New home permits in the City of Fayetteville, AR

Data through September 2026 · updated 19 Oct 2026

1,345 new home permits were issued in the City of Fayetteville, October 2024 through September 2026: about 672 a year and 10% of all permits. 737 new home permits in the last 12 months (Oct 2025–Sep 2026), 21% more than the 608 in the 12 months before. The busiest month is March. The usual one took 205 days from issue to the city's final.

1,345permits issued
737last 12 months
Marbusiest month
205days, usual issue to final
84%finished
$374,000usual declared value
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 79Oct2024Nov 2024: 60Dec 2024: 30Jan 2025: 65Jan2025Feb 2025: 41Mar 2025: 73Apr 2025: 39May 2025: 34Jun 2025: 45Jul 2025: 43JulAug 2025: 50Sep 2025: 49Oct 2025: 35Nov 2025: 30Dec 2025: 70Jan 2026: 43Jan2026Feb 2026: 112Mar 2026: 157Apr 2026: 72May 2026: 39Jun 2026: 54Jul 2026: 56JulAug 2026: 34Sep 2026: 35
The same numbers as a table
MonthPermits
Oct 202479
Nov 202460
Dec 202430
Jan 202565
Feb 202541
Mar 202573
Apr 202539
May 202534
Jun 202545
Jul 202543
Aug 202550
Sep 202549
Oct 202535
Nov 202530
Dec 202570
Jan 202643
Feb 2026112
Mar 2026157
Apr 202672
May 202639
Jun 202654
Jul 202656
Aug 202634
Sep 202635

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). March is the busiest (205), May the quietest (65). A busy month at the permit counter usually means a longer wait for a contractor.

January: 96 (100 = an average month)February: 137 (100 = an average month)March: 205 (100 = an average month)205April: 99 (100 = an average month)May: 65 (100 = an average month)June: 88 (100 = an average month)July: 88 (100 = an average month)August: 75 (100 = an average month)September: 75 (100 = an average month)October: 102 (100 = an average month)November: 80 (100 = an average month)December: 89 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January96
February137
March205
April99
May65
June88
July88
August75
September75
October102
November80
December89

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 513 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025608
Finished84.4%
Expired5.3%
Usual days, issue to final205
Middle half, days123–322

Download this table (CSV)

What a new home permit is declared at

The value written on the permit at application, from 1,345 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$374,000
Middle half$284,103–$448,693

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Residential Building: New Single-Family98673%
Residential Building: New Townhouse25519%
Residential Building: New Two-Family1048%

Download this table (CSV)

How Fayetteville compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Fayetteville GIS: Permit layer (Permits MapServer layer 0, from the city's EnerGov permit system), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, plumbing, mechanical, electrical, gas, pool, demolition, sign and fire-protection permits the City of Fayetteville, Arkansas issues inside city limits. Plumbing permits the city issues for properties outside its limits (Farmington and other areas on city water), right-of-way, street closure, grading and vendor permits in the same file are not counted. Springdale, Johnson, Farmington and unincorporated Washington County run their own permit offices and are not in this file, and neither is Fayetteville, North Carolina.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Fayetteville.
  • A final date is the city's finalize date; a permit marked complete counts as finished.
  • The value is the job value declared on the permit.
  • Gas permits for furnaces and heaters count as HVAC; other gas permits count as plumbing. Lawn irrigation permits are plumbing permits in the city's file and count as plumbing.
  • Homes are permits whose type or work class names a residence (including HVAC and water heater change-outs and home decks, sheds and patio covers); commercial work counts as other.
  • The file has no ZIP code we can publish, so there are no ZIP code pages.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in the City of Fayetteville, AR", https://contractorrecords.com/fayetteville-ar/new-home-permits, data through September 2026, from City of Fayetteville Development Services, Building Safety Division building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits: declared value · New homes permits by permit type.

Common questions

  • How many new home permits does Fayetteville issue a year?About 672 a year in the City of Fayetteville: 1,345 permits issued October 2024 through September 2026, 737 of them in the last 12 months.
  • How long does a new home permit take in Fayetteville?The usual one took 205 days from issue to the city's final inspection, and the middle half took 123 to 322 days (513 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Fayetteville file the most new home permits?March (205 against an average month of 100); May is the quietest (65). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.