The rule in 3 cities, with their permit counts
Rules from each city's own page, read 23 October 2026. Counts are driveway permits in the city's file over three years to September 2026 (Cape Coral's file starts January 2025, and its count includes pavers and slabs); "usual days" is the typical time from issue to final inspection.
| City | The rule | Driveway permits | Usual filed value | Usual days to final |
|---|---|---|---|---|
| Austin, TX | Exempt: "A sidewalk, driveway, or concrete flatwork that is not located in the public right-of-way" | 2,137 (driveways and sidewalks) | — | 69 |
| Naperville, IL | "Installing or replacing a driveway, driveway approach or sidewalk" needs a permit; owners submit the application | 1,175 (driveways and sidewalks) | $4,498 | 99 |
| Cape Coral, FL | Driveway is on its map of common permits; even a shed's "concrete slab ... must be permitted separately" | 745 (driveways, pavers, slabs) | $7,500 | 57 |
Nine more departments, without driveway counts in our file:
| Building department | The rule |
|---|---|
| Cary, NC | "Residential driveways and curb cuts" need a permit |
| San Diego County (unincorporated) | "No person shall construct a residential driveway" without a permit, unless it is part of a new house's permit |
| Saint Paul, MN | "Residential sidewalks and driveways do not require a building permit. However, a zoning review is required for new or expanded driveways." |
| Pikes Peak Regional (Colorado Springs) | Exempt: "Private sidewalks, driveways, and platforms supported directly upon grade" |
| Seattle, WA | Exempt if "less than 18 inches above grade and not over a basement or other building story" |
| Bellevue, WA | Pavers need no permit below the earthwork thresholds; a clearing and grading permit "may be required" for a new or replaced driveway, and a new or moved driveway "also requires a right of way permit" |
| Elk Grove, CA | Exempt: "Sidewalks and driveways not more than 30 inches" above adjacent grade |
| Anaheim, CA | Exempt: "Platforms, walks and driveways not more than 30 inches above grade" |
| Palo Alto, CA | Exempt up to 30 inches above grade, not over a basement and not part of an accessible route |
Where the street changes the answer
The building code stops at your property line; the apron does not. Naperville spells it out: "The driveway apron, the public sidewalk and the curb and gutter are all located in the public right-of-way," and work there needs a "Work in the Right-of-Way Worksheet". A decorative apron of brick, stamped or exposed-aggregate concrete needs a "Right-of-Way Encroachment Agreement" on top. Naperville also caps the apron at 24 feet wide at the street and the driveway at 20 feet at the property line.
So a contractor who says "driveways don't need permits" can be right about the slab in Austin or Saint Paul and wrong about the curb cut.
What happens if you skip it
- Colorado Springs area: where a permit is required, Pikes Peak Regional issues a stop work order and files a "Certificate of Alleged Non-compliance" with the county Clerk and Recorder.
- Naperville: decorative materials placed in the right-of-way are there "at the risk of the owner" and may be disturbed by others working in it.
More in permit vs no permit.
Who pulls it
The paving contractor, or you. Naperville names property owners as the ones who submit the driveway application. Where the apron is involved, ask whether the contractor files Naperville-style right-of-way paperwork itself or leaves it to you, before the old slab comes out.
How long it takes
The usual driveway permit closed in 57 days in Cape Coral and 69 in Austin, against 99 in Naperville. Austin's and Cape Coral's finish: 98.8% and 98.1% of permits a year or more old reached a final, against 76.5% in Naperville.
Check it in five minutes
- Mark where your lot ends; the apron, public sidewalk and curb are usually the city's.
- If the driveway changes size, shape or location, expect a zoning or survey step (Saint Paul, Naperville).
- Ask the contractor which permits it pulls: driveway, right-of-way or curb cut, and grading.
See every Naperville driveway contractor by permits filed →
What this does not tell you
We read 12 departments' rules. HOA rules and stormwater limits on paved area are separate. A driveway poured under an exemption leaves no record, so our counts understate how many were built, and Austin's and Naperville's include sidewalks.
