Data through September 2026 · updated 19 Oct 2026
The usual permit in the City of Charleston takes 202 days from issue to the city's final inspection; the middle half take 134 to 324 days. That is from 1,122 permits issued Oct 2024–Sep 2025 that reached a final. New home permits are quickest at 208 days; home addition permits take longest at 256 days. This is the time to finish the work and close the permit, not the wait for approval.
“How long does a permit take?” can mean two waits. This page measures the second one.
Getting the permit (not measured): application → issue, the wait for the city to approve the plans. Ask the city for its current review times.
Finishing the work (measured here): issue → final. From the day the city issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.
Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.
| Kind of work | Permits | Finished | Expired | Usual days to final | Middle half (days) |
|---|---|---|---|---|---|
| Remodels & repairs | 1,325 | 55.9% | 0.2% | 212 | 114–344 |
| New homes | 508 | 72.2% | 0.0% | 208 | 170–287 |
| Additions | 283 | 66.1% | 0.0% | 256 | 213–344 |
| Demolition | 238 | 12.2% | 0.4% | – | – |
| Garages, sheds & shade structures | 205 | 43.9% | 0.0% | – | – |
| Other | 989 | 54.6% | 0.2% | 166 | 98–343 |
Each kind of work on its own, issue to the city's final.
The usual remodel and repair permit in the City of Charleston takes 212 days from issue to final; the middle half take 114 to 344 days (290 permits with a final date, issued Oct 2024–Sep 2025). 56% of the 1,325 permits issued then have finished and under 1% expired. Charleston remodel and repair permits →
The usual new home permit in the City of Charleston takes 208 days from issue to final; the middle half take 170 to 287 days (332 permits with a final date, issued Oct 2024–Sep 2025). 72% of the 508 permits issued then have finished and 0% expired. Charleston new home permits →
The usual home addition permit in the City of Charleston takes 256 days from issue to final; the middle half take 213 to 344 days (79 permits with a final date, issued Oct 2024–Sep 2025). 66% of the 283 permits issued then have finished and 0% expired. Charleston home addition permits →
From our cross-city data studies: the same measure, read the same way, for every city we cover.
Source: City of Charleston GIS, Permits All Issued (Dashboard View), EnerGov layer External/Applications 1134, read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.
Building permits the City of Charleston Department of Permitting & Inspections issues inside the city limits only: the Peninsula, West Ashley, James Island, Johns Island, Daniel Island and Cainhoy parts of the city. North Charleston, Mount Pleasant, Summerville and unincorporated Charleston County run their own permit offices and are not in this file. Business-license certificates of occupancy, tree removal, rental registrations and sidewalk dining permits are left out.
Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →
Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:
Contractor Records, "How long do permits take in the City of Charleston, SC?", https://contractorrecords.com/charleston-sc/how-long-does-a-permit-take, data through September 2026, from the City of Charleston Department of Permitting & Inspections building-permit records.Link to a table: By kind of work · Each kind of permit.
Download the tables (CSV): Days to final by kind of work.