Data through September 2026 · updated 20 Oct 2026

72,744 building permits issued in Baltimore County, October 2024 through September 2026: about 36,372 a year. The biggest kind of work is electrical, with 25,685. 36,489 permits in the last 12 months (Oct 2025–Sep 2026), about the same as the 36,255 in the 12 months before. 84% were permits for homes. The busiest month for permits is October.

72,744permits issued
36,489last 12 months
+1%vs the 12 months before
84%for homes
Octbusiest month
Sep 2026records through

By kind of work

Permits issued October 2024 through September 2026. Last 12 months is Oct 2025–Sep 2026; the 12 months before is Oct 2024–Sep 2025. Homes is the share issued as residential permits. Busiest month is the calendar month with the most permits on average.

Kind of workPermitsShareLast 12 mo12 mo beforeChangeHomesBusiest month
Electrical25,68535%13,12112,564+4%82%July
Plumbing22,47331%10,79011,683−8%90%March
HVAC5,3367%2,8632,473+16%95%April
Garages, sheds & shade structures2,9634%1,4281,535−7%100%July
Fences & walls2,8194%1,3251,494−11%94%May
New homes2,3083%1,381927+49%100%November
Solar1,4002%762638+19%94%September
Remodels & repairs1,1782%618560+10%100%April
Additions1,0441%496548−9%100%October
Demolition299under 1%140159−12%72%October
Pools & spas251under 1%122129−5%100%June
Other6,8599%3,3843,475−3%39%October

Fewer than 100 permits, so no row: roofing (91), ADUs & casitas (38).

Download this table (CSV)

By year

Permits issued in each calendar year of the window. Per year scales a part year to 12 months.

YearMonthsPermitsPer year
2024 (from October)38,94035,760
20251236,65636,656
2026 (through September)927,14836,197

Download this table (CSV)

By month

Permits issued each month, October 2024 through September 2026. The tallest bar is the busiest month on file.

Oct 2024: 3,334Oct2024Nov 2024: 2,701Dec 2024: 2,905Jan 2025: 2,308Jan2025Feb 2025: 2,533Mar 2025: 2,732Apr 2025: 3,105May 2025: 3,204Jun 2025: 3,346Jul 2025: 3,717JulAug 2025: 3,395Sep 2025: 2,975Oct 2025: 3,634Nov 2025: 2,864Dec 2025: 2,843Jan 2026: 2,474Jan2026Feb 2026: 2,648Mar 2026: 3,290Apr 2026: 3,472May 2026: 3,197Jun 2026: 3,210Jul 2026: 3,178JulAug 2026: 3,001Sep 2026: 2,678
The same numbers as a table
MonthPermits
Oct 20243,334
Nov 20242,701
Dec 20242,905
Jan 20252,308
Feb 20252,533
Mar 20252,732
Apr 20253,105
May 20253,204
Jun 20253,346
Jul 20253,717
Aug 20253,395
Sep 20252,975
Oct 20253,634
Nov 20252,864
Dec 20252,843
Jan 20262,474
Feb 20262,648
Mar 20263,290
Apr 20263,472
May 20263,197
Jun 20263,210
Jul 20263,178
Aug 20263,001
Sep 20262,678

Download this table (CSV)

When each kind of work is filed

Permits by calendar month, 100 = an average month (the thin line), October 2024 through September 2026. Kinds of work do not all peak together. Each month is counted twice (once a year), so one unusual month still moves these numbers.

