Contractor Records
Home › Adams County › Permit statistics

Unincorporated Adams County, CO building permit statistics

Data through September 2026 · updated 23 Oct 2026

6,247 building permits issued in unincorporated Adams County, October 2024 through September 2026: about 3,124 a year. The biggest kind of work is roofing, with 1,869. 2,761 permits in the last 12 months (Oct 2025–Sep 2026), 21% fewer than the 3,486 in the 12 months before. 85% were permits for homes. The busiest month for permits is July.

6,247permits issued
2,761last 12 months
−21%vs the 12 months before
85%for homes
Julbusiest month
Sep 2026records through

By kind of work

Permits issued October 2024 through September 2026. Last 12 months is Oct 2025–Sep 2026; the 12 months before is Oct 2024–Sep 2025. Homes is the share issued as residential permits. Busiest month is the calendar month with the most permits on average.

Kind of workPermitsShareLast 12 mo12 mo beforeChangeHomesBusiest month
Roofing1,86930%6521,217−46%95%July
HVAC1,16919%671498+35%91%July
Electrical69311%340353−4%90%September
Remodels & repairs5499%273276−1%100%October
New homes3275%108219−51%100%April
Plumbing3205%185135+37%97%September
Garages, sheds & shade structures2875%111176−37%100%March
Solar2564%77179−57%40%August
Fences & walls1623%8280+2%83%May
Other4798%198281−30%8%May

Fewer than 100 permits, so no row: demolition (88), additions (20), pools & spas (16), ADUs & casitas (12).

Download this table (CSV)

By year

Permits issued in each calendar year of the window. Per year scales a part year to 12 months.

YearMonthsPermitsPer year
2024 (from October)38853,540
2025123,3213,321
2026 (through September)92,0412,721

Download this table (CSV)

By month

Permits issued each month, October 2024 through September 2026. The tallest bar is the busiest month on file.

Oct 2024: 408Oct2024Nov 2024: 254Dec 2024: 223Jan 2025: 236Jan2025Feb 2025: 207Mar 2025: 252Apr 2025: 211May 2025: 253Jun 2025: 244Jul 2025: 532JulAug 2025: 338Sep 2025: 328Oct 2025: 285Nov 2025: 272Dec 2025: 163Jan 2026: 200Jan2026Feb 2026: 226Mar 2026: 232Apr 2026: 174May 2026: 250Jun 2026: 230Jul 2026: 267JulAug 2026: 242Sep 2026: 220
The same numbers as a table
MonthPermits
Oct 2024408
Nov 2024254
Dec 2024223
Jan 2025236
Feb 2025207
Mar 2025252
Apr 2025211
May 2025253
Jun 2025244
Jul 2025532
Aug 2025338
Sep 2025328
Oct 2025285
Nov 2025272
Dec 2025163
Jan 2026200
Feb 2026226
Mar 2026232
Apr 2026174
May 2026250
Jun 2026230
Jul 2026267
Aug 2026242
Sep 2026220

Download this table (CSV)

When each kind of work is filed

Permits by calendar month, 100 = an average month (the thin line), October 2024 through September 2026. Kinds of work do not all peak together. Each month is counted twice (once a year), so one unusual month still moves these numbers.

Roofing

1,869 permits · busiest July, quietest February

January: 50 (100 = an average month)February: 46 (100 = an average month)March: 68 (100 = an average month)April: 54 (100 = an average month)May: 82 (100 = an average month)June: 80 (100 = an average month)July: 247 (100 = an average month)247August: 112 (100 = an average month)September: 120 (100 = an average month)October: 180 (100 = an average month)November: 107 (100 = an average month)December: 55 (100 = an average month)JFMAMJJASOND

HVAC

1,169 permits · busiest July, quietest April

January: 109 (100 = an average month)February: 83 (100 = an average month)March: 82 (100 = an average month)April: 62 (100 = an average month)May: 93 (100 = an average month)June: 98 (100 = an average month)July: 141 (100 = an average month)141August: 136 (100 = an average month)September: 89 (100 = an average month)October: 123 (100 = an average month)November: 106 (100 = an average month)December: 79 (100 = an average month)JFMAMJJASOND

Electrical

693 permits · busiest September, quietest May

January: 78 (100 = an average month)February: 81 (100 = an average month)March: 90 (100 = an average month)April: 104 (100 = an average month)May: 76 (100 = an average month)June: 99 (100 = an average month)July: 111 (100 = an average month)August: 128 (100 = an average month)September: 130 (100 = an average month)130October: 111 (100 = an average month)November: 111 (100 = an average month)December: 81 (100 = an average month)JFMAMJJASOND

Remodels & repairs

549 permits · busiest October, quietest April

January: 85 (100 = an average month)February: 131 (100 = an average month)March: 92 (100 = an average month)April: 63 (100 = an average month)May: 107 (100 = an average month)June: 94 (100 = an average month)July: 98 (100 = an average month)August: 107 (100 = an average month)September: 109 (100 = an average month)October: 133 (100 = an average month)133November: 90 (100 = an average month)December: 90 (100 = an average month)JFMAMJJASOND

