New home permits in the City of Charleston, SC

Data through September 2026 · updated 19 Oct 2026

1,142 new home permits were issued in the City of Charleston, October 2024 through September 2026: about 571 a year and 15% of all permits. 634 new home permits in the last 12 months (Oct 2025–Sep 2026), 25% more than the 508 in the 12 months before. The busiest month is July. The usual one took 208 days from issue to the city's final. 29492 has the most, 411.

What this file covers: The city's layer holds building permits only, so trade permits are few.

1,142permits issued
634last 12 months
Julbusiest month
208days, usual issue to final
72%finished
$266,275usual declared value
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 25Oct2024Nov 2024: 13Dec 2024: 19Jan 2025: 30Jan2025Feb 2025: 32Mar 2025: 17Apr 2025: 71May 2025: 27Jun 2025: 23Jul 2025: 106JulAug 2025: 61Sep 2025: 84Oct 2025: 90Nov 2025: 31Dec 2025: 62Jan 2026: 70Jan2026Feb 2026: 59Mar 2026: 58Apr 2026: 45May 2026: 52Jun 2026: 47Jul 2026: 51JulAug 2026: 35Sep 2026: 34
The same numbers as a table
MonthPermits
Oct 202425
Nov 202413
Dec 202419
Jan 202530
Feb 202532
Mar 202517
Apr 202571
May 202527
Jun 202523
Jul 2025106
Aug 202561
Sep 202584
Oct 202590
Nov 202531
Dec 202562
Jan 202670
Feb 202659
Mar 202658
Apr 202645
May 202652
Jun 202647
Jul 202651
Aug 202635
Sep 202634

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). July is the busiest (165), November the quietest (46). A busy month at the permit counter usually means a longer wait for a contractor.

January: 105 (100 = an average month)February: 96 (100 = an average month)March: 79 (100 = an average month)April: 122 (100 = an average month)May: 83 (100 = an average month)June: 74 (100 = an average month)July: 165 (100 = an average month)165August: 101 (100 = an average month)September: 124 (100 = an average month)October: 121 (100 = an average month)November: 46 (100 = an average month)December: 85 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January105
February96
March79
April122
May83
June74
July165
August101
September124
October121
November46
December85

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 332 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025508
Finished72.2%
Expired0.0%
Usual days, issue to final208
Middle half, days170–287

Download this table (CSV)

What a new home permit is declared at

The value written on the permit at application, from 1,141 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$266,275
Middle half$151,581–$355,744

Download this table (CSV)

ZIP codes with the most new home permits

Counted at the property's ZIP code. Share is the part of the city's 1,142 new home permits.

ZIP codePermitsShare
2949241136%
2945517215%
2941413912%
29412565%
29403545%
29407514%
29401212%
294052under 1%

Download this table (CSV)

How Charleston compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Charleston GIS, Permits All Issued (Dashboard View), EnerGov layer External/Applications 1134, read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building permits the City of Charleston Department of Permitting & Inspections issues inside the city limits only: the Peninsula, West Ashley, James Island, Johns Island, Daniel Island and Cainhoy parts of the city. North Charleston, Mount Pleasant, Summerville and unincorporated Charleston County run their own permit offices and are not in this file. Business-license certificates of occupancy, tree removal, rental registrations and sidewalk dining permits are left out.

  • The city's public permit layer names no contractor, so there are no contractor lists, rankings or firm pages for Charleston.
  • The layer holds building permits only: the city's separate electrical, plumbing and mechanical permits are not published, so trade counts come only from single-family alteration permits whose description names one trade (roofing above all) and are far below the real number of trade jobs.
  • The value is the valuation on the permit application, which sets the fee. It is not a final cost.
  • Many permits stay marked Issued after the work passed its final inspection. A permit counts as finished if the city marked it Completed, recorded a finaled date or recorded a passed final inspection; only those with a finaled date add days.
  • Permits the city marked void or that were cancelled or denied are not counted.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in the City of Charleston, SC", https://contractorrecords.com/charleston-sc/new-home-permits, data through September 2026, from the City of Charleston Department of Permitting & Inspections building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits: declared value · New homes permits by ZIP code.

Common questions

  • How many new home permits does Charleston issue a year?About 571 a year in the City of Charleston: 1,142 permits issued October 2024 through September 2026, 634 of them in the last 12 months.
  • How long does a new home permit take in Charleston?The usual one took 208 days from issue to the city's final inspection, and the middle half took 170 to 287 days (332 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Charleston file the most new home permits?July (165 against an average month of 100); November is the quietest (46). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most new home permits in Charleston?29492, with 411 of the 1,142 (36%); then 29455 (172).