Data through September 2026 · updated 18 Oct 2026

51,876 building permits issued in Detroit, October 2024 through September 2026: about 25,938 a year. The biggest kind of work is plumbing, with 13,739. 21,722 permits in the last 12 months (Oct 2025–Sep 2026), 28% fewer than the 30,154 in the 12 months before. 77% were permits for homes. The busiest month for permits is October.

51,876permits issued
21,722last 12 months
−28%vs the 12 months before
77%for homes
Octbusiest month
Sep 2026records through

By kind of work

Permits issued October 2024 through September 2026. Last 12 months is Oct 2025–Sep 2026; the 12 months before is Oct 2024–Sep 2025. Homes is the share issued as residential permits. Busiest month is the calendar month with the most permits on average.

Kind of workPermitsShareLast 12 mo12 mo beforeChangeHomesBusiest month
Plumbing13,73926%4,7159,024−48%88%October
HVAC12,98925%5,4887,501−27%75%April
Electrical9,70519%4,4625,243−15%66%October
Remodels & repairs7,11914%3,6243,495+4%100%October
Demolition2,1254%6121,513−60%91%October
Roofing1,8204%8091,011−20%93%October
Solar398under 1%219179+22%91%October
New homes212under 1%107105+2%100%October
Garages, sheds & shade structures130under 1%6763+6%100%May
Additions102under 1%4458−24%100%July
Other3,4987%1,5521,946−20%7%July

Fewer than 100 permits, so no row: fences & walls (30), pools & spas (8), ADUs & casitas (1).

Download this table (CSV)

By year

Permits issued in each calendar year of the window. Per year scales a part year to 12 months.

YearMonthsPermitsPer year
2024 (from October)37,37429,496
20251228,82828,828
2026 (through September)915,67420,899

Download this table (CSV)

By month

Permits issued each month, October 2024 through September 2026. The tallest bar is the busiest month on file.

Oct 2024: 3,263Oct2024Nov 2024: 2,170Dec 2024: 1,941Jan 2025: 2,621Jan2025Feb 2025: 2,181Mar 2025: 2,974Apr 2025: 2,891May 2025: 2,570Jun 2025: 2,687Jul 2025: 2,783JulAug 2025: 2,192Sep 2025: 1,881Oct 2025: 2,423Nov 2025: 1,768Dec 2025: 1,857Jan 2026: 1,503Jan2026Feb 2026: 1,861Mar 2026: 1,795Apr 2026: 1,887May 2026: 1,445Jun 2026: 1,881Jul 2026: 1,611JulAug 2026: 1,527Sep 2026: 2,164
The same numbers as a table
MonthPermits
Oct 20243,263
Nov 20242,170
Dec 20241,941
Jan 20252,621
Feb 20252,181
Mar 20252,974
Apr 20252,891
May 20252,570
Jun 20252,687
Jul 20252,783
Aug 20252,192
Sep 20251,881
Oct 20252,423
Nov 20251,768
Dec 20251,857
Jan 20261,503
Feb 20261,861
Mar 20261,795
Apr 20261,887
May 20261,445
Jun 20261,881
Jul 20261,611
Aug 20261,527
Sep 20262,164

Download this table (CSV)

When each kind of work is filed

Permits by calendar month, 100 = an average month (the thin line), October 2024 through September 2026. Kinds of work do not all peak together. Each month is counted twice (once a year), so one unusual month still moves these numbers.

Plumbing

13,739 permits · busiest October, quietest December

January: 99 (100 = an average month)February: 100 (100 = an average month)March: 109 (100 = an average month)April: 106 (100 = an average month)May: 83 (100 = an average month)June: 113 (100 = an average month)July: 118 (100 = an average month)August: 74 (100 = an average month)September: 103 (100 = an average month)October: 151 (100 = an average month)151November: 77 (100 = an average month)December: 66 (100 = an average month)JFMAMJJASOND

HVAC

12,989 permits · busiest April, quietest August

January: 111 (100 = an average month)February: 109 (100 = an average month)March: 130 (100 = an average month)April: 131 (100 = an average month)131May: 94 (100 = an average month)June: 94 (100 = an average month)July: 80 (100 = an average month)August: 69 (100 = an average month)September: 82 (100 = an average month)October: 113 (100 = an average month)November: 90 (100 = an average month)December: 98 (100 = an average month)JFMAMJJASOND

Electrical

9,705 permits · busiest October, quietest January

January: 86 (100 = an average month)February: 88 (100 = an average month)March: 119 (100 = an average month)April: 99 (100 = an average month)May: 99 (100 = an average month)June: 109 (100 = an average month)July: 95 (100 = an average month)August: 91 (100 = an average month)September: 95 (100 = an average month)October: 127 (100 = an average month)127November: 93 (100 = an average month)December: 98 (100 = an average month)JFMAMJJASOND

Remodels & repairs

7,119 permits · busiest October, quietest January

January: 64 (100 = an average month)February: 76 (100 = an average month)March: 83 (100 = an average month)April: 103 (100 = an average month)May: 115 (100 = an average month)June: 115 (100 = an average month)July: 115 (100 = an average month)August: 116 (100 = an average month)September: 103 (100 = an average month)October: 129 (100 = an average month)129November: 89 (100 = an average month)December: 92 (100 = an average month)JFMAMJJASOND

Demolition

2,125 permits · busiest October, quietest February

January: 137 (100 = an average month)February: 57 (100 = an average month)March: 86 (100 = an average month)April: 132 (100 = an average month)May: 66 (100 = an average month)June: 106 (100 = an average month)July: 93 (100 = an average month)August: 88 (100 = an average month)September: 67 (100 = an average month)October: 144 (100 = an average month)144November: 142 (100 = an average month)December: 82 (100 = an average month)JFMAMJJASOND

