Do I need a permit to build a house in Denton, TX? The City's new-home permit, fees and 13 inspections

Yes. A new house in Denton needs a City of Denton building permit, and the City will not issue one until the lot is platted; builders filed 2,906 new-home permits from October 2023 to September 2026, and by our estimate the usual one reached final 181 days after issue. The permit fee itself is $0.94 per square foot plus $150 of plan review, and the water, wastewater and roadway impact fees collected alongside it can cost more.

By Contractor Records · data through October 18, 2026

What the City asks for

From the City's New Residential Construction page, read 23 October 2026:

Requirement Detail
Platted lot "Lot shall be platted prior to building permit issuance"
Zoning Setbacks and lot coverage per Denton Development Code 3.2; building size per 5.3.3; site and building design per 7.10.3
Forms Residential Application, Energy Compliance Path form, Residential Submittal Requirements; "additional documents may be required upon review"
Where Applications and plans go in through the City's eTRAKiT portal
Fees Payable "once permit is approved": building permit, plan review, water meter, water/sewer impact, roadway impact, T-pole and park development fees, and a fence fee if any
Utilities A Request for Service form before meter installation or solid waste service; Customer Service (940) 349-8700

What it costs

From the City's Permit and Fee Schedule, effective 1 October 2026 (Ordinance 26-1576), read 23 October 2026:

Fee Amount
Building permit fee, one- and two-family dwelling $0.94 per square foot
Plan review fee $150
Water and wastewater impact fees Set by plat date, meter size and service zone, "determined by meter size and dwelling type at plan review"
Working without a permit (Table 6) $453
House size Permit + plan review (our arithmetic)
2,000 sq ft $2,030
2,500 sq ft $2,500
3,000 sq ft $2,970

The schedule does not say which square footage it means (living area or under roof), and the impact fees on lots platted in different years differ by thousands of dollars per meter, so the City says to "call Building Safety for final fee totals": (940) 349-8600. Build prices from our permits: Denton new home cost.

The 13 inspections

From the City's Inspections List, in order, for a new single-family home:

# Inspection What is checked
1 T-pole Temporary construction power
2 Plumbing underground Water test, DWV test, supply distribution
3 Foundation Forms and steel before the pour; hand the inspector a form board survey
4 Exterior sheathing Before wrap, siding or masonry
5 Braced wall Wind bracing, hold-downs, straps
6 Brick ties / lath / stucco Supports before brick or stucco
7 Frame / MEP roughs Framing, plumbing, electrical and mechanical roughs, gas and water tests
8 Insulation Minimum insulation, window and door SHGC and U-factor
9 Sidewalk Forms and fiber mesh
10 Approach Driveway approach steel, depth and gutter flow line
11 Electrical meter release Service built, devices trimmed out
12 Gas meter release Air test to the stops
13 Building final (certificate of occupancy) Termite treatment, landscape, fence, drainage, duct blaster and blower door reports, energy report, irrigation final, FEMA certificate if needed

Inspections are booked in eTRAKiT, or on (940) 349-8600 if you cannot; requests made by 5:59 a.m. are done that day. Cancel by phone before 9 a.m. or pay a re-inspection fee, keep the City-approved plans on site, and expect the final to wait until every unpaid fee is paid. Survey, termite, energy and drainage documents are uploaded to eTRAKiT. A permit expires 180 days after issue unless an inspection renews it for another 180 (Development Services FAQs).

Who can build it

Texas has no state license for home builders. Denton fills the gap with registration: the City "requires all contractors to be registered to perform work", and its electrical, plumbing and mechanical registrations require the matching Texas license (Contractor Registration). The checks are in the Denton contractor license lookup. The City's pages we read do not spell out an owner-builder route; ask Building Safety before planning one, and see the owner-builder permit guide.

What 2,906 Denton new-home permits show

Measure Denton new homes
Permits, October 2023 to September 2026 2,906
Builders 72
Builders with a permit in the 12 months to September 2026 40
Usual filed value $397,548
Middle half of builders' usual value $353,397 to $504,112
Usual days to final (estimated) 181
Finaled (a year or more old) 97.6%
Share held by the busiest builder / five busiest 23.9% / 64.6%
Builders with a single permit 32 (44.4%)
Busiest / quietest month for filing January / May

Denton new homes are a production-builder market: Dr Horton filed 252 permits in the 12 months to September 2026, and five builders hold 64.6% of the total. Almost every house gets its final (97.6%), so finished share will not separate builders here; the value range and the builder's past houses will. The other end is thin: 32 builders filed a single Denton house in three years.

Check it in five minutes

  1. Search the builder under Search Contractors in eTRAKiT to confirm City registration.
  2. Use eTRAKiT's permit search with the CONTRACTOR field to see the builder's other Denton houses and whether they reached FINALED (how).
  3. Compare builders on the Denton new-home builder list.

Other cities: do I need a permit to build a house. National prices: new home construction cost.

See every Denton home builder by permits filed →

What this does not tell you

Denton's yearly permit files have no completion date, so days to final are estimates. We matched few builders to any license, because Texas does not license home builders. Impact fees vary by lot; our fee table covers only the City's building permit and plan review lines. More: Denton permit statistics.

How we know this

Requirements, fees and inspections are quoted from the City of Denton's New Residential Construction page, its Permit and Fee Schedule effective 1 October 2026 and its Inspections List, read 23 October 2026; expiry from its Development Services FAQs and registration from its Contractor Registration page. Fee examples are our arithmetic. Our counts are City of Denton new-home permits, October 2023 to September 2026; days to final are estimated.

Numbers come from City of Denton Building Safety permits on homes (the city's yearly permit reports), data through October 18, 2026. Nobody paid to be on this page and nobody can.

Questions

  • Do I need a permit to build a house in Denton?

    Yes. A new single-family home needs a City of Denton building permit, applied for through eTRAKiT with the residential application, energy compliance form and submittal documents, and the City says the lot must be platted before the permit is issued.

  • How much is a building permit for a new house in Denton?

    The City's fee schedule effective 1 October 2026 sets the one- and two-family building permit fee at $0.94 per square foot plus a $150 plan review fee, so a 2,500 sq ft house is $2,500 before water and wastewater impact fees, roadway impact, meter, park and other fees the City collects at approval.

  • What inspections does a new house need in Denton?

    Thirteen on the City's list, from T-pole and plumbing underground through foundation, sheathing, braced wall, frame and MEP roughs, insulation, sidewalk, approach, electric and gas meter releases, to the building final for the certificate of occupancy.

  • How long does it take to build a permitted house in Denton?

    By our estimate the usual Denton new-home permit reached final 181 days after issue, and 97.6% of new-home permits a year or more old were finaled.

  • Who builds the most new homes in Denton?

    By permits in the 12 months to September 2026, Dr Horton led with 252. The five busiest builders hold 64.6% of Denton new-home permits.