Solar permits in Durham, NC

Data through September 2026 · updated 19 Oct 2026

534 solar permits were issued in Durham, October 2024 through September 2026: about 267 a year and 6% of all permits. 228 solar permits in the last 12 months (Oct 2025–Sep 2026), 25% fewer than the 306 in the 12 months before. The busiest month is October. The usual one took 60 days from issue to the city's final.

What this file covers: Building permits only: electrical, plumbing and mechanical permits are not in the file.

534permits issued
228last 12 months
Octbusiest month
60days, usual issue to final
89%finished
$1,000usual declared value
Sep 2026records through

Solar permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 53Oct2024Nov 2024: 19Dec 2024: 28Jan 2025: 27Jan2025Feb 2025: 28Mar 2025: 17Apr 2025: 9May 2025: 20Jun 2025: 17Jul 2025: 26JulAug 2025: 23Sep 2025: 39Oct 2025: 62Nov 2025: 17Dec 2025: 14Jan 2026: 8Jan2026Feb 2026: 19Mar 2026: 21Apr 2026: 23May 2026: 13Jun 2026: 14Jul 2026: 14JulAug 2026: 15Sep 2026: 8
The same numbers as a table
MonthPermits
Oct 202453
Nov 202419
Dec 202428
Jan 202527
Feb 202528
Mar 202517
Apr 20259
May 202520
Jun 202517
Jul 202526
Aug 202523
Sep 202539
Oct 202562
Nov 202517
Dec 202514
Jan 20268
Feb 202619
Mar 202621
Apr 202623
May 202613
Jun 202614
Jul 202614
Aug 202615
Sep 20268

Download this table (CSV)

When solar permits are filed

By calendar month, 100 = an average month (the thin line). October is the busiest (258), June the quietest (70). A busy month at the permit counter usually means a longer wait for a contractor.

January: 79 (100 = an average month)February: 106 (100 = an average month)March: 85 (100 = an average month)April: 72 (100 = an average month)May: 74 (100 = an average month)June: 70 (100 = an average month)July: 90 (100 = an average month)August: 85 (100 = an average month)September: 106 (100 = an average month)October: 258 (100 = an average month)258November: 81 (100 = an average month)December: 94 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January79
February106
March85
April72
May74
June70
July90
August85
September106
October258
November81
December94

Download this table (CSV)

How long a solar permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 273 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025306
Finished89.2%
Usual days, issue to final60
Middle half, days37–91

Download this table (CSV)

What a solar permit is declared at

The value written on the permit at application, from 533 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$1,000
Middle half$1,000–$5,000

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Alterations: Single Family House51596%
Alterations: Townhouse81%
Alterations: Duplex61%
New: Accessory Structure2under 1%
Addition: Single Family House1under 1%
Interior Alterations: Single Family House1under 1%
Repair: Single Family House1under 1%

Download this table (CSV)

How Durham compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Solar permits for other places in Raleigh–Durham. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City and County of Durham GIS, All Building Permits (PublicServices/Inspections MapServer layer 12; Durham Open Data), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential building permits from Durham City-County Inspections, the joint office that issues permits for the City of Durham and for unincorporated Durham County: new houses, townhouses and duplexes, additions, alterations, repairs, decks, roofs, accessory buildings and demolitions. Commercial permits and buildings of five or more units in the same file are not counted. Electrical, plumbing and mechanical permits are not in this file. Chapel Hill, Raleigh and the other Triangle towns run their own permit offices and are not in this file.

  • The file names no contractor, so there are no contractor lists, rankings or firm pages for Durham.
  • This is the building permit file only. Electrical, plumbing and mechanical permits are published only as a list of permits still open, so they are not counted.
  • The file covers the City of Durham and unincorporated Durham County together and does not say which a permit is in.
  • A permit counts as finished once the office issues its certificate of occupancy or completion; the final date is that sign-off date. The file has no expired status.
  • Solar, roofing, pools, fences and additions are sorted out of the broad alteration and repair permits by their work description. Decks count under Other.
  • The value is the building cost declared on the permit. The file has no ZIP code we can publish, so there are no ZIP code pages.
  • Each new townhouse unit gets its own permit, so new homes count units, not buildings. Townhouses are about half of the new homes.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Solar permits in Durham, NC", https://contractorrecords.com/durham/solar-permits, data through September 2026, from Durham City-County Inspections building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types.

Download the tables (CSV): Solar permits by month · Solar permits by calendar month (index) · Solar permits: days to final · Solar permits: declared value · Solar permits by permit type.

Common questions

  • How many solar permits does Durham issue a year?About 267 a year in Durham: 534 permits issued October 2024 through September 2026, 228 of them in the last 12 months.
  • How long does a solar permit take in Durham?The usual one took 60 days from issue to the city's final inspection, and the middle half took 37 to 91 days (273 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Durham file the most solar permits?October (258 against an average month of 100); June is the quietest (70). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.