Garage, shed and shade structure permits in unincorporated Alachua County, FL

Data through September 2026 · updated 20 Oct 2026

501 garage, shed and shade structure permits were issued in unincorporated Alachua County, October 2024 through September 2026: about 250 a year and 3% of all permits. 232 garage, shed and shade structure permits in the last 12 months (Oct 2025–Sep 2026), 14% fewer than the 269 in the 12 months before. The busiest month is August. The usual one took 75 days from issue to the county's final. 32608 has the most, 116.

501permits issued
232last 12 months
Augbusiest month
75days, usual issue to final
86%finished
Sep 2026records through

Garage, shed and shade structure permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 22Oct2024Nov 2024: 26Dec 2024: 15Jan 2025: 16Jan2025Feb 2025: 24Mar 2025: 23Apr 2025: 25May 2025: 27Jun 2025: 25Jul 2025: 18JulAug 2025: 33Sep 2025: 15Oct 2025: 17Nov 2025: 10Dec 2025: 19Jan 2026: 14Jan2026Feb 2026: 20Mar 2026: 28Apr 2026: 20May 2026: 13Jun 2026: 23Jul 2026: 18JulAug 2026: 24Sep 2026: 26
The same numbers as a table
MonthPermits
Oct 202422
Nov 202426
Dec 202415
Jan 202516
Feb 202524
Mar 202523
Apr 202525
May 202527
Jun 202525
Jul 202518
Aug 202533
Sep 202515
Oct 202517
Nov 202510
Dec 202519
Jan 202614
Feb 202620
Mar 202628
Apr 202620
May 202613
Jun 202623
Jul 202618
Aug 202624
Sep 202626

Download this table (CSV)

When garage, shed and shade structure permits are filed

By calendar month, 100 = an average month (the thin line). August is the busiest (137), January the quietest (72). A busy month at the permit counter usually means a longer wait for a contractor.

January: 72 (100 = an average month)February: 105 (100 = an average month)March: 122 (100 = an average month)April: 108 (100 = an average month)May: 96 (100 = an average month)June: 115 (100 = an average month)July: 86 (100 = an average month)August: 137 (100 = an average month)137September: 98 (100 = an average month)October: 93 (100 = an average month)November: 86 (100 = an average month)December: 81 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January72
February105
March122
April108
May96
June115
July86
August137
September98
October93
November86
December81

Download this table (CSV)

How long a garage, shed and shade structure permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 229 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025269
Finished86.2%
Expired11.2%
Usual days, issue to final75
Middle half, days35–136

Download this table (CSV)

ZIP codes with the most garage, shed and shade structure permits

Counted at the property's ZIP code. Share is the part of the county's 501 garage, shed and shade structure permits.

ZIP codePermitsShare
3260811623%
326696112%
326065110%
326155110%
32618408%
32640377%
32607326%
32653204%
32609194%
32643184%

Download this table (CSV)

The county's own permit types

How the county filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Building Permit / Accessory Structure33066%
Building Permit / Aluminum17134%

Download this table (CSV)

Nearby permit data

Garage, shed and shade structure permits for other places in Gainesville. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Alachua County Growth Management, CitizenServe building permits (ArcGIS: BuildingPermitsCS), read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits the Alachua County Building Division issues for unincorporated land only, plus the small towns that contract with the county for building services. Gainesville, Alachua, High Springs and Newberry run their own permit offices and are not in this file; Gainesville has its own page on this site.

  • The county's file lists the company that pulled each permit, but this page shows permit counts only: there are no contractor lists, rankings or firm pages for this county.
  • The file has no declared job value, so we show no costs.
  • A final date is the county's close date on a permit marked Closed, Complete or Finaled. Permits closed after expiring or closed administratively count as expired.
  • The file has no homes-versus-other flag, so a permit counts as a home when its parcel's Florida property-use code is residential (single-family, mobile home, condo or small multifamily). The ZIP code also comes from the parcel.
  • Window and door replacements are counted under remodels and repairs.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Garage, shed and shade structure permits in unincorporated Alachua County, FL", https://contractorrecords.com/alachua-county/accessory-permits, data through September 2026, from Alachua County Growth Management building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code · Permit types.

Download the tables (CSV): Garages, sheds & shade structures permits by month · Garages, sheds & shade structures permits by calendar month (index) · Garages, sheds & shade structures permits: days to final · Garages, sheds & shade structures permits by ZIP code · Garages, sheds & shade structures permits by permit type.

Common questions

  • How many garage, shed and shade structure permits does Alachua County issue a year?About 250 a year in unincorporated Alachua County: 501 permits issued October 2024 through September 2026, 232 of them in the last 12 months.
  • How long does a garage, shed and shade structure permit take in Alachua County?The usual one took 75 days from issue to the county's final inspection, and the middle half took 35 to 136 days (229 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Alachua County file the most garage, shed and shade structure permits?August (137 against an average month of 100); January is the quietest (72). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most garage, shed and shade structure permits in Alachua County?32608, with 116 of the 501 (23%); then 32669 (61).