Data through January 2025 · updated 23 Oct 2026
5,599 building permits issued in the City of Longview, October 2023 through January 2025: about 4,199 a year. The biggest kind of work is electrical, with 1,374. 71% were permits for homes. The busiest month for permits is July.
Permits issued October 2023 through January 2025. Last 12 months on file is Feb 2024–Jan 2025. Homes is the share issued as residential permits. Busiest month is the calendar month with the most permits on average.
| Kind of work | Permits | Share | Last 12 mo | Homes | Busiest month |
|---|---|---|---|---|---|
| Electrical | 1,374 | 25% | 1,136 | 75% | July |
| Plumbing | 1,301 | 23% | 1,034 | 77% | July |
| HVAC | 750 | 13% | 655 | 71% | May |
| Roofing | 609 | 11% | 490 | 87% | June |
| New homes | 337 | 6% | 239 | 100% | December |
| Remodels & repairs | 170 | 3% | 132 | 100% | February |
| Garages, sheds & shade structures | 124 | 2% | 87 | 93% | April |
| Demolition | 119 | 2% | 112 | 79% | September |
| Solar | 112 | 2% | 76 | 100% | February |
| Other | 636 | 11% | 524 | 0% | April |
Fewer than 100 permits, so no row: additions (37), pools & spas (30).
Permits issued in each calendar year of the window. Per year scales a part year to 12 months.
| Year | Months | Permits | Per year |
|---|---|---|---|
| 2023 (from October) | 3 | 804 | 3,216 |
| 2024 | 12 | 4,453 | 4,453 |
| 2025 (through January) | 1 | 342 | 4,104 |
Permits issued each month, October 2023 through January 2025. The tallest bar is the busiest month on file.
| Month | Permits |
|---|---|
| Oct 2023 | 259 |
| Nov 2023 | 254 |
| Dec 2023 | 291 |
| Jan 2024 | 257 |
| Feb 2024 | 373 |
| Mar 2024 | 350 |
| Apr 2024 | 451 |
| May 2024 | 395 |
| Jun 2024 | 460 |
| Jul 2024 | 481 |
| Aug 2024 | 369 |
| Sep 2024 | 339 |
| Oct 2024 | 365 |
| Nov 2024 | 276 |
| Dec 2024 | 337 |
| Jan 2025 | 342 |
Permits by calendar month, 100 = an average month (the thin line), October 2023 through January 2025. Kinds of work do not all peak together. Each month is counted once, so one unusual month moves these numbers.
1,374 permits · busiest July, quietest November
1,301 permits · busiest July, quietest November
750 permits · busiest May, quietest November
609 permits · busiest June, quietest January
337 permits · busiest December, quietest August
170 permits · busiest February, quietest September
124 permits · busiest April, quietest February
119 permits · busiest September, quietest August
| Kind of work | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Electrical | 86 | 127 | 102 | 135 | 112 | 155 | 171 | 115 | 84 | 75 | 66 | 72 |
| Plumbing | 86 | 101 | 93 | 123 | 113 | 128 | 155 | 107 | 85 | 90 | 79 | 93 |
| HVAC | 76 | 102 | 94 | 117 | 158 | 154 | 143 | 141 | 98 | 98 | 58 | 65 |
| Roofing | 59 | 97 | 108 | 116 | 139 | 144 | 105 | 129 | 121 | 117 | 80 | 64 |
| New homes | 135 | 104 | 128 | 128 | 28 | 57 | 71 | 24 | 76 | 69 | 85 | 202 |
| Remodels & repairs | 80 | 132 | 56 | 132 | 85 | 113 | 113 | 94 | 47 | 113 | 89 | 132 |
| Garages, sheds & shade structures | 103 | 65 | 129 | 168 | 65 | 90 | 155 | 103 | 77 | 84 | 90 | 97 |
| Demolition | 20 | 27 | 40 | 134 | 67 | 188 | 108 | 13 | 309 | 128 | 87 | 121 |
How the city classed each permit. Other covers commercial buildings, signs, towers and similar work.
| Permit class | Permits | Share | Last 12 mo |
|---|---|---|---|
| Homes (residential) | 3,983 | 71% | 3,207 |
| Other | 1,616 | 29% | 1,331 |
Permits issued Oct 2023–Jan 2024, so each has had at least 12 months to reach a final. Finished means the city recorded a final inspection or marked it complete. The file doesn't mark permits expired, so a lapsed permit still reads open.
| Status | Permits | Share |
|---|---|---|
| Finished | 410 | 38.6% |
| Still open | 651 | 61.4% |
From our cross-city data studies: the same measure, read the same way, for every city we cover.
Source: City of Longview PermitDashboardData (ArcGIS feature layer), read 23 Oct 2026. We count permits issued October 2023 through January 2025; denied and withdrawn permits are left out.
Building, trade, re-roof, pool, demolition, sign and fire permits the City of Longview Development Services issues inside the city limits. Unincorporated Gregg and Harrison County and neighbouring towns such as White Oak, Kilgore and Hallsville run their own permit offices and are not in this file. Contractor registrations, certificates of occupancy, plan and site reviews and right-of-way permits in the same layer are not counted.
Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →
Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:
Contractor Records, "The City of Longview, TX building permit statistics", https://contractorrecords.com/longview/permit-statistics, data through January 2025, from the City of Longview Development Services Department building-permit records.Link to a table: By kind of work · By year · By month · When each kind of work is filed · Homes and everything else · How many get finished.