Contractor Records
Home › Huntsville › Remodels & repairs

Remodel and repair permits in the City of Huntsville, AL

Data through September 2026 · updated 19 Oct 2026

1,079 remodel and repair permits were issued in the City of Huntsville, October 2024 through September 2026: about 540 a year and 20% of all permits. 618 remodel and repair permits in the last 12 months (Oct 2025–Sep 2026), 34% more than the 461 in the 12 months before. The busiest month is June. The usual one took 179 days from issue to the city's final.

What this file covers: The city publishes building permits only; electrical, plumbing, mechanical, gas and roofing permits are not in the file.

1,079permits issued
618last 12 months
Junbusiest month
179days, usual issue to final
29%finished
$28,203usual declared value
Sep 2026records through

Remodel and repair permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 54Oct2024Nov 2024: 29Dec 2024: 23Jan 2025: 34Jan2025Feb 2025: 37Mar 2025: 23Apr 2025: 45May 2025: 50Jun 2025: 39Jul 2025: 36JulAug 2025: 49Sep 2025: 42Oct 2025: 50Nov 2025: 34Dec 2025: 37Jan 2026: 44Jan2026Feb 2026: 31Mar 2026: 42Apr 2026: 67May 2026: 61Jun 2026: 80Jul 2026: 53JulAug 2026: 67Sep 2026: 52
The same numbers as a table
MonthPermits
Oct 202454
Nov 202429
Dec 202423
Jan 202534
Feb 202537
Mar 202523
Apr 202545
May 202550
Jun 202539
Jul 202536
Aug 202549
Sep 202542
Oct 202550
Nov 202534
Dec 202537
Jan 202644
Feb 202631
Mar 202642
Apr 202667
May 202661
Jun 202680
Jul 202653
Aug 202667
Sep 202652

Download this table (CSV)

When remodel and repair permits are filed

By calendar month, 100 = an average month (the thin line). June is the busiest (132), December the quietest (67). A busy month at the permit counter usually means a longer wait for a contractor.

January: 87 (100 = an average month)February: 76 (100 = an average month)March: 72 (100 = an average month)April: 125 (100 = an average month)May: 123 (100 = an average month)June: 132 (100 = an average month)132July: 99 (100 = an average month)August: 129 (100 = an average month)September: 105 (100 = an average month)October: 116 (100 = an average month)November: 70 (100 = an average month)December: 67 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January87
February76
March72
April125
May123
June132
July99
August129
September105
October116
November70
December67

Download this table (CSV)

How long a remodel and repair permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 134 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025461
Finished29.1%
Usual days, issue to final179
Middle half, days100–300

Download this table (CSV)

What a remodel and repair permit is declared at

The value written on the permit at application, from 1,051 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$28,203
Middle half$13,154–$62,206

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Alteration (Single Family)1,05097%
Alteration (Condo)252%
Alteration (Townhomes)4under 1%

Download this table (CSV)

How Huntsville compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Huntsville GIS: BuildingPermits and OccupancyCerts layers (Licenses/BuildingPermits MapServer layers 0 and 1), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building permits the City of Huntsville, Alabama issues inside city limits (in Madison, Limestone and Morgan counties): new construction, alterations, additions, accessory buildings and demolitions for homes and commercial buildings. The city does not publish its electrical, plumbing, mechanical, gas or roofing permits, so those trades are not in this file. Madison, unincorporated Madison County and the other nearby towns run their own permit offices and are not in this file, and neither is Huntsville, Texas.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Huntsville.
  • Only building permits are published; electrical, plumbing, mechanical, gas and roofing permits are not in the city's file.
  • The file has no permit status or final inspection date. A permit counts as finished once the city issues a certificate of occupancy for it, and the certificate's date stands in for the final date. Alterations and additions often get no certificate, so they mostly show as open.
  • The value is the contract amount on the permit.
  • Homes are permits for single-family homes, townhomes, duplexes and condos; apartment buildings count as other.
  • The file has no ZIP code we can publish, so there are no ZIP code pages.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Remodel and repair permits in the City of Huntsville, AL", https://contractorrecords.com/huntsville/remodel-permits, data through September 2026, from City of Huntsville Inspection Department building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types.

Download the tables (CSV): Remodels & repairs permits by month · Remodels & repairs permits by calendar month (index) · Remodels & repairs permits: days to final · Remodels & repairs permits: declared value · Remodels & repairs permits by permit type.

Common questions

  • How many remodel and repair permits does Huntsville issue a year?About 540 a year in the City of Huntsville: 1,079 permits issued October 2024 through September 2026, 618 of them in the last 12 months.
  • How long does a remodel and repair permit take in Huntsville?The usual one took 179 days from issue to the city's final inspection, and the middle half took 100 to 300 days (134 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Huntsville file the most remodel and repair permits?June (132 against an average month of 100); December is the quietest (67). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.