Washington's 2024 building and energy codes take effect 3 May 2027: what changes for new homes, additions and AC replacements

Washington's 2024 building and energy codes take effect on 3 May 2027 in every city and county, the State Building Code Council says (SBCC), and the residential energy part is still a proposal: the council filed it on 1 July 2026 and targets final adoption for 20 November 2026. As proposed, it tightens new-home windows to a U-factor of 0.27, cuts the air-leakage limit to 3.0 air changes an hour, requires heat or energy recovery ventilation in climate zone 5, and adds a rule for AC replacements with a heat pump path (CR-102). That last item reaches existing homes: Seattle alone issued 15,441 Heat Pump & AC permits over October 2023 to September 2026.

By Contractor Records · data through October 17, 2026

The dates

Step Date Source
2021 Washington State Energy Code in force (the code this replaces) Since 15 March 2024 SBCC Energy Code
Residential energy code proposal (CR-102) filed 1 July 2026 SBCC
Public hearings 5 August 2026 (Olympia), 7 August 2026 (Spokane) CR-102
Written comments closed 7 August 2026 CR-102
Final adoption, targeted 20 November 2026 SBCC
Effective statewide 3 May 2027 SBCC, CR-102

What the proposal changes for homes

From the CR-102 summary of the 2024 Washington State Energy Code, Residential (SBCC) and the council's June 2026 cost study (pCBA):

Item Proposed for 2024 WSEC-R Who it touches
Window U-factor 0.27 (from 0.28 in climate zone 5 and marine 4C, per proposal 24-RE-036) New homes and additions
Air leakage 3.0 air changes an hour; units under 800 sq ft stay at 4.0 New homes
Ventilation Heat or energy recovery ventilation required in climate zone 5 New homes in climate zone 5
Ducts Generally in conditioned space or deeply buried New homes and additions
Gas equipment Electric-readiness measures when the home uses fuel gas or liquid fuel equipment New homes with gas
AC replacement Alterations rule encouraging heat pumps when an air conditioner is replaced (proposal 24-RE-019, section R503.1.2.5): heat pump path or duct/insulation path Existing homes
Compliance New Energy Rating Index path; energy credit table revised Builders
Low-slope roofs Cool-roof requirement New homes with flat roofs

The council says some sections present alternative options on which it requested testimony, so the adopted text may differ from this table. The cost study found the AC-replacement proposal "cost-effective under current WA utility rates" and called the two-path structure flexible.

What it means for a project in 2027

  1. AC replacements after 3 May 2027. If the final rule keeps the heat pump path, a straight AC swap may need duct or insulation work instead. Ask the contractor which path the quote follows. Seattle splits its HVAC permits into Heat Pump & AC and Furnace & Heating, so you can see who files which.
  2. New homes and additions. Plans drawn to the 2021 code before May 2027 should be checked against the date your department will apply the 2024 code.
  3. Timing. If you are close to the line, ask the building department how it treats an application in review on 3 May 2027. The state rule sets the effective date; it does not answer that question.

Permits in the three Washington cities we cover

City Heat pump / HVAC permits Firms Usual days to final New-home permits
Seattle (Heat Pump & AC) 15,441 272 105 —
Seattle (Furnace & Heating) 18,668 316 66 —
Bellevue (HVAC & Mechanical) 5,650 570 76 194
Bellingham (HVAC & Mechanical) 2,581 68 24 449

Seattle's new homes are not split out as a trade in our data, hence the dashes. Counts cover October 2023 to September 2026. For the permit itself, see the Seattle heat pump permit guide.

Check it yourself in five minutes

Open the council's Energy Code page after 20 November 2026 to see whether the residential code was adopted as proposed. Then, on the compare page for your city, sort heat pump installers by permits reaching final.

What this page does not cover

The table lists proposed changes, not adopted text. Cities can adopt local amendments, and we have not checked any city's. Our permit data does not tell us which code a permit was reviewed under.

How we know this

Dates and proposed changes are quoted from the Washington State Building Code Council's home page, its CR-102 filing for the 2024 residential energy code (1 July 2026) and its June 2026 preliminary cost-benefit analysis, read 26 October 2026. Permit counts are from the City of Seattle, City of Bellevue and City of Bellingham open permit data, October 2023 to September 2026; days run from issue to final.

Numbers come from City of Seattle (SDCI) building, trade and electrical permits on single-family and duplex homes (the city's open-data exports); City of Bellevue permits on single-family homes and condo units; City of Bellingham permits on single-family homes, duplexes and townhomes, data through October 17, 2026. Nobody paid to be on this page and nobody can.

See every Seattle heat pump installer by permit record →

Questions

  • When do Washington's 2024 codes take effect?

    The State Building Code Council says "The effective date of the 2024 codes will be May 3, 2027." The residential energy code rule filed on 1 July 2026 uses the same date for all counties and cities.

  • Is the 2024 Washington residential energy code final?

    Not as of 26 October 2026. The council took comments to 7 August 2026, held hearings on 5 and 7 August, and lists final adoption as targeted for 20 November 2026. The changes below are from the proposed rule.

  • Will I have to install a heat pump when I replace my AC?

    The proposal adds an alterations rule for AC replacement with two paths: a heat pump, or a duct and insulation path. The council's cost study found it cost-effective at current Washington utility rates. The final text is due with adoption.

  • How many heat pump and AC permits does Seattle issue?

    Seattle issued 15,441 Heat Pump & AC permits from October 2023 to September 2026, to 272 firms. The usual filed job value was $8,000.

  • Does a permit filed before 3 May 2027 use the old code?

    The rule sets the date the new code becomes effective; how a department treats an application already under review on that date is up to the department. Ask yours when you apply.