How long building permits take in US cities (2026 data)

Across the 43 US cities and counties in our permit file, the usual electrical permit on a home is signed off 71 days after it is issued, and the usual remodel permit 168 days. The same permit varies even more from place to place: an electrical permit closes in 15 days in Medford, OR and takes 233 in Bismarck, ND; a remodel runs from 59 days in Orlando, FL to 391 in Cleveland, OH.

By Contractor Records · data through October 20, 2026

  • Order of trades. Comparing each trade's usual figure across cities: roofing 41 days, solar 70 days, electrical 71 days, plumbing 75 days, HVAC 76 days, remodel 168 days, new home 238 days.
  • Electrical permits: closed within 30 days in 4 cities and after more than 120 days in 10 cities, out of 37.
  • Across all 216 city-and-trade figures, 27 are 30 days or less and 4 are over a year: new home in Miami, FL (648 days); HVAC in New York City, NY (417 days); new home in Minneapolis, MN (396 days); remodel in Cleveland, OH (391 days).

The figures below are the usual number of days between the day a permit was issued and the day the permit office recorded it as finished (final inspection, closeout or letter of completion), for permits on houses and small residential buildings. "Usual" is the median: half of the permits took less time, half took more.

The short version: each trade across cities

"Usual across cities" is the middle of the city figures, so a big city counts the same as a small one. The fastest and slowest city link to that city's own timing page.

Trade Cities Usual across cities (days) Fastest city (days) Slowest city (days)
Electrical 37 71 Medford, OR (15) Bismarck, ND (233)
Plumbing 35 75 Sacramento County, CA (8) Naperville, IL (360)
HVAC 34 76 Ames, IA (7) New York City, NY (417)
Roofing 20 41 Elk Grove, CA (15) St. Louis, MO (294)
Remodel 36 168 Orlando, FL (59) Cleveland, OH (391)
New home 24 238 Greensboro, NC (156) Miami, FL (648)
Solar 30 70 Bellingham, WA (22) San Francisco, CA (349)

Every city, every trade

A dash means the city has no such trade in its file, or the cell did not meet the rules in the method box (fewer than 200 permits, or most permits a year old never closed). City names link to that city's "how long permits take" page, which shows every trade it has.

City Electrical Plumbing HVAC Roofing Remodel New home Solar Notes
Ames, IA 93 94 7 — 97 — —
Anaheim, CA 35 20 64 16 180 — 103
Arlington, VA 99 75 148 — 112 291 47 county permits
Austin, TX 76 75 118 — 67 356 —
Bellevue, WA 45 190 76 41 216 — —
Bellingham, WA 89 — 24 — — 326 22
Bend, OR 31 67 28 — 88 220 56
Bismarck, ND 233 277 142 — 272 351 — remodel includes additions
Boulder, CO 55 — 76 41 141 — 72
Burlington, VT 84 — — 159 315 — — file ends Mar 2026; roofing includes siding
Cape Coral, FL 25 71 41 39 99 232 49 21 months of data
Cary, NC 41 10 29 — 84 176 45
Cincinnati, OH — 90 278 — 340 — —
Citrus Heights, CA 54 14 62 21 101 — 55 remodel includes additions
Cleveland, OH 146 234 142 91 391 344 —
Columbus, OH 73 111 115 — 155 252 —
Elk Grove, CA 49 23 50 15 79 175 109 remodel includes additions
Greensboro, NC 52 121 48 — 126 156 103
Henderson, NV 29 14 22 — 91 181 25
Honolulu, HI 155 — — — 265 295 102 file ends Jun 2025
Marin County, CA 124 53 96 58 272 — — unincorporated county
Medford, OR 15 12 31 — — 176 34 remodel includes additions
Mesa, AZ 23 33 — — — 201 30
Miami, FL 184 127 73 38 182 648 52
Minneapolis, MN — 113 85 85 161 396 76
Naperville, IL 144 360 — — 175 — 107 timed only in the permit system used from 2024
New York City, NY 162 350 417 — — — 144 HVAC includes boilers
Orlando, FL 127 123 91 27 59 203 42
Palo Alto, CA 70 20 69 48 187 — 109
Provo, UT — — — — 227 254 —
Raleigh, NC 91 133 121 — — — —
Sacramento County, CA 56 8 56 19 85 171 50 unincorporated county; remodel includes additions
Saint Paul, MN 54 77 150 128 206 — 69 file ends Jun 2025
San Diego, CA 71 41 103 — 162 358 72
San Diego County, CA 63 62 163 41 74 225 81 unincorporated county
San Francisco, CA — — — 36 180 — 349
Seattle, WA 44 — 66 67 — — 43 HVAC = furnaces; heat pumps filed separately
Somerville, MA 112 196 365 — 286 — 91
St. Louis, MO — — — 294 361 — —
Sugar Land, TX — 23 — — — — 66
Waco, TX 121 127 112 41 300 174 136 file ends May 2026
Wheaton, IL 159 34 — — 132 — — finish = last passed inspection
Wilmington, NC 54 78 27 — 231 244 71

