Compare contractor bids only after each one prices the same written scope, and compare them line by line before you compare totals. California's licence board says to compare bids "based on identical plans, specifications, and scope of work" and "Do not automatically accept the lowest bid" (CSLB). Then check each total against what firms in your city usually file for that job: in Elk Grove, California the middle half of HVAC firms usually file between $11,775 and $16,906, in Cary, North Carolina the middle half of remodel firms between $20,000 and $65,439.

By Contractor Records · data through October 17, 2026

The comparison sheet

Put each bid in a column and fill in these rows. A blank is a question for that bidder, not a point in its favour.

Line What to look for The legal anchor, where there is one
Scope Same drawings, same materials by brand and model, same rooms Vermont requires "A description of the services to be performed and a description of the materials to be used" (§ 5509(b))
Price type Total price, capped, or uncapped time and materials Vermont makes the contract name one (§ 5509(b)); see fixed price vs cost-plus
Total and breakdown Labour, materials, subcontracted trades, permit fee, disposal Ohio requires the "total estimated cost" on jobs over $25,000 (ORC 4722.02)
Allowances Fixtures, tile or cabinets priced as an allowance, not chosen A low allowance makes a bid look cheaper; set them equal across bids
Permit Who pulls it, and whether the fee is in the price The contractor, in its own name; see owner-builder vs contractor
Deposit Within your state's limit California $1,000 or 10%, whichever is less (B&P § 7159.5); Massachusetts and Pennsylvania one-third
Payment schedule Later payments tied to work done and inspections passed —
Dates Estimated start and completion Required in Vermont (§ 5509) and Ohio (4722.02)
Changes How a change order is priced and approved Vermont: "A description of how and when amendments to the contract may be approved and documented"
Licence The number, on the bid Required on the contract in Pennsylvania (§ 517.7)
Insurance A certificate, with the limits Ohio requires a certificate showing at least $250,000 of liability cover over $25,000 (ORC 4722.02)

Massachusetts publishes its own list of required home improvement contract terms (Mass.gov), and Pennsylvania's are in its Home Improvement Consumer Protection Act. If your state has one, use it as the rows.

How far apart bids should be

The Texas Attorney General's advice is that "Most of the legitimate bids will fall into a fairly close range"; the NAIC adds that a bid "much lower than any of the others doesn't mean it's the best deal". The permit file shows what "close" means for different jobs:

City Job Firms filing it Usual filed value Middle half of firms' usual job
Elk Grove, CA HVAC 339 $16,000 $11,775–$16,906
Cary, NC HVAC 372 $9,891 $7,900–$11,693
Wheaton, IL Roofing 295 $15,432 $13,250–$19,850
Elk Grove, CA Roofing 200 $18,350 $14,849–$24,500
Cary, NC Remodel 626 $40,000 $20,000–$65,439
Naperville, IL Remodel 467 $46,300 $25,000–$77,000
Greensboro, NC Addition 167 $66,975 $44,000–$110,000

Replacement jobs sit in tight bands: Elk Grove HVAC firms' usual jobs fall within a few thousand dollars of each other. Three HVAC bids that are $8,000 apart are probably not pricing the same job, and the scope rows will show why. Remodels and additions spread several times wider, so there the scope sheet does most of the work.

After price: compare the record

Two bids can match on every line and still come from very different firms. The permit file adds the line no quote carries: how often the firm's permits reach a final inspection. Among Cary HVAC firms with ten or more permits, the finished share runs from 51.6% at the 10th percentile to 95.4% at the 90th. Open each bidder on your city's compare page, for example Cary HVAC contractors, and add two rows to the sheet: permits for this kind of job, and the share finished.

Check it in five minutes

  1. Copy the table above into a sheet and fill one column per bid.
  2. Mark every blank and send each bidder its list of questions.
  3. Put each total next to the band for your job and city, or on your city's cost page, for example Cary remodel.
  4. Check each licence on the state board; our verification guide links every state's lookup.
  5. Add the finished share from our compare page. Our how many quotes guide covers how many bids to ask for.

Compare Cary HVAC contractors before you ask for bids →

What this does not tell you

Filed values are what contractors told the city, not their contract prices, and some file labour only. The band describes firms' usual jobs, not your house. The legal anchors are from the states named; your state may require different contract terms or none. A finished share measures whether permits were closed, not whether the work was good.

How we know this

Filed values, firm counts and finished shares come from the City of Elk Grove, Town of Cary, City of Wheaton, City of Naperville and City of Greensboro permit files, three-year windows ending September 2026. The band is the 25th to 75th percentile of firms' own median filed values among firms with three or more permits of that type; the finished-share percentiles are over firms with ten or more permits. Contract rules are quoted from 26 V.S.A. § 5509 and ORC 4722.02 (read 22 October 2026), B&P § 7159.5, Mass.gov and the Pennsylvania HICPA (read 20 October 2026); the bidding advice from CSLB, the Texas Attorney General and the NAIC (read 21 October 2026).

Numbers come from Town of Cary building permit applications (issued permits only); City of Elk Grove TRAKiT building permits on single-family, duplex, mobile-home and ADU homes; City of Greensboro building and trade permits; City of Naperville building permits (the current permit system plus the city's older records); City of Wheaton permits on homes (the city's permit application and inspection exports), data through October 17, 2026. Nobody paid to be on this page and nobody can.

Questions

  • How do I compare contractor bids the right way?

    Make every bidder price the same written scope, then lay the bids side by side on the same lines: price type, what is included, permit, deposit, schedule, licence and insurance. Only then compare totals, against the local range: in Cary, North Carolina the middle half of remodel firms usually file jobs between $20,000 and $65,439.

  • What should be included in a contractor's quote?

    At least what your state requires in the contract. Vermont, on jobs over $10,000: the price type, estimated start and completion dates, a description of the work and materials, and how changes are approved (26 V.S.A. § 5509). Ohio, over $25,000: name, address, phone and taxpayer ID, dates, total estimated cost and an insurance certificate (ORC 4722.02). A quote missing these is not ready to compare.

  • Should I take the lowest bid?

    Not automatically, says California's licence board (CSLB). The Texas Attorney General says most legitimate bids 'will fall into a fairly close range' and warns about the low-ball bidder. Ask the lowest bidder what it left out; the usual answer is a line the others included.

  • How can I ensure the best price from a contractor?

    Give every bidder identical drawings and a written scope, ask for a line-item breakdown, and check each total against the local filed range before you negotiate. A bid far outside the middle half of firms in your city, on either side, is the one to question. Then pick on record as well as price: the finished share of firms' permits ranges widely.

  • How far apart should contractor bids be?

    For standard jobs, close. Elk Grove, California HVAC firms usually file jobs between $11,775 and $16,906; Wheaton, Illinois roofing firms between $13,250 and $19,850. For remodels and additions the range is much wider, so differences in scope explain more of the gap.

Build your own list

Every firm with that kind of permit on record. Pick what you value. The list moves.