Electrical permits in the City of Bozeman, MT

Data through September 2026 · updated 19 Oct 2026

323 electrical permits were issued in the City of Bozeman, October 2024 through September 2026: about 162 a year and 9% of all permits. 192 electrical permits in the last 12 months (Oct 2025–Sep 2026), 47% more than the 131 in the 12 months before. The busiest month is October. The usual one took 29 days from issue to the city's final.

323permits issued
192last 12 months
Octbusiest month
29days, usual issue to final
91%finished
$2,000usual declared value
Sep 2026records through

Electrical permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 16Oct2024Nov 2024: 6Dec 2024: 6Jan 2025: 10Jan2025Feb 2025: 3Mar 2025: 4Apr 2025: 26May 2025: 9Jun 2025: 6Jul 2025: 13JulAug 2025: 8Sep 2025: 24Oct 2025: 27Nov 2025: 9Dec 2025: 11Jan 2026: 5Jan2026Feb 2026: 13Mar 2026: 15Apr 2026: 11May 2026: 16Jun 2026: 26Jul 2026: 21JulAug 2026: 22Sep 2026: 16
The same numbers as a table
MonthPermits
Oct 202416
Nov 20246
Dec 20246
Jan 202510
Feb 20253
Mar 20254
Apr 202526
May 20259
Jun 20256
Jul 202513
Aug 20258
Sep 202524
Oct 202527
Nov 20259
Dec 202511
Jan 20265
Feb 202613
Mar 202615
Apr 202611
May 202616
Jun 202626
Jul 202621
Aug 202622
Sep 202616

Download this table (CSV)

When electrical permits are filed

By calendar month, 100 = an average month (the thin line). October is the busiest (160), January the quietest (56). A busy month at the permit counter usually means a longer wait for a contractor.

January: 56 (100 = an average month)February: 59 (100 = an average month)March: 71 (100 = an average month)April: 137 (100 = an average month)May: 93 (100 = an average month)June: 119 (100 = an average month)July: 126 (100 = an average month)August: 111 (100 = an average month)September: 149 (100 = an average month)October: 160 (100 = an average month)160November: 56 (100 = an average month)December: 63 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January56
February59
March71
April137
May93
June119
July126
August111
September149
October160
November56
December63

Download this table (CSV)

How long an electrical permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 119 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025131
Finished90.8%
Expired6.1%
Usual days, issue to final29
Middle half, days11–132

Download this table (CSV)

What an electrical permit is declared at

The value written on the permit at application, from 314 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$2,000
Middle half$500–$4,976

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Electric Only26181%
Temp Power6219%

Download this table (CSV)

How Bozeman compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Bozeman, BP_Comm_Dev_Report_Data_view (data behind the Building Permit Data Dashboard), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits the City of Bozeman Community Development issues inside the city limits only. Belgrade, Four Corners, Bridger Canyon and the rest of Gallatin County outside the city are not in this file.

  • The city's permit data names no contractor, so there are no contractor lists, rankings or firm pages for Bozeman.
  • The city issues a project's building, electrical, mechanical and plumbing work under one permit number; each number counts once here, under the kind of project it was applied for.
  • The data has no ZIP code, so there are no ZIP pages.
  • A final date is the date every part of the permit passed final inspection or the certificate of occupancy was issued. A permit past its expiration date without a final counts as expired.
  • The value is the valuation on the permit, which sets the fee. It is not a final cost.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Electrical permits in the City of Bozeman, MT", https://contractorrecords.com/bozeman/electrical-permits, data through September 2026, from the City of Bozeman Community Development building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types.

Download the tables (CSV): Electrical permits by month · Electrical permits by calendar month (index) · Electrical permits: days to final · Electrical permits: declared value · Electrical permits by permit type.

Common questions

  • How many electrical permits does Bozeman issue a year?About 162 a year in the City of Bozeman: 323 permits issued October 2024 through September 2026, 192 of them in the last 12 months.
  • How long does an electrical permit take in Bozeman?The usual one took 29 days from issue to the city's final inspection, and the middle half took 11 to 132 days (119 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Bozeman file the most electrical permits?October (160 against an average month of 100); January is the quietest (56). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.