Electrical

25,685 permits · busiest July, quietest November

January: 85 (100 = an average month)February: 88 (100 = an average month)March: 91 (100 = an average month)April: 112 (100 = an average month)May: 107 (100 = an average month)June: 117 (100 = an average month)July: 125 (100 = an average month)125August: 102 (100 = an average month)September: 90 (100 = an average month)October: 102 (100 = an average month)November: 84 (100 = an average month)December: 98 (100 = an average month)JFMAMJJASOND

Plumbing

22,473 permits · busiest March, quietest January

January: 79 (100 = an average month)February: 85 (100 = an average month)March: 121 (100 = an average month)121April: 106 (100 = an average month)May: 98 (100 = an average month)June: 101 (100 = an average month)July: 107 (100 = an average month)August: 111 (100 = an average month)September: 95 (100 = an average month)October: 116 (100 = an average month)November: 92 (100 = an average month)December: 90 (100 = an average month)JFMAMJJASOND

HVAC

5,336 permits · busiest April, quietest September

January: 78 (100 = an average month)February: 109 (100 = an average month)March: 92 (100 = an average month)April: 127 (100 = an average month)127May: 100 (100 = an average month)June: 105 (100 = an average month)July: 113 (100 = an average month)August: 66 (100 = an average month)September: 59 (100 = an average month)October: 115 (100 = an average month)November: 112 (100 = an average month)December: 124 (100 = an average month)JFMAMJJASOND

Garages, sheds & shade structures

2,963 permits · busiest July, quietest January

January: 51 (100 = an average month)February: 72 (100 = an average month)March: 79 (100 = an average month)April: 86 (100 = an average month)May: 116 (100 = an average month)June: 125 (100 = an average month)July: 156 (100 = an average month)156August: 127 (100 = an average month)September: 103 (100 = an average month)October: 111 (100 = an average month)November: 78 (100 = an average month)December: 97 (100 = an average month)JFMAMJJASOND

Fences & walls

2,819 permits · busiest May, quietest January

January: 51 (100 = an average month)February: 60 (100 = an average month)March: 99 (100 = an average month)April: 135 (100 = an average month)May: 160 (100 = an average month)160June: 104 (100 = an average month)July: 101 (100 = an average month)August: 136 (100 = an average month)September: 77 (100 = an average month)October: 129 (100 = an average month)November: 74 (100 = an average month)December: 72 (100 = an average month)JFMAMJJASOND

New homes

2,308 permits · busiest November, quietest December

January: 75 (100 = an average month)February: 88 (100 = an average month)March: 80 (100 = an average month)April: 73 (100 = an average month)May: 79 (100 = an average month)June: 85 (100 = an average month)July: 126 (100 = an average month)August: 124 (100 = an average month)September: 112 (100 = an average month)October: 135 (100 = an average month)November: 154 (100 = an average month)154December: 70 (100 = an average month)JFMAMJJASOND

Solar

1,400 permits · busiest September, quietest February

January: 66 (100 = an average month)February: 63 (100 = an average month)March: 85 (100 = an average month)April: 111 (100 = an average month)May: 89 (100 = an average month)June: 84 (100 = an average month)July: 82 (100 = an average month)August: 113 (100 = an average month)September: 169 (100 = an average month)169October: 148 (100 = an average month)November: 91 (100 = an average month)December: 99 (100 = an average month)JFMAMJJASOND

Remodels & repairs

1,178 permits · busiest April, quietest January

January: 76 (100 = an average month)February: 80 (100 = an average month)March: 87 (100 = an average month)April: 129 (100 = an average month)129May: 116 (100 = an average month)June: 109 (100 = an average month)July: 98 (100 = an average month)August: 94 (100 = an average month)September: 108 (100 = an average month)October: 108 (100 = an average month)November: 96 (100 = an average month)December: 99 (100 = an average month)JFMAMJJASOND
The same numbers as a table
Kind of workJanFebMarAprMayJunJulAugSepOctNovDec
Electrical858891112107117125102901028498
Plumbing798512110698101107111951169290
HVAC78109921271001051136659115112124
Garages, sheds & shade structures517279861161251561271031117897
Fences & walls516099135160104101136771297472
New homes75888073798512612411213515470
Solar6663851118984821131691489199
Remodels & repairs76808712911610998941081089699

Download this table (CSV)

Homes and everything else

How the county classed each permit. Other covers commercial buildings, signs, towers and similar work.

