How long do permits take in unincorporated Alachua County, FL?

Data through September 2026 · updated 20 Oct 2026

The usual permit in unincorporated Alachua County takes 33 days from issue to the county's final inspection; the middle half take 16 to 79 days. That is from 6,908 permits issued Oct 2024–Sep 2025 that reached a final. Roofing permits are quickest at 24 days; new home permits take longest at 194 days. This is the time to finish the work and close the permit, not the wait for approval.

33days, usual issue to final
16–79days, middle half
89%finished
6,908permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the county to approve the plans. Ask the county for its current review times.

Finishing the work (measured here): issue → final. From the day the county issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedExpiredUsual days to finalMiddle half (days)
Roofing2,21196.8%3.0%2414–41
HVAC1,33782.0%17.4%2613–53
Plumbing1,07185.2%13.3%249–57
Remodels & repairs82792.7%6.2%5429–112
Electrical89489.1%10.1%3211–65
New homes34785.9%3.5%194132–267
Garages, sheds & shade structures26986.2%11.2%7535–136
Pools & spas10686.8%8.5%183134–240
Other55683.8%6.3%7631–145

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the county's final.

How long does a roof replacement take in Alachua County, from permit to final?

The usual roofing permit in unincorporated Alachua County takes 24 days from issue to final; the middle half take 14 to 41 days (2,138 permits with a final date, issued Oct 2024–Sep 2025). 97% of the 2,211 permits issued then have finished and 3% expired. Alachua County roofing permits →

How long does an HVAC replacement take in Alachua County, from permit to final?

The usual HVAC permit in unincorporated Alachua County takes 26 days from issue to final; the middle half take 13 to 53 days (1,046 permits with a final date, issued Oct 2024–Sep 2025). 82% of the 1,337 permits issued then have finished and 17% expired. Alachua County HVAC permits →

How long does plumbing work take in Alachua County, from permit to final?

The usual plumbing permit in unincorporated Alachua County takes 24 days from issue to final; the middle half take 9 to 57 days (900 permits with a final date, issued Oct 2024–Sep 2025). 85% of the 1,071 permits issued then have finished and 13% expired. Alachua County plumbing permits →

How long does a remodel take in Alachua County, from permit to final?

The usual remodel and repair permit in unincorporated Alachua County takes 54 days from issue to final; the middle half take 29 to 112 days (760 permits with a final date, issued Oct 2024–Sep 2025). 93% of the 827 permits issued then have finished and 6% expired. Alachua County remodel and repair permits →

How long does electrical work take in Alachua County, from permit to final?

The usual electrical permit in unincorporated Alachua County takes 32 days from issue to final; the middle half take 11 to 65 days (783 permits with a final date, issued Oct 2024–Sep 2025). 89% of the 894 permits issued then have finished and 10% expired. Alachua County electrical permits →

How long does building a new home take in Alachua County, from permit to final?

The usual new home permit in unincorporated Alachua County takes 194 days from issue to final; the middle half take 132 to 267 days (296 permits with a final date, issued Oct 2024–Sep 2025). 86% of the 347 permits issued then have finished and 4% expired. Alachua County new home permits →

How long does a garage, shed or patio cover take in Alachua County, from permit to final?

The usual garage, shed and shade structure permit in unincorporated Alachua County takes 75 days from issue to final; the middle half take 35 to 136 days (229 permits with a final date, issued Oct 2024–Sep 2025). 86% of the 269 permits issued then have finished and 11% expired. Alachua County garage, shed and shade structure permits →

How long does a pool or spa take in Alachua County, from permit to final?

The usual pool and spa permit in unincorporated Alachua County takes 183 days from issue to final; the middle half take 134 to 240 days (91 permits with a final date, issued Oct 2024–Sep 2025). 87% of the 106 permits issued then have finished and 8% expired. Alachua County pool and spa permits →

How long does a demolition take in Alachua County, from permit to final?

The usual demolition permit in unincorporated Alachua County takes 35 days from issue to final; the middle half take 14 to 74 days (66 permits with a final date, issued Oct 2024–Sep 2025).

How long does a solar installation take in Alachua County, from permit to final?

The usual solar permit in unincorporated Alachua County takes 61 days from issue to final; the middle half take 28 to 125 days (82 permits with a final date, issued Oct 2024–Sep 2025).

How Alachua County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

How long permits take for other places in Gainesville. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Alachua County Growth Management, CitizenServe building permits (ArcGIS: BuildingPermitsCS), read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits the Alachua County Building Division issues for unincorporated land only, plus the small towns that contract with the county for building services. Gainesville, Alachua, High Springs and Newberry run their own permit offices and are not in this file; Gainesville has its own page on this site.

  • The county's file lists the company that pulled each permit, but this page shows permit counts only: there are no contractor lists, rankings or firm pages for this county.
  • The file has no declared job value, so we show no costs.
  • A final date is the county's close date on a permit marked Closed, Complete or Finaled. Permits closed after expiring or closed administratively count as expired.
  • The file has no homes-versus-other flag, so a permit counts as a home when its parcel's Florida property-use code is residential (single-family, mobile home, condo or small multifamily). The ZIP code also comes from the parcel.
  • Window and door replacements are counted under remodels and repairs.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in unincorporated Alachua County, FL?", https://contractorrecords.com/alachua-county/how-long-does-a-permit-take, data through September 2026, from Alachua County Growth Management building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Alachua County?From issue to final inspection, the usual permit takes 33 days (middle half 16 to 79 days), from 6,908 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the county for its current review times.
  • Which permits finish fastest in Alachua County?Roofing permits, at 24 days. The slowest are new home permits, at 194 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Alachua County?89% of the 7,889 permits issued Oct 2024–Sep 2025 have finished; 9% expired without a final and the rest are still open.
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.