Contractor Records
Home › Sioux Falls › Demolition

Demolition permits in the City of Sioux Falls, SD

Data through September 2026 · updated 19 Oct 2026

207 demolition permits were issued in the City of Sioux Falls, October 2024 through September 2026: about 104 a year and under 1% of all permits. 100 demolition permits in the last 12 months (Oct 2025–Sep 2026), 7% fewer than the 107 in the 12 months before. The busiest month is May. The usual one took 275 days from issue to the city's final. 57105 has the most, 76.

207permits issued
100last 12 months
Maybusiest month
275days, usual issue to final
80%finished
$14,000usual declared value
Sep 2026records through

Demolition permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 5Oct2024Nov 2024: 13Dec 2024: 7Jan 2025: 13Jan2025Feb 2025: 9Mar 2025: 5Apr 2025: 10May 2025: 12Jun 2025: 10Jul 2025: 10JulAug 2025: 7Sep 2025: 6Oct 2025: 7Nov 2025: 8Dec 2025: 4Jan 2026: 7Jan2026Feb 2026: 5Mar 2026: 4Apr 2026: 11May 2026: 12Jun 2026: 12Jul 2026: 4JulAug 2026: 8Sep 2026: 18
The same numbers as a table
MonthPermits
Oct 20245
Nov 202413
Dec 20247
Jan 202513
Feb 20259
Mar 20255
Apr 202510
May 202512
Jun 202510
Jul 202510
Aug 20257
Sep 20256
Oct 20257
Nov 20258
Dec 20254
Jan 20267
Feb 20265
Mar 20264
Apr 202611
May 202612
Jun 202612
Jul 20264
Aug 20268
Sep 202618

Download this table (CSV)

When demolition permits are filed

By calendar month, 100 = an average month (the thin line). May is the busiest (139), March the quietest (52). A busy month at the permit counter usually means a longer wait for a contractor.

January: 116 (100 = an average month)February: 81 (100 = an average month)March: 52 (100 = an average month)April: 122 (100 = an average month)May: 139 (100 = an average month)139June: 128 (100 = an average month)July: 81 (100 = an average month)August: 87 (100 = an average month)September: 139 (100 = an average month)October: 70 (100 = an average month)November: 122 (100 = an average month)December: 64 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January116
February81
March52
April122
May139
June128
July81
August87
September139
October70
November122
December64

Download this table (CSV)

How long a demolition permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 84 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025107
Finished80.4%
Expired7.5%
Usual days, issue to final275
Middle half, days98–382

Download this table (CSV)

What a demolition permit is declared at

The value written on the permit at application, from 207 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$14,000
Middle half$8,250–$25,000

Download this table (CSV)

ZIP codes with the most demolition permits

Counted at the property's ZIP code. Share is the part of the city's 207 demolition permits.

ZIP codePermitsShare
571057637%
571046732%
571062613%
571032010%
57108105%
5710742%
571972under 1%
571102under 1%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Razing13766%
Demolition7034%

Download this table (CSV)

How these numbers are made

Source: City of Sioux Falls GIS: Building Permits (Data/Community MapServer layer 3), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential and commercial building permits the City of Sioux Falls issues inside city limits, in both Minnehaha and Lincoln counties: new homes and buildings, additions, remodels and repairs, re-shingling, decks, pools, demolition, and electrical, plumbing and mechanical permits. Brandon, Harrisburg, Tea and the unincorporated parts of both counties run their own permit offices and are not in this file.

  • The city's file has a contractor column, but it is empty on every row, so there are no contractor lists, rankings or firm pages for Sioux Falls.
  • A final date is the city's finalized date; a permit marked finaled counts as finished.
  • The value is the valuation declared on the permit.
  • Homes are the city's residential building permits, which include electrical, plumbing and mechanical permits for homes. Commercial remodels, additions and build-outs count as other.
  • Mechanical permits for fireplaces and refrigeration count as HVAC; re-shingle permits count as roofing; decks count with garages, sheds and shade structures.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Demolition permits in the City of Sioux Falls, SD", https://contractorrecords.com/sioux-falls/demolition-permits, data through September 2026, from City of Sioux Falls Planning & Development Services building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types.

Download the tables (CSV): Demolition permits by month · Demolition permits by calendar month (index) · Demolition permits: days to final · Demolition permits: declared value · Demolition permits by ZIP code · Demolition permits by permit type.

Common questions

  • How many demolition permits does Sioux Falls issue a year?About 104 a year in the City of Sioux Falls: 207 permits issued October 2024 through September 2026, 100 of them in the last 12 months.
  • How long does a demolition permit take in Sioux Falls?The usual one took 275 days from issue to the city's final inspection, and the middle half took 98 to 382 days (84 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Sioux Falls file the most demolition permits?May (139 against an average month of 100); March is the quietest (52). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most demolition permits in Sioux Falls?57105, with 76 of the 207 (37%); then 57104 (67).