Data through September 2026 · updated 19 Oct 2026
1,706 building permits were issued in ZIP code 65202 by the City of Columbia Community Development Department, October 2024 through September 2026: 27% of the 6,252 in Columbia, the 2nd busiest ZIP code. HVAC permits lead with 415. 930 permits in the last 12 months (Oct 2025–Sep 2026), 20% more than the 776 in the 12 months before. Permits from a city that runs its own permit office are not counted.
Share here is the part of the 1,706 permits in 65202; citywide is the same for all of Columbia.
| Kind of work | Permits | Share here | Citywide |
|---|---|---|---|
| HVAC | 415 | 24% | 28% |
| Roofing | 378 | 22% | 15% |
| New homes | 268 | 16% | 12% |
| Electrical | 250 | 15% | 16% |
| Remodels & repairs | 144 | 8% | 10% |
| Plumbing | 111 | 7% | 9% |
| Solar | 77 | 5% | 4% |
| Garages, sheds & shade structures | 24 | 1% | 3% |
| Additions | 21 | 1% | 2% |
| Demolition | 7 | under 1% | under 1% |
| Pools & spas | 4 | under 1% | under 1% |
| Fences & walls | 2 | under 1% | under 1% |
| Other | 5 | under 1% | under 1% |
Permits issued in each calendar year of the window.
| Year | Months | Permits | Per year |
|---|---|---|---|
| 2024 (from October) | 3 | 171 | 684 |
| 2025 | 12 | 796 | 796 |
| 2026 (through September) | 9 | 739 | 985 |
Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends.
| Measure | 65202 | Citywide |
|---|---|---|
| Permits issued Oct 2024–Sep 2025 | 776 | 2,956 |
| Finished | 53.1% | 56.3% |
| Expired | 20.4% | 20.8% |
| Usual days, issue to final | 25 | 22 |
Source: City of Columbia GIS, Building Permit Application Status (ArcGIS layer behind the city's Development Permits Viewer), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.
Building and trade permits the City of Columbia issues inside city limits for homes and other non-commercial work: new houses, duplexes and townhouses, home alterations and additions, re-roofs, heating and cooling, electrical, plumbing and gas, residential solar, decks and foundation repair. Commercial building permits, right-of-way and utility permits, fire systems, signs and grading in the same file are not counted, and neither is unincorporated Boone County, which issues its own permits.
Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →
Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:
Contractor Records, "Building permits in 65202, Columbia", https://contractorrecords.com/columbia-mo/zip/65202, data through September 2026, from the City of Columbia Community Development Department building-permit records.Link to a table: By kind of work · By year · How permits finish.
Download the tables (CSV): Permits in 65202 by kind of work · Permits in 65202 by year · Permits in 65202: finished and days to final.