Do I need a roofing permit in Orlando? The re-roof form, the dry-in inspection, fees and timing

Yes: Orlando requires a building permit to replace or repair the roof on a house, and roofing is excluded from Florida's new under-$7,500 permit exemption. The City issued 9,818 roofing permits on homes from October 2023 to September 2026; the usual one was filed at $11,015 and reached final 27 days after issue.

By Contractor Records · data through October 17, 2026

The Orlando rule

The City's roof permit page (read 23 October 2026) is short: "Do you need to replace or repair the roof on your home? You need to get a building permit."

Since 1 July 2026, Florida's HB803 lets single-family owners skip a building permit for some projects under $7,500. Roofing is not one of them. The City's exemption guide lists "roofing", along with windows, doors, siding and soffits, as work "not eligible for exemption, regardless of cost". A patch is still a roof repair, so price alone never takes a roof out of the permit.

What the City asks for When
Residential re-roofing form: estimated cost, roof details, underlayment and covering, fastener types Every re-roof
Owner/Builder Declaration, signed in person at Permitting Services Only if you do the work yourself
Recorded Notice of Commencement "If the value of the work exceeds $5,000"
Dry-in / in-progress inspection, code 125 Before the covering goes on
Completed inspection affidavit (decking nail-down and secondary water barrier) At final

Who pulls it

Normally the roofer. Florida licenses roofing contractors through DBPR, and the City adds that "Contractors getting permits for work in the City of Orlando must be registered with the Permitting Services Division", with a surety bond of at least $5,000 for a state-registered (not certified) contractor (Register a Contractor). 97.7% of the 1,058 roofing firms on Orlando permits matched an active DBPR license in our file.

A homeowner can pull it as owner-builder. The City's declaration makes you "the responsible party of record on a permit" and warns that a frequent practice of unlicensed persons is to have the owner pull the permit. If a roofer asks you to sign it for their job, that is the warning in action.

How to apply

  1. Fill out the re-roofing form linked from the City's roof permit page (online).
  2. Wait for the City. It says it will review the application and contact you "within three business days".
  3. Pay the fees shown in the City's Permit Lookup tool once approved; the permit, inspection sign-off sheet and affidavit are then emailed.
  4. Book inspection 125 before the shingles or tile go on. The City's inspection codes also list 120 roof decking and 600 final.
  5. Final with the affidavit. A re-roof that skipped the dry-in "may be subject to removing a portion of or all of the roof covering".

State law sets the review clock: for work on an existing single-family home under $15,000, the City says it responds "within 5 business days" of a complete application, and you have 10 business days to answer comments (Building Permit Guidelines).

What it costs

From the City's residential fee schedule effective January 2026:

Fee Amount
Building permit, 1 or 2 units $66.24 for the first $1,000 of construction cost, plus $4.41 per additional $1,000 or fraction
Administrative Inspection Fund 1.5% of the permit fee (minimum $2)
DCA Operational Trust Fund surcharge 1% of the permit fee (minimum $2)
Concurrency surcharge 5% of the permit fee
Technology surcharge 3% of the permit fee
Re-inspection (failed inspection) $150
Work without a permit An additional 100% of the permit fee

Construction cost is the contract price or the ICC valuation chart, "whichever is greater". Worked out from the schedule: an $11,000 re-roof is $66.24 + 10 × $4.41 = $110.34, about $122 with the four surcharges. The $150 re-inspection is the line to avoid; it is more than the permit. The City's fee page says it is "currently reviewing the amended permit fees required by HB803" (Permit Development & Impact Fees), so the invoice in Permit Lookup is the final word.

What 9,818 Orlando roofing permits show

Measure Orlando roofing
Permits on homes, October 2023 to September 2026 9,818
Firms that pulled them 1,058
Firms with a permit in the last 12 months 558
Usual filed value $11,015
Middle half of firms' usual value (3+ permits) $10,000 to $15,760
Usual days from issue to final 27
Busiest / quietest month March (125) / September (85)
Firms with one permit in three years 373 (35.3%)

A roof permit is the quickest trade permit to close in Orlando: 27 days, against 91 for HVAC. So a roof permit still open two months after the crew left is behind, usually because the final or the affidavit was never filed. 35.3% of roofing firms filed only one Orlando permit in three years; after a storm, ask the roofer for Orlando addresses you can look up. Prices by job size are on the Orlando roofing cost page.

See every Orlando roofer by days to final →

Next steps

Compare roofers on the Orlando roofing list, then follow hiring a roofer in Orlando for the DBPR check, or the Orlando contractor license lookup. Past permits on your address: Orlando building permit search. Monthly counts: Orlando permit statistics. National prices: roof replacement cost; other cities' rules: do I need a permit for roof replacement.

What this does not tell you

This is the City of Orlando only; an address in unincorporated Orange County or Winter Park permits elsewhere. Almost every Orlando permit is eventually closed, so we show speed to final rather than a finished share. A final means the inspector passed the work, not what it cost or how long the shingles will last.

How we know this

Rules, steps and inspection codes are quoted from City of Orlando Permitting Services pages read 23 October 2026; fees from the City's residential fee schedule effective January 2026, with the worked example computed by us. Counts are City of Orlando permits on one- and two-family homes classified as roofing, October 2023 to September 2026; days to final are the median from issue, and license status is our name match to Florida DBPR records.

Numbers come from City of Orlando building permits for one- and two-family homes, data through October 17, 2026. Nobody paid to be on this page and nobody can.

Questions

  • Do I need a permit to replace my roof in Orlando?

    Yes. The City's roof permit page says that to replace or repair the roof on your home 'You need to get a building permit'. Florida's new under-$7,500 exemption (HB803) does not help: the City lists roofing among the work that is 'not eligible for exemption, regardless of cost'.

  • How much is a roofing permit in Orlando?

    Orlando's 2026 residential schedule charges $66.24 for the first $1,000 of construction cost plus $4.41 for each further $1,000, then percentage surcharges of 1.5%, 1%, 5% and 3%. On an $11,000 re-roof that is $110.34 before surcharges, about $122 with them. The City says it is reviewing fees after HB803, so check the invoice in Permit Lookup.

  • How long does a roofing permit take in Orlando?

    The City says it reviews a re-roof application and contacts you within three business days. In our file the usual Orlando roofing permit reached final 27 days after it was issued.

  • What is inspection 125 on an Orlando roof permit?

    The dry-in or in-progress inspection, reinstated on 1 January 2020 for all re-roofs. It happens before the roof covering goes on; a re-roof that skipped it 'may receive disapproval at final inspection' and may have to remove part or all of the covering so the underlayment and sheathing nailing can be seen.

  • Can a homeowner pull a roofing permit in Orlando?

    Yes, as an owner-builder doing the work yourself. The State requires an Owner/Builder Declaration with the application, and the City says you must sign it in person at the Permitting Services office, 400 South Orange Avenue.