Home addition permits in the City of Charleston, SC

Data through September 2026 · updated 19 Oct 2026

591 home addition permits were issued in the City of Charleston, October 2024 through September 2026: about 296 a year and 8% of all permits. 308 home addition permits in the last 12 months (Oct 2025–Sep 2026), 9% more than the 283 in the 12 months before. The busiest month is May. The usual one took 256 days from issue to the city's final. 29407 has the most, 123.

What this file covers: The city's layer holds building permits only, so trade permits are few.

591permits issued
308last 12 months
Maybusiest month
256days, usual issue to final
66%finished
$99,023usual declared value
Sep 2026records through

Home addition permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 25Oct2024Nov 2024: 24Dec 2024: 24Jan 2025: 16Jan2025Feb 2025: 22Mar 2025: 28Apr 2025: 25May 2025: 33Jun 2025: 18Jul 2025: 25JulAug 2025: 24Sep 2025: 19Oct 2025: 25Nov 2025: 24Dec 2025: 24Jan 2026: 13Jan2026Feb 2026: 20Mar 2026: 22Apr 2026: 27May 2026: 33Jun 2026: 37Jul 2026: 23JulAug 2026: 29Sep 2026: 31
The same numbers as a table
MonthPermits
Oct 202425
Nov 202424
Dec 202424
Jan 202516
Feb 202522
Mar 202528
Apr 202525
May 202533
Jun 202518
Jul 202525
Aug 202524
Sep 202519
Oct 202525
Nov 202524
Dec 202524
Jan 202613
Feb 202620
Mar 202622
Apr 202627
May 202633
Jun 202637
Jul 202623
Aug 202629
Sep 202631

Download this table (CSV)

When home addition permits are filed

By calendar month, 100 = an average month (the thin line). May is the busiest (134), January the quietest (59). A busy month at the permit counter usually means a longer wait for a contractor.

January: 59 (100 = an average month)February: 85 (100 = an average month)March: 102 (100 = an average month)April: 106 (100 = an average month)May: 134 (100 = an average month)134June: 112 (100 = an average month)July: 97 (100 = an average month)August: 108 (100 = an average month)September: 102 (100 = an average month)October: 102 (100 = an average month)November: 97 (100 = an average month)December: 97 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January59
February85
March102
April106
May134
June112
July97
August108
September102
October102
November97
December97

Download this table (CSV)

How long a home addition permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 79 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025283
Finished66.1%
Expired0.0%
Usual days, issue to final256
Middle half, days213–344

Download this table (CSV)

What a home addition permit is declared at

The value written on the permit at application, from 590 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$99,023
Middle half$30,000–$245,000

Download this table (CSV)

ZIP codes with the most home addition permits

Counted at the property's ZIP code. Share is the part of the city's 591 home addition permits.

ZIP codePermitsShare
2940712321%
294039316%
294127913%
294926311%
294145810%
29401529%
29455295%
294051under 1%

Download this table (CSV)

How these numbers are made

Source: City of Charleston GIS, Permits All Issued (Dashboard View), EnerGov layer External/Applications 1134, read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building permits the City of Charleston Department of Permitting & Inspections issues inside the city limits only: the Peninsula, West Ashley, James Island, Johns Island, Daniel Island and Cainhoy parts of the city. North Charleston, Mount Pleasant, Summerville and unincorporated Charleston County run their own permit offices and are not in this file. Business-license certificates of occupancy, tree removal, rental registrations and sidewalk dining permits are left out.

  • The city's public permit layer names no contractor, so there are no contractor lists, rankings or firm pages for Charleston.
  • The layer holds building permits only: the city's separate electrical, plumbing and mechanical permits are not published, so trade counts come only from single-family alteration permits whose description names one trade (roofing above all) and are far below the real number of trade jobs.
  • The value is the valuation on the permit application, which sets the fee. It is not a final cost.
  • Many permits stay marked Issued after the work passed its final inspection. A permit counts as finished if the city marked it Completed, recorded a finaled date or recorded a passed final inspection; only those with a finaled date add days.
  • Permits the city marked void or that were cancelled or denied are not counted.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Home addition permits in the City of Charleston, SC", https://contractorrecords.com/charleston-sc/addition-permits, data through September 2026, from the City of Charleston Department of Permitting & Inspections building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code.

Download the tables (CSV): Additions permits by month · Additions permits by calendar month (index) · Additions permits: days to final · Additions permits: declared value · Additions permits by ZIP code.

Common questions

  • How many home addition permits does Charleston issue a year?About 296 a year in the City of Charleston: 591 permits issued October 2024 through September 2026, 308 of them in the last 12 months.
  • How long does a home addition permit take in Charleston?The usual one took 256 days from issue to the city's final inspection, and the middle half took 213 to 344 days (79 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Charleston file the most home addition permits?May (134 against an average month of 100); January is the quietest (59). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most home addition permits in Charleston?29407, with 123 of the 591 (21%); then 29403 (93).