Data through September 2026 · updated 19 Oct 2026

2,111 new home permits were issued in the City of Huntsville, October 2024 through September 2026: about 1,056 a year and 39% of all permits. 1,203 new home permits in the last 12 months (Oct 2025–Sep 2026), 32% more than the 908 in the 12 months before. The busiest month is April. The usual one took 156 days from issue to the city's final.

What this file covers: The city publishes building permits only; electrical, plumbing, mechanical, gas and roofing permits are not in the file.

2,111permits issued
1,203last 12 months
Aprbusiest month
156days, usual issue to final
92%finished
$39,165usual declared value
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 105Oct2024Nov 2024: 68Dec 2024: 77Jan 2025: 68Jan2025Feb 2025: 93Mar 2025: 28Apr 2025: 113May 2025: 74Jun 2025: 48Jul 2025: 92JulAug 2025: 74Sep 2025: 68Oct 2025: 108Nov 2025: 60Dec 2025: 81Jan 2026: 113Jan2026Feb 2026: 117Mar 2026: 106Apr 2026: 151May 2026: 117Jun 2026: 93Jul 2026: 69JulAug 2026: 106Sep 2026: 82
The same numbers as a table
MonthPermits
Oct 2024105
Nov 202468
Dec 202477
Jan 202568
Feb 202593
Mar 202528
Apr 2025113
May 202574
Jun 202548
Jul 202592
Aug 202574
Sep 202568
Oct 2025108
Nov 202560
Dec 202581
Jan 2026113
Feb 2026117
Mar 2026106
Apr 2026151
May 2026117
Jun 202693
Jul 202669
Aug 2026106
Sep 202682

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). April is the busiest (150), November the quietest (73). A busy month at the permit counter usually means a longer wait for a contractor.

January: 103 (100 = an average month)February: 119 (100 = an average month)March: 76 (100 = an average month)April: 150 (100 = an average month)150May: 109 (100 = an average month)June: 80 (100 = an average month)July: 92 (100 = an average month)August: 102 (100 = an average month)September: 85 (100 = an average month)October: 121 (100 = an average month)November: 73 (100 = an average month)December: 90 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January103
February119
March76
April150
May109
June80
July92
August102
September85
October121
November73
December90

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 839 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025908
Finished92.4%
Usual days, issue to final156
Middle half, days112–238

Download this table (CSV)

What a new home permit is declared at

The value written on the permit at application, from 2,111 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$39,165
Middle half$31,568–$51,172

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
New Construction (Single Family)1,92391%
New Construction (Townhomes)1798%
New Construction (Duplex)9under 1%

Download this table (CSV)

How Huntsville compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Huntsville GIS: BuildingPermits and OccupancyCerts layers (Licenses/BuildingPermits MapServer layers 0 and 1), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building permits the City of Huntsville, Alabama issues inside city limits (in Madison, Limestone and Morgan counties): new construction, alterations, additions, accessory buildings and demolitions for homes and commercial buildings. The city does not publish its electrical, plumbing, mechanical, gas or roofing permits, so those trades are not in this file. Madison, unincorporated Madison County and the other nearby towns run their own permit offices and are not in this file, and neither is Huntsville, Texas.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Huntsville.
  • Only building permits are published; electrical, plumbing, mechanical, gas and roofing permits are not in the city's file.
  • The file has no permit status or final inspection date. A permit counts as finished once the city issues a certificate of occupancy for it, and the certificate's date stands in for the final date. Alterations and additions often get no certificate, so they mostly show as open.
  • The value is the contract amount on the permit.
  • Homes are permits for single-family homes, townhomes, duplexes and condos; apartment buildings count as other.
  • The file has no ZIP code we can publish, so there are no ZIP code pages.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in the City of Huntsville, AL", https://contractorrecords.com/huntsville/new-home-permits, data through September 2026, from City of Huntsville Inspection Department building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits: declared value · New homes permits by permit type.

Common questions

  • How many new home permits does Huntsville issue a year?About 1,056 a year in the City of Huntsville: 2,111 permits issued October 2024 through September 2026, 1,203 of them in the last 12 months.
  • How long does a new home permit take in Huntsville?The usual one took 156 days from issue to the city's final inspection, and the middle half took 112 to 238 days (839 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Huntsville file the most new home permits?April (150 against an average month of 100); November is the quietest (73). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.