Solar permits in Columbia, MO

Data through September 2026 · updated 19 Oct 2026

247 solar permits were issued in Columbia, October 2024 through September 2026: about 124 a year and 4% of all permits. 90 solar permits in the last 12 months (Oct 2025–Sep 2026), 43% fewer than the 157 in the 12 months before. The busiest month is August. The usual one took 28 days from issue to the city's final. 65203 has the most, 147.

247permits issued
90last 12 months
Augbusiest month
28days, usual issue to final
98%finished
$20,496usual declared value
Sep 2026records through

Solar permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 8Oct2024Nov 2024: 23Dec 2024: 18Jan 2025: 12Jan2025Feb 2025: 2Mar 2025: 5Apr 2025: 7May 2025: 4Jun 2025: 5Jul 2025: 8JulAug 2025: 37Sep 2025: 28Oct 2025: 21Nov 2025: 15Dec 2025: 16Jan 2026: 0Jan2026Feb 2026: 10Mar 2026: 5Apr 2026: 2May 2026: 3Jun 2026: 7Jul 2026: 1JulAug 2026: 7Sep 2026: 3
The same numbers as a table
MonthPermits
Oct 20248
Nov 202423
Dec 202418
Jan 202512
Feb 20252
Mar 20255
Apr 20257
May 20254
Jun 20255
Jul 20258
Aug 202537
Sep 202528
Oct 202521
Nov 202515
Dec 202516
Jan 20260
Feb 202610
Mar 20265
Apr 20262
May 20263
Jun 20267
Jul 20261
Aug 20267
Sep 20263

Download this table (CSV)

When solar permits are filed

By calendar month, 100 = an average month (the thin line). August is the busiest (214), May the quietest (34). A busy month at the permit counter usually means a longer wait for a contractor.

January: 58 (100 = an average month)February: 58 (100 = an average month)March: 49 (100 = an average month)April: 44 (100 = an average month)May: 34 (100 = an average month)June: 58 (100 = an average month)July: 44 (100 = an average month)August: 214 (100 = an average month)214September: 151 (100 = an average month)October: 141 (100 = an average month)November: 185 (100 = an average month)December: 165 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January58
February58
March49
April44
May34
June58
July44
August214
September151
October141
November185
December165

Download this table (CSV)

How long a solar permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 154 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025157
Finished98.1%
Expired0.0%
Usual days, issue to final28
Middle half, days13–54

Download this table (CSV)

What a solar permit is declared at

The value written on the permit at application, from 247 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$20,496
Middle half$15,000–$33,884

Download this table (CSV)

ZIP codes with the most solar permits

Counted at the property's ZIP code. Share is the part of the city's 247 solar permits.

ZIP codePermitsShare
6520314760%
652027731%
65201239%

Download this table (CSV)

How Columbia compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Columbia GIS, Building Permit Application Status (ArcGIS layer behind the city's Development Permits Viewer), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building and trade permits the City of Columbia issues inside city limits for homes and other non-commercial work: new houses, duplexes and townhouses, home alterations and additions, re-roofs, heating and cooling, electrical, plumbing and gas, residential solar, decks and foundation repair. Commercial building permits, right-of-way and utility permits, fire systems, signs and grading in the same file are not counted, and neither is unincorporated Boone County, which issues its own permits.

  • The city's file names no contractor on permits issued since its 2018 system change, so there are no contractor lists, rankings or firm pages for Columbia.
  • The city doesn't split trade and re-roof permits into homes and businesses; we count one as a home permit when the lot is zoned for one- or two-family homes or manufactured homes, or the permit's description names a house.
  • A new house gets separate electrical, mechanical and plumbing sub-permits, so one project can count several times, once under each kind of work.
  • The value is the valuation on the permit; many trade permits carry none.
  • A final date is the city's finaled date. Trade sub-permits under a building permit add no days, because the file dates most of them on the day they closed; permits that expired carry no final date even where the file shows one.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Solar permits in Columbia, MO", https://contractorrecords.com/columbia-mo/solar-permits, data through September 2026, from the City of Columbia Community Development Department building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code.

Download the tables (CSV): Solar permits by month · Solar permits by calendar month (index) · Solar permits: days to final · Solar permits: declared value · Solar permits by ZIP code.

Common questions

  • How many solar permits does Columbia issue a year?About 124 a year in Columbia: 247 permits issued October 2024 through September 2026, 90 of them in the last 12 months.
  • How long does a solar permit take in Columbia?The usual one took 28 days from issue to the city's final inspection, and the middle half took 13 to 54 days (154 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Columbia file the most solar permits?August (214 against an average month of 100); May is the quietest (34). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most solar permits in Columbia?65203, with 147 of the 247 (60%); then 65202 (77).