Plumbing permits in the City of Carlsbad, CA

Data through December 2023 · updated 19 Oct 2026

981 plumbing permits were issued in the City of Carlsbad, April 2022 through December 2023: about 561 a year and 12% of all permits. The busiest month is February. The usual one took 142 days from issue to the city's final. 92009 has the most, 440.

981permits issued
566last 12 months on file
Febbusiest month
142days, usual issue to final
46%finished
Dec 2023records through

Plumbing permits by month

Permits issued each month, April 2022 through December 2023.

Apr 2022: 63Apr2022May 2022: 45Jun 2022: 47Jul 2022: 56JulAug 2022: 32Sep 2022: 53Oct 2022: 45Nov 2022: 33Dec 2022: 41Jan 2023: 48Jan2023Feb 2023: 59Mar 2023: 45Apr 2023: 47May 2023: 67Jun 2023: 47Jul 2023: 33JulAug 2023: 57Sep 2023: 43Oct 2023: 38Nov 2023: 51Dec 2023: 31
The same numbers as a table
MonthPermits
Apr 202263
May 202245
Jun 202247
Jul 202256
Aug 202232
Sep 202253
Oct 202245
Nov 202233
Dec 202241
Jan 202348
Feb 202359
Mar 202345
Apr 202347
May 202367
Jun 202347
Jul 202333
Aug 202357
Sep 202343
Oct 202338
Nov 202351
Dec 202331

Download this table (CSV)

When plumbing permits are filed

By calendar month, 100 = an average month (the thin line). February is the busiest (126), December the quietest (77). A busy month at the permit counter usually means a longer wait for a contractor.

January: 103 (100 = an average month)February: 126 (100 = an average month)126March: 96 (100 = an average month)April: 118 (100 = an average month)May: 120 (100 = an average month)June: 101 (100 = an average month)July: 95 (100 = an average month)August: 95 (100 = an average month)September: 103 (100 = an average month)October: 89 (100 = an average month)November: 90 (100 = an average month)December: 77 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January103
February126
March96
April118
May120
June101
July95
August95
September103
October89
November90
December77

Download this table (CSV)

How long a plumbing permit takes

Permits issued Apr 2022–Dec 2022, at least 12 months before the file ends. Usual days is the middle permit among the 190 with a final date.

MeasureValue
Permits issued Apr 2022–Dec 2022415
Finished45.8%
Expired0.0%
Usual days, issue to final142
Middle half, days62–229

Download this table (CSV)

ZIP codes with the most plumbing permits

Counted at the property's ZIP code. Share is the part of the city's 981 plumbing permits.

ZIP codePermitsShare
9200944045%
9201122723%
9200819620%
9201011812%

Download this table (CSV)

How Carlsbad compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Plumbing permits for other places in San Diego. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Carlsbad GIS BuildingPermits (BLDS format, ArcGIS FeatureServer), read 19 Oct 2026. We count permits issued April 2022 through December 2023; denied and withdrawn permits are left out.

Building permits the City of Carlsbad issued inside the city limits, residential and commercial, for applications filed in 2022 and 2023. Carlsbad issues one building permit per job, so re-roofs, solar, water heaters and HVAC change-outs are building permits here. Neighbouring Oceanside, Vista, San Marcos, Encinitas and unincorporated San Diego County are not in this file.

  • The city's open permit layer holds only permits applied for in 2022 and 2023 and was last updated in January 2024, so these pages end with December 2023. Newer Carlsbad permits are only in the city's own permit lookup.
  • Because the layer starts with 2022 applications, permits applied for in 2021 and issued later are missing; the window starts in April 2022, when the monthly counts settle. Long-review jobs such as new homes are undercounted in the first months.
  • The file names no contractor, so there are no contractor lists, rankings or firm pages for Carlsbad.
  • The file has no declared job value, so we show no costs.
  • The file has no work-type field. The kind of work is read from the permit description (re-roof, solar PV, water heater, furnace and so on); commercial permits are counted as other unless they are roofing, solar or pools.
  • A final date is the city's completed date on a permit closed as finaled. Status is as of January 2024, so permits issued late in 2023 had had little time to finish.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Plumbing permits in the City of Carlsbad, CA", https://contractorrecords.com/carlsbad/plumbing-permits, data through December 2023, from City of Carlsbad Building Division building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code.

Download the tables (CSV): Plumbing permits by month · Plumbing permits by calendar month (index) · Plumbing permits: days to final · Plumbing permits by ZIP code.

Common questions

  • How many plumbing permits does Carlsbad issue a year?About 561 a year in the City of Carlsbad: 981 permits issued April 2022 through December 2023, 566 of them in the last 12 months on file (to December 2023).
  • How long does a plumbing permit take in Carlsbad?The usual one took 142 days from issue to the city's final inspection, and the middle half took 62 to 229 days (190 permits issued Apr 2022–Dec 2022 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Carlsbad file the most plumbing permits?February (126 against an average month of 100); December is the quietest (77). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most plumbing permits in Carlsbad?92009, with 440 of the 981 (45%); then 92011 (227).