Permit classPermitsShareLast 12 mo
Homes (residential)61,16384%30,841
Other11,58116%5,648

Download this table (CSV)

How many permits get finished

Permits issued Oct 2024–Sep 2025, so each has had at least 12 months to reach a final. Finished means the county recorded a final inspection or marked it complete; expired means it lapsed without one.

StatusPermitsShare
Finished19,01752.5%
Still open17,07847.1%
Expired1600.4%

Download this table (CSV)

By ZIP code

The 10 ZIP codes with the most permits, counted at the property's ZIP code. A ZIP code can cross into a city that runs its own permit office; only the county's permits are counted.

ZIP codePermitsShareTop kind of work
212205,3297%Electrical (1,988)
212444,7537%Plumbing (1,477)
212284,1856%Electrical (1,501)
210934,0826%Electrical (1,478)
211174,0746%Electrical (1,559)
212083,6905%Electrical (1,279)
212223,6275%Electrical (1,274)
212343,5835%Plumbing (1,277)
211362,8984%Electrical (1,131)
212372,6414%Electrical (955)

All 37 ZIP codes with 250+ permits →

Download this table (CSV)

How Baltimore County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Permit statistics for other places in Baltimore. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Baltimore County GIS, Active Development map service: Cityworks Permits, Electrical Permits, Plumbing Permits and Gas Permits layers, read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, electrical, plumbing and gas permits issued by Baltimore County Permits, Approvals and Inspections, which covers the whole county (it has no incorporated towns): Towson, Catonsville, Dundalk, Essex, Parkville, Pikesville, Owings Mills, Randallstown, Perry Hall, White Marsh and the rest. Baltimore City is a separate jurisdiction with its own permit office and is not in this file; the few trade permits whose ZIP code lies wholly inside Baltimore City are left out. Grading, storm-water and use-and-occupancy permits are not counted.

  • The county's files name no contractor, so there are no contractor lists, rankings or firm pages for Baltimore County.
  • The files carry no final inspection or completion date, so we show no time to final.
  • Electrical, plumbing and gas permits are marked complete when the county signs them off. Building permits in the county's current system are rarely marked closed, so building work (new homes, decks, fences, additions, remodels, commercial work) almost always shows as open and the finished share mostly reflects trade permits.
  • The estimated cost is filled on building permits only; trade permits carry no job value.
  • Gas permits for furnaces and boilers count as HVAC; gas permits for water heaters, ranges, dryers and gas lines count as plumbing. The county publishes no separate mechanical permits, so heat pumps and air conditioners appear under electrical.
  • Solar counts come from solar building permits; the matching electrical permit for the same job counts under electrical. Fire-sprinkler permits count as other.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Baltimore County, MD building permit statistics", https://contractorrecords.com/baltimore-county/permit-statistics, data through September 2026, from Baltimore County Permits, Approvals and Inspections building-permit records.

Link to a table: By kind of work · By year · By month · When each kind of work is filed · Homes and everything else · How many get finished · By ZIP code.

Download the tables (CSV): Permits by kind of work · Permits by year · Permits by month · Permits by calendar month (index) · Homes and other permits · Finished, open and expired · Permits by ZIP code.

Common questions

  • How many building permits does Baltimore County issue a year?About 36,372 a year in Baltimore County: 72,744 permits over 24 months, October 2024 through September 2026. 36,489 permits in the last 12 months (Oct 2025–Sep 2026), about the same as the 36,255 in the 12 months before.
  • Are building permits up or down in Baltimore County?36,489 permits in the last 12 months (Oct 2025–Sep 2026), about the same as the 36,255 in the 12 months before. Electrical permits grew most (12,564 to 13,121); plumbing permits fell most (11,683 to 10,790).
  • What is the busiest month for permits in Baltimore County?October, counting every kind of work (115 against an average month of 100). January is the quietest (79). Each kind of work has its own season; the charts above show them.