Data through September 2026 · updated 19 Oct 2026

7,020 building permits issued in Lincoln, October 2024 through September 2026: about 3,510 a year. The biggest kind of work is garages, sheds & shade structures, with 1,760. 3,602 permits in the last 12 months (Oct 2025–Sep 2026), 5% more than the 3,418 in the 12 months before. 81% were permits for homes. The busiest month for permits is April.

What this file covers: The Lancaster County Assessor logs only permits that can change a property's assessed value, so stand-alone electrical, plumbing and HVAC permits are missing.

7,020permits issued
3,602last 12 months
+5%vs the 12 months before
81%for homes
Aprbusiest month
Sep 2026records through

By kind of work

Permits issued October 2024 through September 2026. Last 12 months is Oct 2025–Sep 2026; the 12 months before is Oct 2024–Sep 2025. Homes is the share issued as residential permits. Busiest month is the calendar month with the most permits on average.

Kind of workPermitsShareLast 12 mo12 mo beforeChangeHomesBusiest month
Garages, sheds & shade structures1,76025%874886−1%100%April
New homes1,75225%914838+9%100%May
Remodels & repairs1,37220%703669+5%100%October
Demolition2724%125147−15%81%April
Additions2273%13196+36%100%August
Pools & spas1602%7684−10%100%July
Roofing1242%7747+64%94%July
Other1,35319%702651+8%4%April

Download this table (CSV)

By year

Permits issued in each calendar year of the window. Per year scales a part year to 12 months.

YearMonthsPermitsPer year
2024 (from October)38343,336
2025123,4413,441
2026 (through September)92,7453,660

Download this table (CSV)

By month

Permits issued each month, October 2024 through September 2026. The tallest bar is the busiest month on file.

Oct 2024: 355Oct2024Nov 2024: 268Dec 2024: 211Jan 2025: 194Jan2025Feb 2025: 178Mar 2025: 271Apr 2025: 363May 2025: 338Jun 2025: 304Jul 2025: 330JulAug 2025: 292Sep 2025: 314Oct 2025: 359Nov 2025: 278Dec 2025: 220Jan 2026: 231Jan2026Feb 2026: 172Mar 2026: 294Apr 2026: 390May 2026: 309Jun 2026: 318Jul 2026: 360JulAug 2026: 361Sep 2026: 310
The same numbers as a table
MonthPermits
Oct 2024355
Nov 2024268
Dec 2024211
Jan 2025194
Feb 2025178
Mar 2025271
Apr 2025363
May 2025338
Jun 2025304
Jul 2025330
Aug 2025292
Sep 2025314
Oct 2025359
Nov 2025278
Dec 2025220
Jan 2026231
Feb 2026172
Mar 2026294
Apr 2026390
May 2026309
Jun 2026318
Jul 2026360
Aug 2026361
Sep 2026310

Download this table (CSV)

When each kind of work is filed

Permits by calendar month, 100 = an average month (the thin line), October 2024 through September 2026. Kinds of work do not all peak together. Each month is counted twice (once a year), so one unusual month still moves these numbers.

Garages, sheds & shade structures

1,760 permits · busiest April, quietest January

January: 40 (100 = an average month)February: 44 (100 = an average month)March: 82 (100 = an average month)April: 149 (100 = an average month)149May: 139 (100 = an average month)June: 130 (100 = an average month)July: 135 (100 = an average month)August: 121 (100 = an average month)September: 117 (100 = an average month)October: 128 (100 = an average month)November: 76 (100 = an average month)December: 40 (100 = an average month)JFMAMJJASOND

New homes

1,752 permits · busiest May, quietest January

January: 60 (100 = an average month)February: 73 (100 = an average month)March: 112 (100 = an average month)April: 97 (100 = an average month)May: 129 (100 = an average month)129June: 91 (100 = an average month)July: 108 (100 = an average month)August: 119 (100 = an average month)September: 96 (100 = an average month)October: 116 (100 = an average month)November: 110 (100 = an average month)December: 90 (100 = an average month)JFMAMJJASOND

Remodels & repairs

1,372 permits · busiest October, quietest February

January: 98 (100 = an average month)February: 65 (100 = an average month)March: 108 (100 = an average month)April: 118 (100 = an average month)May: 85 (100 = an average month)June: 88 (100 = an average month)July: 103 (100 = an average month)August: 113 (100 = an average month)September: 98 (100 = an average month)October: 132 (100 = an average month)132November: 101 (100 = an average month)December: 90 (100 = an average month)JFMAMJJASOND

Demolition

272 permits · busiest April, quietest February

January: 57 (100 = an average month)February: 49 (100 = an average month)March: 88 (100 = an average month)April: 163 (100 = an average month)163May: 79 (100 = an average month)June: 88 (100 = an average month)July: 115 (100 = an average month)August: 101 (100 = an average month)September: 159 (100 = an average month)October: 137 (100 = an average month)November: 115 (100 = an average month)December: 49 (100 = an average month)JFMAMJJASOND

