seven days a week", in person at Town Hall, or by calling 311 (919-469-4000 from outside Cary)
Certificate of occupancy "typically processed within one to two business days following the approved final building inspection", emailed to the homeowner of record and the contractor

The Town's Residential Inspections Information page adds that "A permit is active for six months without any activity, or one year after the last inspection", and that restarting an expired project means a new permit "with the fees doubled."

Who can build it

A licensed general contractor. North Carolina's general contractor law applies when "the cost of the undertaking is forty thousand dollars ($40,000) or more", and the license limitation caps the job: Limited up to $750,000, Intermediate up to $1,500,000, Unlimited without restriction (G.S. 87-1 and 87-10). At Cary's usual $359,500 a Limited license covers most houses; the upper end of Cary builders' usual jobs, $984,847, needs Intermediate. Check the limitation on the NCLBGC search; the electrician and plumbing and HVAC contractors are checked on their own boards, all in the Cary contractor license lookup.

You, as owner. The Town says "an owner of the property can do their own building, electrical, plumbing, and mechanical work", and "State law requires that the property be the owner's primary residence for at least 12 months after completion of the work." If you may sell or rent within a year, use a licensed builder.

What it costs

The Town's FAQ says "For most new construction permits, there are three main components": building permit fees, which "are figured based on square footage"; utility connection and water and sewer development fees, "based on the anticipated use of water and sewer services"; and transportation fees. The Town's Fees page says the rates are in its Proposed Annual Operating Budget 2026: building permit fees on pages 212 to 213, 216 to 218 and 229, utility connection fees on 225 to 226, development fees on 226 to 229, and transportation and development impact fees on page 231. The FAQ also mentions a Fees Estimation Guide; ask for an estimate on your square footage before closing on a lot.

How to apply and get inspected

  1. Apply on the Town's electronic plan review site with the full plan set, plot plan and every contractor's license number.
  2. Plan review, usually one to two weeks; pick up the permit when contacted.
  3. Inspections through Building Permits Online, which also shows the results.
  4. Final and CO. After the approved final building inspection, the certificate of occupancy usually follows within one to two business days.

What 1,087 Cary new home permits show

Measure Cary new homes
Permits, October 2023 to September 2026 1,087
Builders / with a permit in the last 12 months 79 / 39
Usual filed value $359,500
Middle half of builders' usual house (31 builders with 3+ permits) $333,408 to $984,847
Reached final (permits a year or more old) 99.0%
Usual days from issue to final 176
Share held by the busiest / five busiest builders 26.5% / 67.8%
Builders with a single permit 36 (45.6%)
Busiest / quietest month July (147) / November (52)

Cary new homes are two markets. Production builders dominate: M/I Homes of Raleigh, LLC filed 62 in the last 12 months, and five builders hold 67.8% of permits. The rest is a long tail: 36 builders filed one Cary house in three years, and builders' usual houses range from $333,408 to $984,847. Almost everything reaches final (99.0%), so in Cary the useful comparison is speed and price, not completion. Prices by home value: Cary new home cost; national: new home construction cost.

Compare every Cary home builder by permits and usual price →

Related

Rules elsewhere: do I need a permit to build a house. Choosing one: hiring a home builder. Past permits on a lot: Cary building permit search. Counts by year: Cary permit statistics.

What this does not tell you

Filed value is the builder's construction figure and leaves out the lot. The Town publishes fee rates inside its budget document, not as a standalone schedule, so we give the fee structure, not amounts. Our file does not match NC licenses.

How we know this

Permit, application, review time, survey, inspection and certificate of occupancy rules are quoted from the Town of Cary's Residential Permits & Inspections FAQ; permit expiry from its Residential Inspections Information page; fee locations from its Fees page, all read 26 October 2026; license thresholds from G.S. 87-1 and 87-10. Our figures are Town of Cary new single-family home permits, October 2023 to September 2026.

Numbers come from Town of Cary building permit applications (issued permits only), data through October 16, 2026. Nobody paid to be on this page and nobody can.

Questions

  • Do I need a permit to build a house in Cary?

    Yes. The Town's FAQ says 'A permit is required anytime work is done on a building or structure, or the systems serving the structure.' A new home also needs a plot plan, and an as-built survey if it comes within 5 feet of a setback, easement or buffer.

  • How long does it take to get a new home permit in Cary?

    The Town says plan review for one- and two-family homes 'normally takes one to two weeks', and it contacts you to pick up the permit when everything is approved. In our file the usual Cary new home then took 176 days from issue to final.

  • How much are permit fees for a new house in Cary?

    The Town lists three main parts: building permit fees figured on square footage, utility connection and water and sewer development fees based on expected water use, and transportation fees. The rates are in the Town's Proposed Annual Operating Budget 2026, building permit fees on pages 212 to 213, 216 to 218 and 229.

  • Can I build my own house in Cary without a contractor?

    Yes, as owner. The Town says an owner can do their own building, electrical, plumbing and mechanical work, but 'State law requires that the property be the owner's primary residence for at least 12 months after completion of the work.' Otherwise a new home needs a licensed general contractor, since the North Carolina license applies from $40,000.

  • How long after the final inspection do I get a certificate of occupancy in Cary?

    Usually 1 to 2 business days. The Town says certificates of occupancy are 'typically processed within one to two business days following the approved final building inspection', and emailed to the homeowner of record and the contractor. The usual Cary new home reached final 176 days after its permit was issued.