605 remodel and repair permits were issued in Columbia, October 2024 through September 2026: about 302 a year and 10% of all permits. 320 remodel and repair permits in the last 12 months (Oct 2025–Sep 2026), 12% more than the 285 in the 12 months before. The busiest month is January. The usual one took 63 days from issue to the city's final. 65203 has the most, 358.

605permits issued
320last 12 months
Janbusiest month
63days, usual issue to final
19%finished
$19,572usual declared value
Sep 2026records through

Remodel and repair permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 28Oct2024Nov 2024: 19Dec 2024: 22Jan 2025: 32Jan2025Feb 2025: 18Mar 2025: 27Apr 2025: 25May 2025: 26Jun 2025: 20Jul 2025: 17JulAug 2025: 19Sep 2025: 32Oct 2025: 27Nov 2025: 25Dec 2025: 34Jan 2026: 27Jan2026Feb 2026: 20Mar 2026: 26Apr 2026: 22May 2026: 31Jun 2026: 31Jul 2026: 36JulAug 2026: 21Sep 2026: 20
The same numbers as a table
MonthPermits
Oct 202428
Nov 202419
Dec 202422
Jan 202532
Feb 202518
Mar 202527
Apr 202525
May 202526
Jun 202520
Jul 202517
Aug 202519
Sep 202532
Oct 202527
Nov 202525
Dec 202534
Jan 202627
Feb 202620
Mar 202626
Apr 202622
May 202631
Jun 202631
Jul 202636
Aug 202621
Sep 202620

Download this table (CSV)

When remodel and repair permits are filed

By calendar month, 100 = an average month (the thin line). January is the busiest (117), February the quietest (75). A busy month at the permit counter usually means a longer wait for a contractor.

January: 117 (100 = an average month)117February: 75 (100 = an average month)March: 105 (100 = an average month)April: 93 (100 = an average month)May: 113 (100 = an average month)June: 101 (100 = an average month)July: 105 (100 = an average month)August: 79 (100 = an average month)September: 103 (100 = an average month)October: 109 (100 = an average month)November: 87 (100 = an average month)December: 111 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January117
February75
March105
April93
May113
June101
July105
August79
September103
October109
November87
December111

Download this table (CSV)

How long a remodel and repair permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 55 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025285
Finished19.3%
Expired29.8%
Usual days, issue to final63
Middle half, days21–154

Download this table (CSV)

What a remodel and repair permit is declared at

The value written on the permit at application, from 586 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$19,572
Middle half$10,650–$40,000

Download this table (CSV)

ZIP codes with the most remodel and repair permits

Counted at the property's ZIP code. Share is the part of the city's 605 remodel and repair permits.

ZIP codePermitsShare
6520335859%
6520214424%
6520110317%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Foundation Repair: Foundation Repair32654%
Building (Residential Alter/Add): Alteration (Residential)27946%

Download this table (CSV)

How Columbia compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Columbia GIS, Building Permit Application Status (ArcGIS layer behind the city's Development Permits Viewer), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building and trade permits the City of Columbia issues inside city limits for homes and other non-commercial work: new houses, duplexes and townhouses, home alterations and additions, re-roofs, heating and cooling, electrical, plumbing and gas, residential solar, decks and foundation repair. Commercial building permits, right-of-way and utility permits, fire systems, signs and grading in the same file are not counted, and neither is unincorporated Boone County, which issues its own permits.

  • The city's file names no contractor on permits issued since its 2018 system change, so there are no contractor lists, rankings or firm pages for Columbia.
  • The city doesn't split trade and re-roof permits into homes and businesses; we count one as a home permit when the lot is zoned for one- or two-family homes or manufactured homes, or the permit's description names a house.
  • A new house gets separate electrical, mechanical and plumbing sub-permits, so one project can count several times, once under each kind of work.
  • The value is the valuation on the permit; many trade permits carry none.
  • A final date is the city's finaled date. Trade sub-permits under a building permit add no days, because the file dates most of them on the day they closed; permits that expired carry no final date even where the file shows one.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Remodel and repair permits in Columbia, MO", https://contractorrecords.com/columbia-mo/remodel-permits, data through September 2026, from the City of Columbia Community Development Department building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types.

Download the tables (CSV): Remodels & repairs permits by month · Remodels & repairs permits by calendar month (index) · Remodels & repairs permits: days to final · Remodels & repairs permits: declared value · Remodels & repairs permits by ZIP code · Remodels & repairs permits by permit type.

Common questions

  • How many remodel and repair permits does Columbia issue a year?About 302 a year in Columbia: 605 permits issued October 2024 through September 2026, 320 of them in the last 12 months.
  • How long does a remodel and repair permit take in Columbia?The usual one took 63 days from issue to the city's final inspection, and the middle half took 21 to 154 days (55 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Columbia file the most remodel and repair permits?January (117 against an average month of 100); February is the quietest (75). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.