New home permits in McKinney, TX

Data through September 2026 · updated 19 Oct 2026

3,360 new home permits were issued in McKinney, October 2024 through September 2026: about 1,680 a year and 80% of all permits. 1,378 new home permits in the last 12 months (Oct 2025–Sep 2026), 30% fewer than the 1,982 in the 12 months before. The busiest month is February. The usual one took 195 days from issue to the city's final.

What this file covers: McKinney publishes dated permits only for new homes and commercial buildings (new buildings, additions and finish-outs). Its trade, re-roof, remodel, pool and other home permits are not in the file, so the totals here are far below everything the city issues.

3,360permits issued
1,378last 12 months
Febbusiest month
195days, usual issue to final
99%finished
$344,928usual declared value
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 223Oct2024Nov 2024: 173Dec 2024: 204Jan 2025: 172Jan2025Feb 2025: 196Mar 2025: 154Apr 2025: 182May 2025: 172Jun 2025: 125Jul 2025: 160JulAug 2025: 128Sep 2025: 93Oct 2025: 84Nov 2025: 93Dec 2025: 80Jan 2026: 130Jan2026Feb 2026: 139Mar 2026: 115Apr 2026: 150May 2026: 146Jun 2026: 158Jul 2026: 103JulAug 2026: 109Sep 2026: 71
The same numbers as a table
MonthPermits
Oct 2024223
Nov 2024173
Dec 2024204
Jan 2025172
Feb 2025196
Mar 2025154
Apr 2025182
May 2025172
Jun 2025125
Jul 2025160
Aug 2025128
Sep 202593
Oct 202584
Nov 202593
Dec 202580
Jan 2026130
Feb 2026139
Mar 2026115
Apr 2026150
May 2026146
Jun 2026158
Jul 2026103
Aug 2026109
Sep 202671

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). February is the busiest (120), September the quietest (59). A busy month at the permit counter usually means a longer wait for a contractor.

January: 108 (100 = an average month)February: 120 (100 = an average month)120March: 96 (100 = an average month)April: 119 (100 = an average month)May: 114 (100 = an average month)June: 101 (100 = an average month)July: 94 (100 = an average month)August: 85 (100 = an average month)September: 59 (100 = an average month)October: 110 (100 = an average month)November: 95 (100 = an average month)December: 101 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January108
February120
March96
April119
May114
June101
July94
August85
September59
October110
November95
December101

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 1,957 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20251,982
Finished98.7%
Usual days, issue to final195
Middle half, days162–242

Download this table (CSV)

What a new home permit is declared at

The value written on the permit at application, from 3,345 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$344,928
Middle half$264,096–$399,840

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Single Family Residence - Detached3,01490%
Single Family Residence - Attached34610%

Download this table (CSV)

How McKinney compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

New home permits for other places in Dallas–Fort Worth. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of McKinney GIS, Snapshotv2 map service: Residential Permits (layer 3) and Commercial Permits (layer 4), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

New-home permits and commercial building permits (new buildings, additions and finish-outs) the City of McKinney issues inside the city limits. The city publishes no dated file of its trade, re-roof, remodel, pool or other home permits, so those are not here. Unincorporated Collin County and neighboring Allen, Frisco, Prosper and Melissa issue their own permits.

  • The city's file names no contractor (builder), so there are no contractor lists, rankings or firm pages for McKinney.
  • Only new homes and commercial building permits are published with dates: McKinney's trade, re-roof, remodel and pool permits are not in this file, so the totals here are far below everything the city issues.
  • The file has no status column. A permit with a completion date counts as finished and every other permit as open; cancelled or lapsed permits can't be told apart from work in progress.
  • Days to final run from the issue date to the city's completion date, which for a new home is roughly how long it took to build.
  • Value is the valuation declared on the permit, not the sale price of the home.
  • The file has no ZIP code, so there are no ZIP pages for McKinney.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in McKinney, TX", https://contractorrecords.com/mckinney/new-home-permits, data through September 2026, from the City of McKinney Development Services building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits: declared value · New homes permits by permit type.

Common questions

  • How many new home permits does McKinney issue a year?About 1,680 a year in McKinney: 3,360 permits issued October 2024 through September 2026, 1,378 of them in the last 12 months.
  • How long does a new home permit take in McKinney?The usual one took 195 days from issue to the city's final inspection, and the middle half took 162 to 242 days (1,957 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in McKinney file the most new home permits?February (120 against an average month of 100); September is the quietest (59). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.