New homes

327 permits · busiest April, quietest August

January: 84 (100 = an average month)February: 139 (100 = an average month)March: 139 (100 = an average month)April: 206 (100 = an average month)206May: 128 (100 = an average month)June: 103 (100 = an average month)July: 92 (100 = an average month)August: 29 (100 = an average month)September: 37 (100 = an average month)October: 77 (100 = an average month)November: 59 (100 = an average month)December: 106 (100 = an average month)JFMAMJJASOND

Plumbing

320 permits · busiest September, quietest April

January: 120 (100 = an average month)February: 105 (100 = an average month)March: 90 (100 = an average month)April: 52 (100 = an average month)May: 64 (100 = an average month)June: 68 (100 = an average month)July: 116 (100 = an average month)August: 109 (100 = an average month)September: 150 (100 = an average month)150October: 116 (100 = an average month)November: 112 (100 = an average month)December: 98 (100 = an average month)JFMAMJJASOND

Garages, sheds & shade structures

287 permits · busiest March, quietest August

January: 79 (100 = an average month)February: 75 (100 = an average month)March: 176 (100 = an average month)176April: 96 (100 = an average month)May: 92 (100 = an average month)June: 130 (100 = an average month)July: 100 (100 = an average month)August: 63 (100 = an average month)September: 100 (100 = an average month)October: 88 (100 = an average month)November: 113 (100 = an average month)December: 88 (100 = an average month)JFMAMJJASOND

Solar

256 permits · busiest August, quietest May

January: 75 (100 = an average month)February: 136 (100 = an average month)March: 80 (100 = an average month)April: 75 (100 = an average month)May: 61 (100 = an average month)June: 66 (100 = an average month)July: 80 (100 = an average month)August: 169 (100 = an average month)169September: 141 (100 = an average month)October: 169 (100 = an average month)November: 84 (100 = an average month)December: 66 (100 = an average month)JFMAMJJASOND
The same numbers as a table
Kind of workJanFebMarAprMayJunJulAugSepOctNovDec
Roofing50466854828024711212018010755
HVAC10983826293981411368912310679
Electrical788190104769911112813011111181
Remodels & repairs85131926310794981071091339090
New homes841391392061281039229377759106
Plumbing1201059052646811610915011611298
Garages, sheds & shade structures79751769692130100631008811388
Solar7513680756166801691411698466

Download this table (CSV)

Homes and everything else

How the county classed each permit. Other covers commercial buildings, signs, towers and similar work.

Permit classPermitsShareLast 12 mo
Homes (residential)5,31785%2,404
Other93015%357

Download this table (CSV)

How Adams County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Permit statistics for other places in Denver and Boulder. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Adams County, Building Permits Eye On Adams (ArcGIS layer), read 23 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out. The county's layer leaves most permits marked Permit Issued after the work is done, so no finished share is shown.

Permits the Adams County Building Division issues for unincorporated land only, such as Welby, Sherrelwood, Berkeley, Twin Lakes, Strasburg and the rural east. Thornton, Westminster, Commerce City, Brighton, Northglenn, Federal Heights, Arvada and Aurora issue their own permits and are not in this file.

  • The county's permit layer names no contractor, so there are no contractor lists, rankings or firm pages for Adams County.
  • The layer has no issue date, so a permit is dated by the day its case was opened; cases still in review or waiting on fees are not counted.
  • There is no job value, no final inspection date and no ZIP code in the layer, so we show no costs, no time to final and no ZIP pages.
  • The type of work is blank on about a third of permits (mostly online re-roof and furnace or air-conditioner permits); for those the kind of work is read from the permit's description.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Unincorporated Adams County, CO building permit statistics", https://contractorrecords.com/adams-county/permit-statistics, data through September 2026, from Adams County Community & Economic Development building-permit records.

Link to a table: By kind of work · By year · By month · When each kind of work is filed · Homes and everything else.

Download the tables (CSV): Permits by kind of work · Permits by year · Permits by month · Permits by calendar month (index) · Homes and other permits.

Common questions

  • How many building permits does Adams County issue a year?About 3,124 a year in unincorporated Adams County: 6,247 permits over 24 months, October 2024 through September 2026. 2,761 permits in the last 12 months (Oct 2025–Sep 2026), 21% fewer than the 3,486 in the 12 months before.
  • Are building permits up or down in Adams County?2,761 permits in the last 12 months (Oct 2025–Sep 2026), 21% fewer than the 3,486 in the 12 months before. HVAC permits grew most (498 to 671); roofing permits fell most (1,217 to 652).
  • What is the busiest month for permits in Adams County?July, counting every kind of work (153 against an average month of 100). April is the quietest (74). Each kind of work has its own season; the charts above show them.
  • What share of Adams County permits are for homes?85%: 5,317 of the 6,247 permits issued October 2024 through September 2026 were residential permits.