Plumbing permits in the City of Thornton, CO

Data through September 2026 · updated 20 Oct 2026

1,867 plumbing permits were issued in the City of Thornton, October 2024 through September 2026: about 934 a year and 24% of all permits. 960 plumbing permits in the last 12 months (Oct 2025–Sep 2026), 6% more than the 907 in the 12 months before. The busiest month is March. 80241 has the most, 499.

What this file covers: Re-roof, fence and backflow permits are left out of every month: the city's published file stops carrying them after July 2025.

1,867permits issued
960last 12 months
Marbusiest month
78%finished
$3,450usual declared value
Sep 2026records through

Plumbing permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 81Oct2024Nov 2024: 68Dec 2024: 80Jan 2025: 71Jan2025Feb 2025: 63Mar 2025: 85Apr 2025: 78May 2025: 73Jun 2025: 84Jul 2025: 78JulAug 2025: 80Sep 2025: 66Oct 2025: 84Nov 2025: 66Dec 2025: 89Jan 2026: 89Jan2026Feb 2026: 55Mar 2026: 100Apr 2026: 68May 2026: 78Jun 2026: 80Jul 2026: 93JulAug 2026: 70Sep 2026: 88
The same numbers as a table
MonthPermits
Oct 202481
Nov 202468
Dec 202480
Jan 202571
Feb 202563
Mar 202585
Apr 202578
May 202573
Jun 202584
Jul 202578
Aug 202580
Sep 202566
Oct 202584
Nov 202566
Dec 202589
Jan 202689
Feb 202655
Mar 2026100
Apr 202668
May 202678
Jun 202680
Jul 202693
Aug 202670
Sep 202688

Download this table (CSV)

When plumbing permits are filed

By calendar month, 100 = an average month (the thin line). March is the busiest (119), February the quietest (76). A busy month at the permit counter usually means a longer wait for a contractor.

January: 103 (100 = an average month)February: 76 (100 = an average month)March: 119 (100 = an average month)119April: 94 (100 = an average month)May: 97 (100 = an average month)June: 105 (100 = an average month)July: 110 (100 = an average month)August: 96 (100 = an average month)September: 99 (100 = an average month)October: 106 (100 = an average month)November: 86 (100 = an average month)December: 109 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January103
February76
March119
April94
May97
June105
July110
August96
September99
October106
November86
December109

Download this table (CSV)

How many plumbing permits get finished

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends.

MeasureValue
Permits issued Oct 2024–Sep 2025907
Finished77.6%
Expired21.9%

Download this table (CSV)

What a plumbing permit is declared at

The value written on the permit at application, from 1,864 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$3,450
Middle half$2,360–$5,000

Download this table (CSV)

ZIP codes with the most plumbing permits

Counted at the property's ZIP code. Share is the part of the city's 1,867 plumbing permits.

ZIP codePermitsShare
8024149927%
8060246125%
8022945524%
8023331417%
802601277%
800237under 1%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Plumbing - Water Heater1,20865%
Plumbing - Sewer Repair38621%
Plumbing - Water Pipe New/Alteration684%
Plumbing - Water Heater Tankless503%
Mechanical - Gas Piping473%
Plumbing - Water Softner System322%
Plumbing - New Irrigation Meter/Backflow251%
Plumbing - Plumbing System New/Alteration231%
Plumbing - Drain Vent/Pipe9under 1%
Plumbing - Water Connection6under 1%

Download this table (CSV)

How Thornton compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Plumbing permits for other places in Denver and Boulder. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Thornton Permits map service, layer Building Permits (2017-present), read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building and trade permits the City of Thornton issues inside the city limits, including the part of Thornton in Weld County, except re-roof, fence and backflow/irrigation permits, which the city's published file stops carrying after July 2025 and are left out of every month. Unincorporated Adams County, Northglenn, Westminster and Federal Heights issue their own permits and are not in this file. Right-of-way permits are left out.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Thornton.
  • Re-roof, fence and backflow permits are not counted: the city's published file drops them after July 2025 (re-roofs went from hundreds a month to almost none), so counting the earlier ones would show a collapse that did not happen. Roofing is not covered on these pages for that reason.
  • The file has a status but no final date, so we can say how many permits finished but not how long they took.
  • Value is the valuation declared on the permit application, not the final cost of the job.
  • Status Closed counts as finished; Expired and Expired Closed count as expired.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Plumbing permits in the City of Thornton, CO", https://contractorrecords.com/thornton/plumbing-permits, data through September 2026, from the City of Thornton Development Department building-permit records.

Link to a table: By month · Season · How many get finished · Declared value · By ZIP code · Permit types.

Download the tables (CSV): Plumbing permits by month · Plumbing permits by calendar month (index) · Plumbing permits: finished share · Plumbing permits: declared value · Plumbing permits by ZIP code · Plumbing permits by permit type.

Common questions

  • How many plumbing permits does Thornton issue a year?About 934 a year in the City of Thornton: 1,867 permits issued October 2024 through September 2026, 960 of them in the last 12 months.
  • When do people in Thornton file the most plumbing permits?March (119 against an average month of 100); February is the quietest (76). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most plumbing permits in Thornton?80241, with 499 of the 1,867 (27%); then 80602 (461).