Solar permits in the Town of Timnath, CO

Data through December 2024 · updated 21 Oct 2026

332 solar permits were issued in the Town of Timnath, January 2023 through December 2024: about 166 a year and 18% of all permits. 171 solar permits in the last 12 months on file (Jan 2024–Dec 2024), 6% more than the 161 in the 12 months before. The busiest month is March. The usual one took 75 days from issue to the town's final. 80547 has the most, 225.

332permits issued
171last 12 months on file
Marbusiest month
75days, usual issue to final
98%finished
$15,400usual declared value
Dec 2024records through

Solar permits by month

Permits issued each month, January 2023 through December 2024.

Jan 2023: 7Jan2023Feb 2023: 12Mar 2023: 17Apr 2023: 15May 2023: 7Jun 2023: 15Jul 2023: 17JulAug 2023: 14Sep 2023: 11Oct 2023: 27Nov 2023: 15Dec 2023: 4Jan 2024: 31Jan2024Feb 2024: 9Mar 2024: 30Apr 2024: 15May 2024: 13Jun 2024: 15Jul 2024: 19JulAug 2024: 19Sep 2024: 11Oct 2024: 5Nov 2024: 4Dec 2024: 0
The same numbers as a table
MonthPermits
Jan 20237
Feb 202312
Mar 202317
Apr 202315
May 20237
Jun 202315
Jul 202317
Aug 202314
Sep 202311
Oct 202327
Nov 202315
Dec 20234
Jan 202431
Feb 20249
Mar 202430
Apr 202415
May 202413
Jun 202415
Jul 202419
Aug 202419
Sep 202411
Oct 20245
Nov 20244
Dec 20240

Download this table (CSV)

When solar permits are filed

By calendar month, 100 = an average month (the thin line). March is the busiest (170), December the quietest (14). A busy month at the permit counter usually means a longer wait for a contractor.

January: 137 (100 = an average month)February: 76 (100 = an average month)March: 170 (100 = an average month)170April: 108 (100 = an average month)May: 72 (100 = an average month)June: 108 (100 = an average month)July: 130 (100 = an average month)August: 119 (100 = an average month)September: 80 (100 = an average month)October: 116 (100 = an average month)November: 69 (100 = an average month)December: 14 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January137
February76
March170
April108
May72
June108
July130
August119
September80
October116
November69
December14

Download this table (CSV)

How long a solar permit takes

Permits issued Jan 2023–Dec 2023, at least 12 months before the file ends. Usual days is the middle permit among the 157 with a final date.

MeasureValue
Permits issued Jan 2023–Dec 2023161
Finished97.5%
Expired2.5%
Usual days, issue to final75
Middle half, days49–95

Download this table (CSV)

What a solar permit is declared at

The value written on the permit at application, from 332 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$15,400
Middle half$11,200–$19,600

Download this table (CSV)

ZIP codes with the most solar permits

Counted at the property's ZIP code. Share is the part of the town's 332 solar permits.

ZIP codePermitsShare
8054722568%
8052410632%

Download this table (CSV)

The town's own permit types

How the town filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
PV System (Residential Alteration)33099%
Residential Roof/PV Solar Permit1under 1%
PV System (Commercial Alteration)1under 1%

Download this table (CSV)

Most active contractors by permits filed

The contractors named on the most solar permits in the Town of Timnath GIS file, January 2023 through December 2024, with 5 or more each. Share is the part of all 332 solar permits; 100% of them name a contractor we can show. This is volume, not quality: more permits doesn't mean better work. Individuals' names, owner-builders and blanks are left out.

ContractorPermitsShare
Namaste Solar Electric, Inc.21765%
Ion Solar, LLC278%
Sunrun Installation Services, Inc.165%
BRS Field Ops, LLC113%
Oneworldenergy, LLC82%
Tesla Energy Operations Inc.72%
Apollo Energy LLC62%
Colorado Solar Co, LLC62%
Freedom Solar Power, LLC52%

Download this table (CSV)

Other kinds of work here

How Timnath compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Solar permits for other places in Northern Colorado. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Town of Timnath GIS, Building Permits 2020 through 2024 (ArcGIS layer BP2020thru2024), with the town's 2025 certificates of completion and occupancy, read 21 Oct 2026. We count permits issued January 2023 through December 2024; denied and withdrawn permits are left out.

Building, trade, roofing, solar, fence and demolition permits issued by the Town of Timnath Building Department for property in the town, east of Fort Collins in Larimer County. Fort Collins, Windsor and unincorporated Larimer County run their own permit offices and are not in this file.

  • The town's permit layer is a one-time export covering 2020 through 2024 (last edited January 2025), and the town publishes no permit list for 2025 or later, so the window ends in December 2024.
  • Statuses are as of the January 2025 export. A permit still in progress then that appears on the town's 2025 list of certificates of completion and occupancy counts as finished on its certificate date.
  • Job values are the valuation on the permit. For new homes this is the town's building valuation, not the sale price.
  • Attached single-family homes (townhomes) count as new homes; a few multi-family buildings count as other.
  • Timnath is a small, fast-growing town: about 900 permits a year, a large share of them new homes in new subdivisions, so a few builders account for many permits.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Solar permits in the Town of Timnath, CO", https://contractorrecords.com/timnath/solar-permits, data through December 2024, from Town of Timnath Building Department building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types · Most active contractors by permits filed.

Download the tables (CSV): Solar permits by month · Solar permits by calendar month (index) · Solar permits: days to final · Solar permits: declared value · Solar permits by ZIP code · Solar permits by permit type · Most active contractors by permits filed.

Common questions

  • How many solar permits does Timnath issue a year?About 166 a year in the Town of Timnath: 332 permits issued January 2023 through December 2024, 171 of them in the last 12 months on file (to December 2024).
  • How long does a solar permit take in Timnath?The usual one took 75 days from issue to the town's final inspection, and the middle half took 49 to 95 days (157 permits issued Jan 2023–Dec 2023 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Timnath file the most solar permits?March (170 against an average month of 100); December is the quietest (14). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most solar permits in Timnath?80547, with 225 of the 332 (68%); then 80524 (106).