Data through September 2026 · updated 19 Oct 2026

4,041 plumbing permits were issued in the City of Fayetteville, October 2024 through September 2026: about 2,020 a year and 31% of all permits. 2,155 plumbing permits in the last 12 months (Oct 2025–Sep 2026), 14% more than the 1,886 in the 12 months before. The busiest month is March. The usual one took 129 days from issue to the city's final.

4,041permits issued
2,155last 12 months
Marbusiest month
129days, usual issue to final
83%finished
$7,200usual declared value
Sep 2026records through

Plumbing permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 173Oct2024Nov 2024: 191Dec 2024: 137Jan 2025: 153Jan2025Feb 2025: 124Mar 2025: 149Apr 2025: 206May 2025: 106Jun 2025: 177Jul 2025: 194JulAug 2025: 113Sep 2025: 163Oct 2025: 114Nov 2025: 118Dec 2025: 173Jan 2026: 148Jan2026Feb 2026: 212Mar 2026: 343Apr 2026: 204May 2026: 142Jun 2026: 152Jul 2026: 233JulAug 2026: 167Sep 2026: 149
The same numbers as a table
MonthPermits
Oct 2024173
Nov 2024191
Dec 2024137
Jan 2025153
Feb 2025124
Mar 2025149
Apr 2025206
May 2025106
Jun 2025177
Jul 2025194
Aug 2025113
Sep 2025163
Oct 2025114
Nov 2025118
Dec 2025173
Jan 2026148
Feb 2026212
Mar 2026343
Apr 2026204
May 2026142
Jun 2026152
Jul 2026233
Aug 2026167
Sep 2026149

Download this table (CSV)

When plumbing permits are filed

By calendar month, 100 = an average month (the thin line). March is the busiest (146), May the quietest (74). A busy month at the permit counter usually means a longer wait for a contractor.

January: 89 (100 = an average month)February: 100 (100 = an average month)March: 146 (100 = an average month)146April: 122 (100 = an average month)May: 74 (100 = an average month)June: 98 (100 = an average month)July: 127 (100 = an average month)August: 83 (100 = an average month)September: 93 (100 = an average month)October: 85 (100 = an average month)November: 92 (100 = an average month)December: 92 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January89
February100
March146
April122
May74
June98
July127
August83
September93
October85
November92
December92

Download this table (CSV)

How long a plumbing permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 1,557 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20251,886
Finished82.6%
Expired4.1%
Usual days, issue to final129
Middle half, days58–218

Download this table (CSV)

What a plumbing permit is declared at

The value written on the permit at application, from 4,028 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$7,200
Middle half$2,358–$12,250

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Plumbing: Inside City Residential2,00350%
Gas: Residential94223%
Plumbing: Water Heater Changeout3759%
Plumbing: Inside City Commercial3709%
Plumbing: Inside City Irrigation Residential1664%
Gas: Commercial1113%
Plumbing: Inside City Irrigation Commercial742%

Download this table (CSV)

How Fayetteville compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Fayetteville GIS: Permit layer (Permits MapServer layer 0, from the city's EnerGov permit system), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, plumbing, mechanical, electrical, gas, pool, demolition, sign and fire-protection permits the City of Fayetteville, Arkansas issues inside city limits. Plumbing permits the city issues for properties outside its limits (Farmington and other areas on city water), right-of-way, street closure, grading and vendor permits in the same file are not counted. Springdale, Johnson, Farmington and unincorporated Washington County run their own permit offices and are not in this file, and neither is Fayetteville, North Carolina.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Fayetteville.
  • A final date is the city's finalize date; a permit marked complete counts as finished.
  • The value is the job value declared on the permit.
  • Gas permits for furnaces and heaters count as HVAC; other gas permits count as plumbing. Lawn irrigation permits are plumbing permits in the city's file and count as plumbing.
  • Homes are permits whose type or work class names a residence (including HVAC and water heater change-outs and home decks, sheds and patio covers); commercial work counts as other.
  • The file has no ZIP code we can publish, so there are no ZIP code pages.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Plumbing permits in the City of Fayetteville, AR", https://contractorrecords.com/fayetteville-ar/plumbing-permits, data through September 2026, from City of Fayetteville Development Services, Building Safety Division building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types.

Download the tables (CSV): Plumbing permits by month · Plumbing permits by calendar month (index) · Plumbing permits: days to final · Plumbing permits: declared value · Plumbing permits by permit type.

Common questions

  • How many plumbing permits does Fayetteville issue a year?About 2,020 a year in the City of Fayetteville: 4,041 permits issued October 2024 through September 2026, 2,155 of them in the last 12 months.
  • How long does a plumbing permit take in Fayetteville?The usual one took 129 days from issue to the city's final inspection, and the middle half took 58 to 218 days (1,557 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Fayetteville file the most plumbing permits?March (146 against an average month of 100); May is the quietest (74). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.