This is the City of Eugene. Springfield and unincorporated Lane County run their own permit offices.
The rule
Oregon's Building Codes Division (Oregon permits, read 24 October 2026) lists installing "a wood stove, fireplace insert, pellet stove or related venting" as permit work, and portable ventilation appliances such as room air cleaners and window fans as exempt. It also notes that "Work exempt from a building permit is not necessarily exempt from a mechanical, electrical or plumbing permit." The City's mechanical permit form (Form F-304, updated July 2026) lists the residential equipment that is permitted:
| Equipment | Fee per item (July 2026) |
|---|---|
| Fuel-burning equipment: gas furnace, gas boiler, wood stove, fireplace insert (vents and flues included) | $44.30 |
| Other equipment: electric furnace, heat pump outdoor unit, ductless indoor units, air handler, air conditioner | $30.35 |
| Alterations and additions to existing ductwork | $28.10 |
| Gas piping system, new or altered, any number of outlets | $24.30 |
| Exhaust and ventilation (dryer, bath fan, range hood) | $22.95 |
| Attic or crawlspace fans | Electrical permit only |
| Minimum permit fee | $114.50 |
On top: a City administrative fee of 9% and a technology fee of 2% of permit and plan review fees, and a State surcharge of 12% of the permit fee plus the administrative fee. By our arithmetic from the form, a single furnace or heat pump swap pays the $114.50 minimum and comes to about $142 with those fees.
Who can pull it
Either a contractor, whose section of the form asks for a CCB license number, or the owner. The owner statement reads "This installation is being made on residential or farm property owned by me or a member of my immediate family" and "This property is not intended for sale, exchange, lease, or rent." If you plan to sell or rent the house, hire the contractor. For propane, Oregon's BCD page says "anyone, including homeowners, who install, extend, alter, or repair any LP gas appliance or piping" must be licensed through the State Fire Marshal.
How to apply and get it inspected
- Apply in the City's eBuild Permit System, or submit the mechanical permit form.
- A heat pump or AC also needs an electrical permit for the circuit; the City's residential combo form covers mechanical, electrical and plumbing together when the owner or one contractor holding all the licenses does all the work (Eugene electrical permit).
- Schedule inspections online through the City's Schedule Inspections tool.
- Oregon's BCD says the permit must be on site and "expires if work is not started within 180 days from its issuance."
What 5,394 Eugene HVAC permits show
From Eugene HVAC permits, October 2024 to September 2026:
| Measure | Eugene HVAC (mechanical) |
|---|---|
| Issued | 5,394 (30% of all permits) |
| Last 12 months / 12 months before | 2,630 / 2,764 (−5%) |
| Busiest month (index, 100 = average) | July (132), then June (120) and August (112) |
| Quietest month | January (86) |
| Peak single month | 311, July 2025 |
Eugene's HVAC filings follow the cooling season: June to August is when heat pump and AC installs pile up, and January to April run 9% to 14% below average. A changeout booked in late winter meets the shortest queue. Filings fell 5% in the latest 12 months. Year and month counts for every kind of work are on Eugene permit statistics, and the rows on browse Eugene permits.
Before you hire
Look up past permits at the address or by contractor in the City's Permit Search, using the Eugene building permit search guide, and check the firm's CCB license with how to check a contractor's license in Oregon. Rules elsewhere: HVAC replacement. Costs: HVAC replacement cost.
What this does not tell you
The City's issued-permit report has no status or completion date, so we show no finished share or time to final, and trade permits carry no job value, so no costs. Contractor names are cut at 30 characters and not matched to CCB records, so no firm lists. The count covers the City's mechanical permits we class as HVAC, homes and businesses alike; 72% of all Eugene permits in the window were filed as Residential.
How we know this
The permit items, fees, surcharges and owner statement are from the City of Eugene's Residential Mechanical Permit Application (Form F-304, updated July 2026); the state rules from the Oregon Building Codes Division's Oregon permits page; the eBuild and inspection tools from the City's Building Permits page, all read 24 October 2026. Our counts are the City's Issued Building Permits report, read 19 October 2026: mechanical permits issued October 2024 to September 2026.
Numbers come from public permit records in 57 cities, data through October 19, 2026. Nobody paid to be on this page and nobody can.
Questions
- Do I need a permit to replace a furnace or heat pump in Eugene?
Yes. The City's residential mechanical permit lists gas furnaces, electric furnaces, heat pump outdoor units, ductless indoor units, air handlers and air conditioners as fee items, each needing the permit. A heat pump also needs an electrical permit for its circuit.
- Can a homeowner pull an HVAC permit in Eugene?
Yes, for their own home. The City's mechanical permit form has an owner statement that the installation is on residential or farm property owned by you or an immediate family member, and that the property is not intended for sale, exchange, lease or rent. Otherwise a contractor with a CCB license applies.
- How much is a mechanical permit in Eugene?
The July 2026 form lists $44.30 for a gas furnace, $30.35 for a heat pump, AC or air handler, $28.10 for duct alterations and $24.30 for gas piping, with a $114.50 minimum. The City adds 9% administrative and 2% technology fees, and the State a 12% surcharge.
- Do I need a permit for a wood stove in Eugene?
Yes. Oregon's Building Codes Division lists installing a wood stove, fireplace insert, pellet stove or related venting as work that needs a permit, and the City's mechanical form prices it as fuel-burning equipment at $44.30.
- When is the busiest time for HVAC permits in Eugene?
July. From October 2024 to September 2026, July ran 32% above an average month and June 20% above; January was the quietest, 14% below.
Build your own list
Pick your city and the kind of work. Every firm with a permit on record, sorted by what you value.
Related guides
- Albuquerque building permit search: how to look up permits on an address
- Building a casita in Albuquerque: the 750 sq ft limit, rear-yard rule, parking, free plans, and who builds them
- Do I need a permit to build a house in Albuquerque? GB-2 or homeowner, the plan set and the fee
- Do I need a solar permit in Albuquerque? Building and electrical permits, the engineer triggers and the fee
- Do I need an HVAC permit in Virginia Beach? The like-for-like exception, fees, inspections and 8,024 permits
- Do I need a plumbing permit in Virginia Beach? New fixtures, sewer and water lines, fees and 8,227 permits
- Residential Mechanical Permit Application, Form F-304 (updated July 2026) — City of Eugene (2026-10-24)
- Oregon permits — Oregon Building Codes Division (2026-10-24)
- Building Permits — City of Eugene Planning & Development (2026-10-24)
- Building Activity Reports: Issued Building Permits — City of Eugene (2026-10-19)