House Demolition Cost in New York City, NY: what the permits say

How much does house demolition cost in New York City? The usual demolition job filed with New York City is $25,000, from 1,700 priced permits (October 2023 through September 2026); the middle half of firms file between $12,500 and $35,000. A filed value is what the contractor wrote on the permit, not a quote or the final bill. The file does not say which New York City demolition permits were whole-house teardowns and which were garages, sheds or partial demolition, so every figure here covers all of them.

$25,000usual filed value
$12,500–$35,000middle half of firms' usual jobs
1,700priced permits (98% of 1,736)
349firms on file
32days, permit issue to final
Sep 2026records through

How much does it cost to tear down a house in New York City?

The usual New York City demolition permit is filed at $25,000, from 1,700 priced permits, October 2023 through September 2026. Half were filed for less, half for more. The file does not separate whole-house teardowns from garages, sheds or partial demolition, so read it as the middle of all demolition jobs, not a house-only price. A filed value is what the contractor wrote on the permit, not a quote or the final bill. A demolition permit here usually takes 32 days from issue to final inspection. How long permits take →

What the spread looks like

Approximately, from each firm's own spread: every firm's range of filed values, weighted by its 1,700 priced permits across 348 firms, pooled into one. Half of New York City demolition permits were filed between $10,300 and $45,500.

PercentileFiled valueReads as
10th$5,0001 in 10 permits filed below
25th$10,3001 in 4 filed below
50th$23,400the middle permit
75th$45,5001 in 4 filed above
90th$68,6001 in 10 filed above

By home value

Firms split into thirds by the usual value of the homes they work on, with each third's usual filed value weighted by permits. Home values: NYC Department of Finance market values.

Firms working onUsual home valueUsual filed valueFirmsPermits
Lower thirdunder $650,000$35,40096619
Middle third$650,000–$1,009,000$22,50097559
Upper third$1,014,000 and up$15,00097448

Busiest firms and what they usually charge

Top 10 by permits in the last 12 months. Usual is each firm's middle filed value; middle half is the range its middle half of jobs were filed in. Busy is not the same as careful: pick what you value to build a list.

FirmPermitsLast 12 moUsualMiddle halfFinished
Sken Services Corp18280$50,000$15,000–$50,00099.9%
N Tech Design of America7142$30,000$15,000–$50,00099.5%
Stream Rock Contsruction3429$15,000$5,000–$45,0003 of 6
Golden Time Contracting I3718$3,000$1,500–$45,00095.7%
L&L Construction Develop3716$15,000$5,000–$40,00092.3%
Perciballi Industries Inc3713$22,500$18,500–$28,75099.4%
Zefi & Co. LLC2213$27,500$10,000–$35,0009 of 9
Crowbar Industries Inc1313$15,000$10,000–$30,000—
Bethel Building Corp2412$18,000$10,000–$25,00099.3%
Granite Environment, LLC3010$301,254$191,527–$367,15099.3%

Why filed values run low or high

  • The 10 busiest firms usually file $30,000; the 310 firms with fewer than 10 permits usually file $21,000.
  • Firms working on the most expensive third of homes (usual home value $1,014,000 and up) usually file $15,000, against $35,400 for the least expensive third.
  • One permit type covers small and large jobs: 1 in 10 demolition permits is filed under $5,000 and 1 in 10 over $68,600, 14 times as much.
  • 97.9% of the 1,736 permits carry a value; the 36 without one are left out of every figure here.

Is your quote normal? Compare it with 1,700 filed values

Line your quote up against the file. In New York City, 1 in 10 demolition filed values sit under $5,000, the middle half between $10,300 and $45,500, and 1 in 10 over $68,600.

  • $89,200Above $68,600: higher than 9 in 10 filed values for this work in New York City.
  • $25,000Right at the usual $25,000: in the middle of the file.
  • $3,500Below $5,000: lower than 9 in 10. Ask what the quote leaves out.

When to schedule demolition in New York City

New York City files the fewest demolition permits in January (77 against an average month of 100) and the most in September (123). If you can choose, ask for quotes in a quiet month. We have no prices by month, so this is about crews' schedules, not a discount. When each trade is busiest in New York City →

How these numbers are made

Source: NYC Department of Buildings permits and DOB NOW filings on one- and two-family homes (NYC Open Data). The window is October 2023 through September 2026; a permit filed after that isn't here yet.

Usual is the middle permit: half were filed for less, half for more. Only permits with a filed value count; a value of $0 or none is left out.

The spread is approximate: we keep seven points of each firm's own range of filed values, not every permit, and pool them.

Nobody paid to be on this page and nobody can. How the records work in New York City →

Common questions

  • How many quotes should I get for a demolition job in New York City?At least three. In the permit record the middle half of New York City demolition firms usually file between $12,500 and $35,000 a job, so two ordinary firms can sit 2.8 times apart and both be normal for New York City. A third quote shows which one is the outlier. Filed values are what contractors wrote on permits, not quotes, so use them to judge the spread, not to price your own job.
  • What range is normal for demolition jobs in New York City?Half of permits were filed between $10,300 and $45,500; 8 in 10 between $5,000 and $68,600. These are approximate, pooled from each firm's own spread.
  • How much do demolition contractors charge in New York City?The usual demolition job is filed at $25,000; the middle half of firms usually file between $12,500 and $35,000. The 10 firms with the most permits in the last 12 months usually file $30,000, more than the usual. See every firm's usual job →
  • Do bigger houses get bigger bills?Not in the file: firms working on the upper third of homes by value usually file $15,000, the lower third $35,400.
  • Where does this data come from?NYC Department of Buildings permits and DOB NOW filings on one- and two-family homes (NYC Open Data), read October 2026. How the records work in New York City →