Do I need a permit to build a new home in McKinney, TX? The builder packet, fees, and how long 3,360 permits took

Yes: every new house in McKinney needs a residential building permit, submitted online with the City's Residential Builder Packet and a sealed foundation letter, at $0.68 per gross square foot plus $100 plan review. McKinney issued 3,360 new-home permits from October 2024 to September 2026, and the usual one issued in the first year reached the City's completion date 195 days later.

By Contractor Records · data through October 19, 2026

What the City requires

The City of McKinney's Residential Builder Packet (read 24 October 2026) covers single-family detached, attached and duplex homes. Applications go online through Citizen Self Service at mckinneytexas.org/css; the City has not taken paper forms since 31 December 2019, and "Incomplete submittals will be rejected."

Submittal Note
Signature verification form, list of builder options, designer's certification letter The form also names the licensed trades (below)
Structural engineer's letter Signed and sealed, certifying the foundation plan
Energy code compliance form and energy report
Site plan Setbacks, easements, driveway and lot details
Architectural and electrical plans; structural plans Foundation, details, ceiling framing, shear walls, roof framing
HOA approval; historic Certificate of Appropriateness If applicable

The signature verification form asks for the TDLR electrical contractor and master electrician, the master plumber licensed by the Texas State Board of Plumbing Examiners (TSBPE), and the TDLR air conditioning and refrigeration contractor, each signed by the license holder. The packet does not say whether an owner can be the builder of record; call Building Inspections at 469-617-4800 before you plan on it.

What it costs

From the City's permit fee schedule, linked from its Fee Schedule page:

Fee Amount
New residential construction $0.68 per gross square foot
Residential plan review $100
Mechanical, electrical, plumbing permits $40 each
Certificate of occupancy (temporary) $100 ($50)
Reinspection: first / second / third or more $50 / $75 / $100

A 2,500 sq ft house comes to $1,700 + $100 + $120 + $100 = $2,020 in City permit fees before water and sewer taps; the builder packet lists those separately (a 1-inch water tap alone is $1,450, effective 1 October 2025). The City notes the fees are set in Appendix A of its Code of Ordinances and can change by ordinance.

The inspection sequence

The builder packet lists the inspections in order:

  1. Pre-construction: initial erosion control.
  2. Temporary pole (if any) and ground plumbing: rough, sewer, water, gas.
  3. Foundation, with a pier letter if applicable.
  4. Frame and electrical rough (foundation and framing letters required), plumbing top-out and mechanical rough, brick ties or pre-stucco.
  5. Flatwork: walks, drives and patios.
  6. Electric and gas meters.
  7. Finals: plumbing and HVAC, then building and electrical.

Before final, the builder uploads to Citizen Self Service a drainage survey no more than 30 days old, a third-party energy report, a termite affidavit, a spray foam letter if used, the irrigation final report and the Water Department's blue tag.

What 3,360 McKinney new-home permits show

Measure McKinney new homes
Issued October 2024 to September 2026 3,360 (80% of the permits in the City's published file)
October 2024 to September 2025 / October 2025 to September 2026 1,982 / 1,378 (−30%)
Detached / attached 3,014 / 346
Reached completion, permits issued October 2024 to September 2025 98.7%
Usual days, issue to completion (middle half) 195 (162–242)
Usual declared value (middle half) $344,928 ($264,096–$399,840)
Busiest / quietest calendar month (index) February (120) / September (59)

A McKinney house usually goes from permit to completion in a little over six months, and three in four finish within 242 days. If a builder quotes a much longer schedule for a standard plan, ask why. The declared value is the builder's figure on the permit, not the sale price. Monthly counts and days are on McKinney new-home permits, the spread on how long permits take in McKinney, totals on McKinney permit statistics, and the rows on browse McKinney permits.

Before you build or buy new

Look up the permit and its inspections in Citizen Self Service (McKinney building permit search), and check the trade licenses on TDLR and TSBPE (how to check a contractor's license in Texas). General rules are in do I need a permit to build a house; costs in new home construction cost.

What this does not tell you

The City's file names no builder, so we cannot rank builders. It has no status column: a permit without a completion date may be under construction, cancelled or lapsed. And it has no ZIP code, so there are no neighborhood counts. Unincorporated Collin County, Allen, Frisco, Prosper and Melissa permit their own homes.

How we know this

Submittals, licensing and inspections are from the City of McKinney's Residential Builder Packet; fees from the City's Permit Fees schedule linked from its Fee Schedule page, read 24 October 2026. Our counts are the City's Snapshotv2 Residential Permits layer, read 19 October 2026: new single-family permits issued October 2024 to September 2026; days run from issue to the City's completion date.

Numbers come from public permit records in 57 cities, data through October 19, 2026. Nobody paid to be on this page and nobody can.

Questions

  • How much is a building permit for a new house in McKinney?

    $0.68 per gross square foot under the City's permit fee schedule, so about $1,700 for a 2,500 sq ft house, plus a $100 residential plan review fee, $40 each for the mechanical, electrical and plumbing permits and $100 for the certificate of occupancy. Water and sewer tap fees are separate.

  • How long does it take to build a house in McKinney?

    The usual new-home permit issued October 2024 to September 2025 reached the City's completion date 195 days after issue; the middle half took 162 to 242 days. That is roughly the build time, not counting plan review before the permit.

  • Who can do the electrical and plumbing on a new McKinney house?

    The City's builder packet asks for a TDLR-licensed electrical contractor and master electrician, a master plumber licensed by the Texas State Board of Plumbing Examiners, and a TDLR air conditioning contractor, each signing the signature verification form.

  • How many new homes are permitted in McKinney?

    3,360 new-home permits from October 2024 to September 2026: 1,982 in the first year and 1,378 in the second, a 30% drop. 3,014 were detached houses and 346 attached.

  • What inspections does a new home in McKinney need?

    Erosion control first, then temporary pole and ground plumbing, foundation, frame and electrical rough with plumbing top-out and mechanical rough, flatwork, meters, and finals for plumbing and HVAC and then building and electrical, per the City's builder packet.

Build your own list

Pick your city and the kind of work. Every firm with a permit on record, sorted by what you value.