Contractor Records
Home › Durham › New homes

New home permits in Durham, NC

Data through September 2026 · updated 19 Oct 2026

4,838 new home permits were issued in Durham, October 2024 through September 2026: about 2,419 a year and 55% of all permits. 2,218 new home permits in the last 12 months (Oct 2025–Sep 2026), 15% fewer than the 2,620 in the 12 months before. The busiest month is May. The usual one took 173 days from issue to the city's final.

What this file covers: Building permits only: electrical, plumbing and mechanical permits are not in the file.

4,838permits issued
2,218last 12 months
Maybusiest month
173days, usual issue to final
93%finished
$379,456usual declared value
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 114Oct2024Nov 2024: 216Dec 2024: 130Jan 2025: 173Jan2025Feb 2025: 218Mar 2025: 235Apr 2025: 248May 2025: 328Jun 2025: 280Jul 2025: 243JulAug 2025: 220Sep 2025: 215Oct 2025: 259Nov 2025: 178Dec 2025: 116Jan 2026: 128Jan2026Feb 2026: 175Mar 2026: 226Apr 2026: 197May 2026: 200Jun 2026: 236Jul 2026: 170JulAug 2026: 199Sep 2026: 134
The same numbers as a table
MonthPermits
Oct 2024114
Nov 2024216
Dec 2024130
Jan 2025173
Feb 2025218
Mar 2025235
Apr 2025248
May 2025328
Jun 2025280
Jul 2025243
Aug 2025220
Sep 2025215
Oct 2025259
Nov 2025178
Dec 2025116
Jan 2026128
Feb 2026175
Mar 2026226
Apr 2026197
May 2026200
Jun 2026236
Jul 2026170
Aug 2026199
Sep 2026134

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). May is the busiest (131), December the quietest (61). A busy month at the permit counter usually means a longer wait for a contractor.

January: 75 (100 = an average month)February: 97 (100 = an average month)March: 114 (100 = an average month)April: 110 (100 = an average month)May: 131 (100 = an average month)131June: 128 (100 = an average month)July: 102 (100 = an average month)August: 104 (100 = an average month)September: 87 (100 = an average month)October: 93 (100 = an average month)November: 98 (100 = an average month)December: 61 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January75
February97
March114
April110
May131
June128
July102
August104
September87
October93
November98
December61

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 2,438 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20252,620
Finished93.1%
Usual days, issue to final173
Middle half, days146–225

Download this table (CSV)

What a new home permit is declared at

The value written on the permit at application, from 4,837 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$379,456
Middle half$308,380–$471,618

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
New: Townhouse2,58253%
New: Single Family House2,17445%
New: Duplex671%
New: Mobile Home10under 1%
New: Modular Unit3under 1%
Foundation Only: Townhouse1under 1%
New: 3-4 Residential Units1under 1%

Download this table (CSV)

How Durham compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

New home permits for other places in Raleigh–Durham. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City and County of Durham GIS, All Building Permits (PublicServices/Inspections MapServer layer 12; Durham Open Data), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential building permits from Durham City-County Inspections, the joint office that issues permits for the City of Durham and for unincorporated Durham County: new houses, townhouses and duplexes, additions, alterations, repairs, decks, roofs, accessory buildings and demolitions. Commercial permits and buildings of five or more units in the same file are not counted. Electrical, plumbing and mechanical permits are not in this file. Chapel Hill, Raleigh and the other Triangle towns run their own permit offices and are not in this file.

  • The file names no contractor, so there are no contractor lists, rankings or firm pages for Durham.
  • This is the building permit file only. Electrical, plumbing and mechanical permits are published only as a list of permits still open, so they are not counted.
  • The file covers the City of Durham and unincorporated Durham County together and does not say which a permit is in.
  • A permit counts as finished once the office issues its certificate of occupancy or completion; the final date is that sign-off date. The file has no expired status.
  • Solar, roofing, pools, fences and additions are sorted out of the broad alteration and repair permits by their work description. Decks count under Other.
  • The value is the building cost declared on the permit. The file has no ZIP code we can publish, so there are no ZIP code pages.
  • Each new townhouse unit gets its own permit, so new homes count units, not buildings. Townhouses are about half of the new homes.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in Durham, NC", https://contractorrecords.com/durham/new-home-permits, data through September 2026, from Durham City-County Inspections building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits: declared value · New homes permits by permit type.

Common questions

  • How many new home permits does Durham issue a year?About 2,419 a year in Durham: 4,838 permits issued October 2024 through September 2026, 2,218 of them in the last 12 months.
  • How long does a new home permit take in Durham?The usual one took 173 days from issue to the city's final inspection, and the middle half took 146 to 225 days (2,438 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Durham file the most new home permits?May (131 against an average month of 100); December is the quietest (61). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.