How we know this
Rules are quoted from the pages under Sources, read 23 October 2026. Permit counts, filed values, usual days to final and finished shares come from each city's permit file over the three years ending September 2026 (Cape Coral from January 2025). "Usual days" is the median from issue to final inspection; "reached a final" counts permits a year or more old.
Numbers come from City of Austin issued construction permits; City of Naperville building permits (the current permit system plus the city's older records); City of Cape Coral building permits (the city's open permit table starts January 2025), data through October 17, 2026. Nobody paid to be on this page and nobody can.
Questions
- Do I need a permit to replace a driveway in the same place?
In Naperville, yes: 'Installing or replacing a driveway' is on its permit list, though a same-location replacement skips the plat of survey. In Austin, Saint Paul and the Pikes Peak region, a driveway entirely on private land needs no building permit, but the apron at the street still falls under right-of-way rules.
- Do I need a permit to widen a driveway?
Usually some approval, even where the slab is exempt. Saint Paul says 'a zoning review is required for new or expanded driveways', Naperville wants the new pavement drawn on a plat of survey, and Bellevue requires a right-of-way permit for a new driveway or one that changes location.
- Do pavers or gravel need a permit?
Bellevue says a permit is not required for driveway or garden pavers unless the earthwork passes its clearing-and-grading thresholds (for landscaping: 50 cubic yards of excavation or fill, or 1,000 square feet of disturbance). Naperville treats paver accents up to 24 inches beside the driveway as landscaping; wider than that, they count as a walkway or patio and need a permit.
- How long does a driveway permit take?
The usual driveway permit reached its final inspection in 57 days in Cape Coral, 69 in Austin and 99 in Naperville.
- How much does a permitted driveway cost?
The usual filed value on a driveway permit was $4,498 in Naperville and $7,500 in Cape Coral, where the count also includes pavers and slabs. Filed values are what the contractor wrote on the application.
Build your own list
Every firm with that kind of permit on record. Pick what you value. The list moves.
Related guides
- Do I need a driveway permit in Austin? The right-of-way line, the DS permit and the $220 review fee
- Do I need a driveway permit in Naperville? The concrete season, width limits, decorative aprons and the $88 fee
- Do I need a permit for a pool? Yes for in-ground: the rule in 13 cities, and how long they take
- Do I need a driveway permit in Greensboro? Yes, for access to a City street, and it closes in about a week
- Do I need a plumbing permit in Sacramento? Online minor permits, the fee parts and 8,247 permits
- Do I need an electrical permit in San Antonio? The licensed-contractor rule, fees and 15,456 permits
For one city
- Work Exempt from Building Permits — City of Austin Development Services (accessed 2026-10-23)
- Guide to Building Permits (rev. 10/31/2022) — City of Naperville, IL (accessed 2026-10-23)
- Application Information: Residential Driveways (rev. 6/26/2023) — City of Naperville, IL (accessed 2026-10-23)
- Driveway Permit — City of Naperville, IL (accessed 2026-10-23)
- Map of Common Permits — City of Cape Coral, FL (accessed 2026-10-23)
- Shed (New DBPR Approved) guideline, rev. January 2026 — City of Cape Coral, FL (accessed 2026-10-23)
- Residential Permits FAQ — Town of Cary, NC (accessed 2026-10-23)
- PDS 110 Building Permit Requirements per Adoptive Ordinance (rev. 01/01/2026) — County of San Diego (accessed 2026-10-23)
- Permit Not Required — Pikes Peak Regional Building Department (accessed 2026-10-23)
- Homeowner Permits — Pikes Peak Regional Building Department (accessed 2026-10-23)
- Do You Need a Permit? — Seattle SDCI (accessed 2026-10-23)
- When is a permit required? — City of Saint Paul DSI (accessed 2026-10-23)
- Work requiring permits — City of Bellevue, WA (accessed 2026-10-23)
- Do I need a building permit? — City of Elk Grove, CA (accessed 2026-10-23)
- When is a Building Permit Required? — City of Anaheim, CA (accessed 2026-10-23)
- Work Exempt from Permit (rev. 05/20/2015) — City of Palo Alto, CA (accessed 2026-10-23)