Data through December 2024 · updated 21 Oct 2026
The usual permit in the Town of Timnath takes 144 days from issue to the town's final inspection; the middle half take 67 to 200 days. That is from 814 permits issued Jan 2023–Dec 2023 that reached a final. Solar permits are quickest at 75 days; new home permits take longest at 196 days. This is the time to finish the work and close the permit, not the wait for approval.
“How long does a permit take?” can mean two waits. This page measures the second one.
Getting the permit (not measured): application → issue, the wait for the town to approve the plans. Ask the town for its current review times.
Finishing the work (measured here): issue → final. From the day the town issued the permit to the day it recorded the final inspection. We count only permits issued Jan 2023–Dec 2023, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.
Permits issued Jan 2023–Dec 2023. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.
Each kind of work on its own, issue to the town's final.
The usual new home permit in the Town of Timnath takes 196 days from issue to final; the middle half take 160 to 241 days (323 permits with a final date, issued Jan 2023–Dec 2023). 99% of the 326 permits issued then have finished and under 1% expired. Timnath new home permits →
The usual solar permit in the Town of Timnath takes 75 days from issue to final; the middle half take 49 to 95 days (157 permits with a final date, issued Jan 2023–Dec 2023). 98% of the 161 permits issued then have finished and 2% expired. Timnath solar permits →
The usual remodel and repair permit in the Town of Timnath takes 98 days from issue to final; the middle half take 61 to 165 days (82 permits with a final date, issued Jan 2023–Dec 2023).
From our cross-city data studies: the same measure, read the same way, for every city we cover.
How long permits take for other places in Northern Colorado. Each permit office keeps its own file, so the numbers are not added together.
Source: Town of Timnath GIS, Building Permits 2020 through 2024 (ArcGIS layer BP2020thru2024), with the town's 2025 certificates of completion and occupancy, read 21 Oct 2026. We count permits issued January 2023 through December 2024; denied and withdrawn permits are left out.
Building, trade, roofing, solar, fence and demolition permits issued by the Town of Timnath Building Department for property in the town, east of Fort Collins in Larimer County. Fort Collins, Windsor and unincorporated Larimer County run their own permit offices and are not in this file.
Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →
Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:
Contractor Records, "How long do permits take in the Town of Timnath, CO?", https://contractorrecords.com/timnath/how-long-does-a-permit-take, data through December 2024, from Town of Timnath Building Department building-permit records.Link to a table: By kind of work · Each kind of permit.
Download the tables (CSV): Days to final by kind of work.