Fence and wall permits in Fort Myers, FL

Data through September 2026 · updated 19 Oct 2026

411 fence and wall permits were issued in Fort Myers, October 2024 through September 2026: about 206 a year and 5% of all permits. 189 fence and wall permits in the last 12 months (Oct 2025–Sep 2026), 15% fewer than the 222 in the 12 months before. The busiest month is August. The usual one took 36 days from issue to the city's final. 33901 has the most, 175.

411permits issued
189last 12 months
Augbusiest month
36days, usual issue to final
91%finished
Sep 2026records through

Fence and wall permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 15Oct2024Nov 2024: 13Dec 2024: 19Jan 2025: 9Jan2025Feb 2025: 20Mar 2025: 16Apr 2025: 17May 2025: 28Jun 2025: 21Jul 2025: 22JulAug 2025: 24Sep 2025: 18Oct 2025: 16Nov 2025: 14Dec 2025: 13Jan 2026: 17Jan2026Feb 2026: 12Mar 2026: 20Apr 2026: 12May 2026: 18Jun 2026: 18Jul 2026: 18JulAug 2026: 24Sep 2026: 7
The same numbers as a table
MonthPermits
Oct 202415
Nov 202413
Dec 202419
Jan 20259
Feb 202520
Mar 202516
Apr 202517
May 202528
Jun 202521
Jul 202522
Aug 202524
Sep 202518
Oct 202516
Nov 202514
Dec 202513
Jan 202617
Feb 202612
Mar 202620
Apr 202612
May 202618
Jun 202618
Jul 202618
Aug 202624
Sep 20267

Download this table (CSV)

When fence and wall permits are filed

By calendar month, 100 = an average month (the thin line). August is the busiest (140), September the quietest (73). A busy month at the permit counter usually means a longer wait for a contractor.

January: 76 (100 = an average month)February: 93 (100 = an average month)March: 105 (100 = an average month)April: 85 (100 = an average month)May: 134 (100 = an average month)June: 114 (100 = an average month)July: 117 (100 = an average month)August: 140 (100 = an average month)140September: 73 (100 = an average month)October: 91 (100 = an average month)November: 79 (100 = an average month)December: 93 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January76
February93
March105
April85
May134
June114
July117
August140
September73
October91
November79
December93

Download this table (CSV)

How long a fence and wall permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 203 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025222
Finished91.4%
Expired6.3%
Usual days, issue to final36
Middle half, days19–105

Download this table (CSV)

ZIP codes with the most fence and wall permits

Counted at the property's ZIP code. Share is the part of the city's 411 fence and wall permits.

ZIP codePermitsShare
3390117543%
3391611929%
339054511%
33913277%
33971195%
3390782%
3391272%
3396672%
339194under 1%

Download this table (CSV)

Nearby permit data

Fence and wall permits for other places in Southwest Florida. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Fort Myers, EnerGov Citizen Self Service public permit search, read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits the City of Fort Myers issues for one- and two-family homes inside city limits: re-roofs, air-conditioner change-outs, plumbing, electrical, solar, windows, doors and shutters, pools, fences, screen enclosures and new houses. Commercial and multi-family permits, signs, events and right-of-way work are not counted. Unincorporated Lee County, Cape Coral, Bonita Springs and Estero run their own permit offices and are not in this file.

  • The city's public permit search shows no contractor, so there are no contractor lists, rankings or firm pages for Fort Myers.
  • The search results carry no job value, so we show no costs.
  • A final date is the day the city finaled the permit. Permits the city marks Closed count as finished but add no days.
  • These rows come from the city's public permit search, which the city's website terms describe as public information that is generally available to copy or distribute.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Fence and wall permits in Fort Myers, FL", https://contractorrecords.com/fort-myers/fence-permits, data through September 2026, from the City of Fort Myers Community Development Department building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code.

Download the tables (CSV): Fences & walls permits by month · Fences & walls permits by calendar month (index) · Fences & walls permits: days to final · Fences & walls permits by ZIP code.

Common questions

  • How many fence and wall permits does Fort Myers issue a year?About 206 a year in Fort Myers: 411 permits issued October 2024 through September 2026, 189 of them in the last 12 months.
  • How long does a fence and wall permit take in Fort Myers?The usual one took 36 days from issue to the city's final inspection, and the middle half took 19 to 105 days (203 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Fort Myers file the most fence and wall permits?August (140 against an average month of 100); September is the quietest (73). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most fence and wall permits in Fort Myers?33901, with 175 of the 411 (43%); then 33916 (119).