Roofing

1,820 permits · busiest October, quietest May

January: 79 (100 = an average month)February: 87 (100 = an average month)March: 96 (100 = an average month)April: 92 (100 = an average month)May: 72 (100 = an average month)June: 86 (100 = an average month)July: 85 (100 = an average month)August: 121 (100 = an average month)September: 89 (100 = an average month)October: 158 (100 = an average month)158November: 131 (100 = an average month)December: 105 (100 = an average month)JFMAMJJASOND

Solar

398 permits · busiest October, quietest December

January: 75 (100 = an average month)February: 93 (100 = an average month)March: 112 (100 = an average month)April: 99 (100 = an average month)May: 109 (100 = an average month)June: 72 (100 = an average month)July: 112 (100 = an average month)August: 127 (100 = an average month)September: 75 (100 = an average month)October: 145 (100 = an average month)145November: 118 (100 = an average month)December: 63 (100 = an average month)JFMAMJJASOND

New homes

212 permits · busiest October, quietest November

January: 85 (100 = an average month)February: 79 (100 = an average month)March: 113 (100 = an average month)April: 142 (100 = an average month)May: 113 (100 = an average month)June: 96 (100 = an average month)July: 51 (100 = an average month)August: 119 (100 = an average month)September: 142 (100 = an average month)October: 181 (100 = an average month)181November: 23 (100 = an average month)December: 57 (100 = an average month)JFMAMJJASOND
The same numbers as a table
Kind of workJanFebMarAprMayJunJulAugSepOctNovDec
Plumbing9910010910683113118741031517766
HVAC11110913013194948069821139098
Electrical868811999991099591951279398
Remodels & repairs6476831031151151151161031298992
Demolition13757861326610693886714414282
Roofing7987969272868512189158131105
Solar759311299109721121277514511863
New homes857911314211396511191421812357

Download this table (CSV)

Homes and everything else

How the city classed each permit. Other covers commercial buildings, signs, towers and similar work.

Permit classPermitsShareLast 12 mo
Homes (residential)40,09477%16,611
Other11,78223%5,111

Download this table (CSV)

By ZIP code

The 10 ZIP codes with the most permits, counted at the property's ZIP code. A ZIP code can cross into a city that runs its own permit office; only the city's permits are counted.

ZIP codePermitsShareTop kind of work
482043,5867%Plumbing (2,049)
482213,2626%HVAC (825)
482352,9136%HVAC (1,149)
482242,7875%Plumbing (770)
482382,7815%Plumbing (1,414)
482062,6195%Plumbing (1,336)
482272,6105%HVAC (787)
482132,4585%Plumbing (1,066)
482052,4345%HVAC (676)
482192,4315%HVAC (767)

All 27 ZIP codes with 250+ permits →

Download this table (CSV)

How Detroit compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Detroit Open Data, BSEED Building Permits, Trades Permits and Demolition Permits layers, read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out. The city's public permit layers carry an issue date but no permit status and no final inspection or closed date, so no finished share is shown.

Building, trades (mechanical, electrical, plumbing, elevator, fire alarm, boiler, generator) and demolition permits the City of Detroit Buildings, Safety Engineering and Environmental Department (BSEED) issues inside city limits. Revisions of an earlier permit are not counted again. Hamtramck, Highland Park, Dearborn and the rest of Wayne County run their own permit offices and are not in this file.

  • The city's file has no permit status and no final inspection date, so we show neither a finished share nor time to final.
  • Only building permits carry a value: the estimated contractor cost written on the application, not the final cost. Trade and demolition permits have no value, so the HVAC, electrical, plumbing and demolition figures carry none.
  • Detroit issues electrical, plumbing and mechanical work as separate trades permits, so one house job can count several times, once under each kind of work. A building alteration that mentions trade work stays a remodel.
  • Plumbing counts include the Detroit Water and Sewerage Department's lead service line and water main replacement programmes, which file thousands of plumbing permits a year.
  • Homes are told apart by the building permit's use group and use type and, for trade and demolition permits, by the property class on the city assessor's parcel file.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Detroit, MI building permit statistics", https://contractorrecords.com/detroit/permit-statistics, data through September 2026, from the City of Detroit Buildings, Safety Engineering and Environmental Department building-permit records.

Link to a table: By kind of work · By year · By month · When each kind of work is filed · Homes and everything else · By ZIP code.

Download the tables (CSV): Permits by kind of work · Permits by year · Permits by month · Permits by calendar month (index) · Homes and other permits · Permits by ZIP code.

Common questions

  • How many building permits does Detroit issue a year?About 25,938 a year in Detroit: 51,876 permits over 24 months, October 2024 through September 2026. 21,722 permits in the last 12 months (Oct 2025–Sep 2026), 28% fewer than the 30,154 in the 12 months before.
  • Are building permits up or down in Detroit?21,722 permits in the last 12 months (Oct 2025–Sep 2026), 28% fewer than the 30,154 in the 12 months before. Remodel and repair permits grew most (3,495 to 3,624); plumbing permits fell most (9,024 to 4,715).
  • What is the busiest month for permits in Detroit?October, counting every kind of work (132 against an average month of 100). August is the quietest (86). Each kind of work has its own season; the charts above show them.
  • What share of Detroit permits are for homes?77%: 40,094 of the 51,876 permits issued October 2024 through September 2026 were residential permits.