What makes a city slow or fast here

The clock stops when the office records a final, not when the contractor packs up. Two things stretch it that have nothing to do with how fast the work went:

  • Who books the final. Where the homeowner or contractor must call for the final inspection, permits sit open after the job is done. Where the office closes small trade permits on a single visit, the clock is short.
  • Bundled jobs. A new-home or remodel permit stays open until the whole house passes, so it runs for months by design.

So a long figure is a reason to ask your contractor how and when the final will be booked, not proof that contractors in that city are slow. Our guide to why a permit is still open covers what to do when yours is.

How we know this

What is counted. Permits on houses and small residential buildings (as each city's data allows) that name a contractor, issued in the city's data window (three years to the end of September 2026 in most cities; see the Notes column). The usual days figure is a Kaplan-Meier median from issue to the recorded finish date, so permits still open count as "not finished yet" instead of being dropped.

What is left out. Cities that do not record the date a permit was finished (Albuquerque, Cambridge, Chicago, Colorado Springs, Denton, Pittsburgh, Scottsdale and Tyler, where any timing is an estimate from permit age) and Nashville, which has no completion dates. A city-and-trade cell is shown only when the trade has 200 or more permits and, where the city records it, at least half of its permits a year or more old were finished. Denver's open data no longer carries final dates for new homes and remodels.

Caveats. Trade names differ by city: the column is the closest match, and the Notes column says where it covers more (remodel with additions) or less (Seattle's HVAC is furnaces; heat pumps are a separate permit). Saint Paul and Honolulu files end in June 2025, Scottsdale's in December 2025, Burlington's in March 2026 and Waco's in May 2026. San Diego County, Marin County and Sacramento County are unincorporated-county permits only. Wheaton's finish date is its last passed inspection.

Regenerating. The tables are built by seo/tools/studies.py from the same files as every city page; rerun it after a data refresh.

Numbers come from public permit records in 53 cities, data through October 20, 2026. Nobody paid to be on this page and nobody can.

Pick your city and see every contractor's finished share and speed →

Questions

  • How long does a building permit take to close?

    On homes, the usual figure across the cities we measure runs from about six weeks for roofing to most of a year for a new home; the summary table at the top of this page has the exact figure for each trade. In Seattle the usual electrical permit closes 44 days after it is issued; in Austin the usual remodel permit takes 67 days.

  • Is this the time it takes to get a permit approved?

    No. Every figure here starts on the day the permit was issued and ends on the day the permit office recorded the final inspection or closeout. Plan review before the permit is issued is not counted, and neither is any wait between signing a contract and filing.

  • Why does the same kind of permit take so much longer in one city than another?

    The clock stops when the office records a final, so it measures the whole job plus the time to book and record the final inspection. Offices that issue simple trade permits and final them on one visit show short times (Medford's usual electrical permit: 15 days); offices where finals are often left for later show long ones (New York City's HVAC and boiler permits: 417 days).

  • Why are some cities missing?

    Some cities record only whether a permit is finished today, not the date it was finished, so their timing would be an estimate; we leave those out of this study. Nashville's file has no completion dates at all. The others are left out trade by trade when they have fewer than 200 permits or when most permits a year old were never closed.

  • Can I use these figures in an article?

    Yes. Link to this page as the source and give the data window. Each city row links to that city's own timing page with more trades and the method in full.