Data through July 2026 · updated 23 Oct 2026

949 electrical permits were issued in Johns Creek, August 2024 through July 2026: about 474 a year and 24% of all permits. 469 electrical permits in the last 12 months on file (Aug 2025–Jul 2026), 2% fewer than the 480 in the 12 months before. The busiest month is March.

949permits issued
469last 12 months on file
Marbusiest month
87%finished
Jul 2026records through

Electrical permits by month

Permits issued each month, August 2024 through July 2026.

Aug 2024: 39Aug2024Sep 2024: 55Oct 2024: 35Nov 2024: 52Dec 2024: 41Jan 2025: 32Jan2025Feb 2025: 28Mar 2025: 44Apr 2025: 30May 2025: 30Jun 2025: 56Jul 2025: 38JulAug 2025: 33Sep 2025: 35Oct 2025: 42Nov 2025: 37Dec 2025: 23Jan 2026: 34Jan2026Feb 2026: 37Mar 2026: 50Apr 2026: 38May 2026: 57Jun 2026: 38Jul 2026: 45Jul
The same numbers as a table
MonthPermits
Aug 202439
Sep 202455
Oct 202435
Nov 202452
Dec 202441
Jan 202532
Feb 202528
Mar 202544
Apr 202530
May 202530
Jun 202556
Jul 202538
Aug 202533
Sep 202535
Oct 202542
Nov 202537
Dec 202523
Jan 202634
Feb 202637
Mar 202650
Apr 202638
May 202657
Jun 202638
Jul 202645

Download this table (CSV)

When electrical permits are filed

By calendar month, 100 = an average month (the thin line). March is the busiest (119), December the quietest (81). A busy month at the permit counter usually means a longer wait for a contractor.

January: 83 (100 = an average month)February: 82 (100 = an average month)March: 119 (100 = an average month)119April: 86 (100 = an average month)May: 110 (100 = an average month)June: 119 (100 = an average month)July: 105 (100 = an average month)August: 91 (100 = an average month)September: 114 (100 = an average month)October: 97 (100 = an average month)November: 113 (100 = an average month)December: 81 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January83
February82
March119
April86
May110
June119
July105
August91
September114
October97
November113
December81

Download this table (CSV)

How many electrical permits get finished

Permits issued Aug 2024–Jul 2025, at least 12 months before the file ends.

MeasureValue
Permits issued Aug 2024–Jul 2025480
Finished86.9%
Expired12.3%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Electrical83188%
Low voltage9610%
Electrical (residential)182%
Low voltage (residential)4under 1%

Download this table (CSV)

Other kinds of work here

How Johns Creek compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Johns Creek, Building Permits Issued (ArcGIS layer), read 23 Oct 2026. We count permits issued August 2024 through July 2026; denied and withdrawn permits are left out.

Permits the City of Johns Creek issues for homes inside city limits: residential building permits, plus mechanical, electrical, plumbing, fence, retaining-wall and demolition permits on property the tax roll classes as residential. Commercial building permits, trade permits on commercial property, right-of-way, sign, tree-removal and land-disturbance permits in the same file are not counted. Alpharetta, Milton, Duluth and the rest of Fulton and Forsyth counties run their own permit offices and are not in this file.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Johns Creek.
  • The file has no job value, no final inspection date and no ZIP code, so we show no costs, no time to final and no ZIP pages.
  • A residential building permit in the file doesn't say whether it is a new house, an addition or a remodel, so those permits are counted together under other.
  • The city last refreshed its permit file in mid-August 2026, so the window ends in July 2026.
  • Trade permits are counted as home permits when the parcel's tax class is residential; trade permits on parcels we couldn't match are left out.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Electrical permits in Johns Creek, GA", https://contractorrecords.com/johns-creek/electrical-permits, data through July 2026, from the City of Johns Creek Community Development Department building-permit records.

Link to a table: By month · Season · How many get finished · Permit types.

Download the tables (CSV): Electrical permits by month · Electrical permits by calendar month (index) · Electrical permits: finished share · Electrical permits by permit type.

Common questions

  • How many electrical permits does Johns Creek issue a year?About 474 a year in Johns Creek: 949 permits issued August 2024 through July 2026, 469 of them in the last 12 months on file (to July 2026).
  • When do people in Johns Creek file the most electrical permits?March (119 against an average month of 100); December is the quietest (81). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.