Data through September 2026 · updated 19 Oct 2026
The usual permit in Durham takes 154 days from issue to the city's final inspection; the middle half take 109 to 207 days. That is from 4,052 permits issued Oct 2024–Sep 2025 that reached a final. Demolition permits are quickest at 50 days; new home permits take longest at 173 days. This is the time to finish the work and close the permit, not the wait for approval.
“How long does a permit take?” can mean two waits. This page measures the second one.
Getting the permit (not measured): application → issue, the wait for the city to approve the plans. Ask the city for its current review times.
Finishing the work (measured here): issue → final. From the day the city issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.
Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.
| Kind of work | Permits | Finished | Usual days to final | Middle half (days) |
|---|---|---|---|---|
| New homes | 2,620 | 93.1% | 173 | 146–225 |
| Remodels & repairs | 818 | 79.7% | 99 | 46–159 |
| Additions | 439 | 77.0% | 143 | 75–238 |
| Solar | 306 | 89.2% | 60 | 37–91 |
| Garages, sheds & shade structures | 122 | 65.6% | 86 | 49–162 |
| Other | 164 | 84.8% | 44 | 23–82 |
Each kind of work on its own, issue to the city's final.
The usual new home permit in Durham takes 173 days from issue to final; the middle half take 146 to 225 days (2,438 permits with a final date, issued Oct 2024–Sep 2025). 93% of the 2,620 permits issued then have finished. Durham new home permits →
The usual remodel and repair permit in Durham takes 99 days from issue to final; the middle half take 46 to 159 days (652 permits with a final date, issued Oct 2024–Sep 2025). 80% of the 818 permits issued then have finished. Durham remodel and repair permits →
The usual home addition permit in Durham takes 143 days from issue to final; the middle half take 75 to 238 days (338 permits with a final date, issued Oct 2024–Sep 2025). 77% of the 439 permits issued then have finished. Durham home addition permits →
The usual solar permit in Durham takes 60 days from issue to final; the middle half take 37 to 91 days (273 permits with a final date, issued Oct 2024–Sep 2025). 89% of the 306 permits issued then have finished. Durham solar permits →
The usual garage, shed and shade structure permit in Durham takes 86 days from issue to final; the middle half take 49 to 162 days (80 permits with a final date, issued Oct 2024–Sep 2025). 66% of the 122 permits issued then have finished. Durham garage, shed and shade structure permits →
The usual demolition permit in Durham takes 50 days from issue to final; the middle half take 28 to 142 days (64 permits with a final date, issued Oct 2024–Sep 2025).
From our cross-city data studies: the same measure, read the same way, for every city we cover.
How long permits take for other places in Raleigh–Durham. Each permit office keeps its own file, so the numbers are not added together.
Source: City and County of Durham GIS, All Building Permits (PublicServices/Inspections MapServer layer 12; Durham Open Data), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.
Residential building permits from Durham City-County Inspections, the joint office that issues permits for the City of Durham and for unincorporated Durham County: new houses, townhouses and duplexes, additions, alterations, repairs, decks, roofs, accessory buildings and demolitions. Commercial permits and buildings of five or more units in the same file are not counted. Electrical, plumbing and mechanical permits are not in this file. Chapel Hill, Raleigh and the other Triangle towns run their own permit offices and are not in this file.
Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →
Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:
Contractor Records, "How long do permits take in Durham, NC?", https://contractorrecords.com/durham/how-long-does-a-permit-take, data through September 2026, from Durham City-County Inspections building-permit records.Link to a table: By kind of work · Each kind of permit.
Download the tables (CSV): Days to final by kind of work.