Additions

227 permits · busiest August, quietest February

January: 58 (100 = an average month)February: 42 (100 = an average month)March: 79 (100 = an average month)April: 127 (100 = an average month)May: 90 (100 = an average month)June: 127 (100 = an average month)July: 116 (100 = an average month)August: 153 (100 = an average month)153September: 137 (100 = an average month)October: 111 (100 = an average month)November: 95 (100 = an average month)December: 63 (100 = an average month)JFMAMJJASOND

Pools & spas

160 permits · busiest July, quietest December

January: 38 (100 = an average month)February: 45 (100 = an average month)March: 105 (100 = an average month)April: 180 (100 = an average month)May: 135 (100 = an average month)June: 158 (100 = an average month)July: 202 (100 = an average month)202August: 98 (100 = an average month)September: 82 (100 = an average month)October: 38 (100 = an average month)November: 90 (100 = an average month)December: 30 (100 = an average month)JFMAMJJASOND

Roofing

124 permits · busiest July, quietest January

January: 10 (100 = an average month)February: 48 (100 = an average month)March: 116 (100 = an average month)April: 165 (100 = an average month)May: 145 (100 = an average month)June: 58 (100 = an average month)July: 174 (100 = an average month)174August: 135 (100 = an average month)September: 165 (100 = an average month)October: 97 (100 = an average month)November: 58 (100 = an average month)December: 29 (100 = an average month)JFMAMJJASOND
The same numbers as a table
Kind of workJanFebMarAprMayJunJulAugSepOctNovDec
Garages, sheds & shade structures4044821491391301351211171287640
New homes607311297129911081199611611090
Remodels & repairs986510811885881031139813210190
Demolition574988163798811510115913711549
Additions584279127901271161531371119563
Pools & spas38451051801351582029882389030
Roofing104811616514558174135165975829

Download this table (CSV)

Homes and everything else

How the city classed each permit. Other covers commercial buildings, signs, towers and similar work.

Permit classPermitsShareLast 12 mo
Homes (residential)5,65781%2,901
Other1,36319%701

Download this table (CSV)

By ZIP code

The 10 ZIP codes with the most permits, counted at the property's ZIP code. A ZIP code can cross into a city that runs its own permit office; only the city's permits are counted.

ZIP codePermitsShareTop kind of work
685161,31319%New homes (437)
685216139%Garages, sheds & shade structures (191)
685025007%Remodels & repairs (176)
685064917%Garages, sheds & shade structures (186)
685234546%New homes (284)
685103775%Remodels & repairs (116)
685073655%Garages, sheds & shade structures (115)
685263485%New homes (205)
685053235%Garages, sheds & shade structures (99)
685203195%New homes (206)

All 12 ZIP codes with 250+ permits →

Download this table (CSV)

How Lincoln compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: Lancaster County Assessor, PublicAnalytics map service: Permits layer, read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out. The file carries no usable permit status, so it can't say which permits were finished, so no finished share is shown.

Building permits for properties with a Lincoln address, as logged by the Lancaster County Assessor. Lincoln Building & Safety issues permits for the city and the county around it, so a few rural properties with a Lincoln mailing address are included. The small towns of Lancaster County (Waverly, Hickman, Bennet, Firth and others) are not counted. Only permits that can change a property's assessed value are logged: no stand-alone electrical, plumbing or HVAC permits.

  • The Assessor's permit log names no contractor, so there are no contractor lists, rankings or firm pages for Lincoln.
  • The Assessor logs only permits that can change assessed value: new homes, additions, remodels, decks, sheds, garages, pools, demolitions and some roofs. Electrical, plumbing and HVAC permits are not in the log, and re-roofs are mostly missing.
  • The log's status is the Assessor's own review, not a final inspection, and it has no final dates, so we show no finished share and no time to final; every permit is listed as open.
  • The value is the amount on the permit as logged by the Assessor.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Lincoln, NE building permit statistics", https://contractorrecords.com/lincoln/permit-statistics, data through September 2026, from the City of Lincoln Building & Safety Department (as logged by the Lancaster County Assessor) building-permit records.

Link to a table: By kind of work · By year · By month · When each kind of work is filed · Homes and everything else · By ZIP code.

Download the tables (CSV): Permits by kind of work · Permits by year · Permits by month · Permits by calendar month (index) · Homes and other permits · Permits by ZIP code.

Common questions

  • How many building permits does Lincoln issue a year?About 3,510 a year in Lincoln: 7,020 permits over 24 months, October 2024 through September 2026. 3,602 permits in the last 12 months (Oct 2025–Sep 2026), 5% more than the 3,418 in the 12 months before.
  • Are building permits up or down in Lincoln?3,602 permits in the last 12 months (Oct 2025–Sep 2026), 5% more than the 3,418 in the 12 months before. New home permits grew most (838 to 914); demolition permits fell most (147 to 125).
  • What is the busiest month for permits in Lincoln?April, counting every kind of work (129 against an average month of 100). February is the quietest (60). Each kind of work has its own season; the charts above show them.
  • What share of Lincoln permits are for homes?81%: 5,657 of the 7,020 permits issued October 2024 through September 2026 were residential permits.