Data through September 2026 · updated 19 Oct 2026
2,982 building permits issued in Greenville, October 2024 through September 2026: about 1,491 a year. The biggest kind of work is new homes, with 750. 1,393 permits in the last 12 months (Oct 2025–Sep 2026), 12% fewer than the 1,589 in the 12 months before. 78% were permits for homes. The busiest month for permits is October.
What this file covers: The city publishes building and demolition permits only; electrical, plumbing and mechanical permits are not in the file.
Permits issued October 2024 through September 2026. Last 12 months is Oct 2025–Sep 2026; the 12 months before is Oct 2024–Sep 2025. Homes is the share issued as residential permits. Busiest month is the calendar month with the most permits on average.
| Kind of work | Permits | Share | Last 12 mo | 12 mo before | Change | Homes | Busiest month |
|---|---|---|---|---|---|---|---|
| New homes | 750 | 25% | 297 | 453 | −34% | 100% | October |
| Remodels & repairs | 663 | 22% | 300 | 363 | −17% | 100% | March |
| Additions | 533 | 18% | 286 | 247 | +16% | 100% | August |
| Demolition | 222 | 7% | 103 | 119 | −13% | 77% | October |
| Garages, sheds & shade structures | 135 | 5% | 65 | 70 | −7% | 99% | June |
| Other | 603 | 20% | 319 | 284 | +12% | 0% | March |
Fewer than 100 permits, so no row: roofing (59), ADUs & casitas (8), pools & spas (5), electrical (2), fences & walls (2).
Permits issued in each calendar year of the window. Per year scales a part year to 12 months.
| Year | Months | Permits | Per year |
|---|---|---|---|
| 2024 (from October) | 3 | 403 | 1,612 |
| 2025 | 12 | 1,492 | 1,492 |
| 2026 (through September) | 9 | 1,087 | 1,449 |
Permits issued each month, October 2024 through September 2026. The tallest bar is the busiest month on file.
| Month | Permits |
|---|---|
| Oct 2024 | 172 |
| Nov 2024 | 123 |
| Dec 2024 | 108 |
| Jan 2025 | 119 |
| Feb 2025 | 141 |
| Mar 2025 | 134 |
| Apr 2025 | 126 |
| May 2025 | 136 |
| Jun 2025 | 118 |
| Jul 2025 | 131 |
| Aug 2025 | 129 |
| Sep 2025 | 152 |
| Oct 2025 | 117 |
| Nov 2025 | 87 |
| Dec 2025 | 102 |
| Jan 2026 | 133 |
| Feb 2026 | 91 |
| Mar 2026 | 137 |
| Apr 2026 | 102 |
| May 2026 | 110 |
| Jun 2026 | 107 |
| Jul 2026 | 142 |
| Aug 2026 | 140 |
| Sep 2026 | 125 |
Permits by calendar month, 100 = an average month (the thin line), October 2024 through September 2026. Kinds of work do not all peak together. Each month is counted twice (once a year), so one unusual month still moves these numbers.
750 permits · busiest October, quietest December
663 permits · busiest March, quietest June
533 permits · busiest August, quietest December
222 permits · busiest October, quietest November
135 permits · busiest June, quietest July
| Kind of work | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| New homes | 85 | 77 | 104 | 98 | 104 | 80 | 134 | 110 | 123 | 138 | 86 | 61 |
| Remodels & repairs | 98 | 94 | 121 | 109 | 101 | 76 | 109 | 85 | 98 | 109 | 101 | 100 |
| Additions | 101 | 99 | 117 | 74 | 95 | 119 | 106 | 137 | 122 | 104 | 65 | 61 |
| Demolition | 103 | 114 | 76 | 59 | 114 | 86 | 97 | 114 | 119 | 162 | 49 | 108 |
| Garages, sheds & shade structures | 107 | 107 | 98 | 71 | 107 | 142 | 62 | 116 | 133 | 89 | 107 | 62 |
How the city classed each permit. Other covers commercial buildings, signs, towers and similar work.
| Permit class | Permits | Share | Last 12 mo |
|---|---|---|---|
| Homes (residential) | 2,322 | 78% | 1,052 |
| Other | 660 | 22% | 341 |
Permits issued Oct 2024–Sep 2025, so each has had at least 12 months to reach a final. Finished means the city recorded a final inspection or marked it complete. The file doesn't mark permits expired, so a lapsed permit still reads open.
| Status | Permits | Share |
|---|---|---|
| Finished | 1,107 | 69.7% |
| Still open | 482 | 30.3% |
From our cross-city data studies: the same measure, read the same way, for every city we cover.
Source: City of Greenville GIS, BuildingPermits_PriorTwoYears (InfoHUB MapServer layer 0), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.
Building and demolition permits the City of Greenville Building Codes division issued inside the city limits. Homes with a Greenville mailing address outside the city (Taylors, Berea, Mauldin's edges and the rest of unincorporated Greenville County) get their permits from Greenville County and are not in this file. Electrical, plumbing and mechanical permits are not published and are not counted.
Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →
Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:
Contractor Records, "Greenville, SC building permit statistics", https://contractorrecords.com/greenville-sc/permit-statistics, data through September 2026, from City of Greenville Building Codes building-permit records.Link to a table: By kind of work · By year · By month · When each kind of work is filed · Homes and everything else · How many get finished.
Download the tables (CSV): Permits by kind of work · Permits by year · Permits by month · Permits by calendar month (index) · Homes and other permits · Finished, open and expired.