Contractor Records
Home › Guides › Do I need an electrical permit in Nashville? Metro's list, who can pull it, and the deadlines

Do I need an electrical permit in Nashville? Metro's list, who can pull it, and the deadlines

Yes: Metro Nashville requires an electrical trade permit for nearly all new or moved wiring on a house, from relocating an outlet to increasing the service size, and it is pulled by a Metro-certified electrical contractor or by a homeowner who passes Metro's homeowner exam. 1,163 firms pulled 50,235 electrical permits on Davidson County homes from September 2023 to September 2026, and 89.5% of those a year or more old reached a final.

By Contractor Records · data through September 21, 2026

What Metro's list says

Metro Codes publishes a list of projects that may or may not require a permit, repeated on its renovation page (both read 23 October 2026). The electrical lines for one- and two-family homes:

Job Permit for a 1 or 2 family home
Electrical relocation of fixture, switch, outlet, etc. Yes
Electrical service, increase size Yes
Smoke detectors, new or relocation Yes, electrical
Attic fan Yes, electrical
Burglar alarm Yes, electrical
Solar systems, new Yes, electrical
Signs that require electrical installation Yes
Replacing dishwashers, disposals or refrigerators with ice makers No

The list is about work "not related to a new building or a building addition"; new houses and additions carry their electrical permits under the building permit. Metro also notes that a renovation permit "will trigger required inspections and allow trade permits to be pulled by registered contractors", so a kitchen remodel usually means a building permit plus separate electrical, plumbing and gas/mechanical permits.

Who can pull it

Metro's trades permit page (read 23 October 2026): "Only licensed contractors with an e-permit account can apply for a trade permit using our online system." Everyone else applies at the Department of Codes and Building Safety, Metro Office Building, 800 President Ronald Reagan Way, 7:30 a.m. to 4:00 p.m. weekdays, and can download the electrical application to fill in first.

Three layers of licensing sit behind the permit:

  1. Metro. The Mechanical, Plumbing, Electrical Examiners & Appeals Board issues the master electrician's certificate and the equipment and low-voltage installer licenses, and "shall also examine applicants for homeowner permits" (Metro Codes, read 22 October 2026).
  2. State, by contract size. Electrical subcontractors need a Tennessee CE license when their part is "$25,000 or more" (Board for Licensing Contractors). Metro's application asks "CONTRACT AMOUNT OVER $ 25000 (YES/NO)" and has the applicant certify compliance with the state Contractor's Licensing Act.
  3. Home improvement license. In Davidson County, residential remodeling jobs from $3,000 to $24,999 need a state home improvement license (Board for Licensing Contractors).

If you pull a homeowner permit, the permit names you, so the job never shows in any electrician's record, and Metro's 2021 repair-permit guidance warns that an owner who holds a permit "becomes totally responsible for code compliance including the work of subcontractors".

What the application asks, and the deadlines

The electrical application is itemised: temporary service (30 to 200 amps), building service size (60 to 6,000 amps), sub-panels, outlets and 220-volt outlets, residential appliances (disposal, dishwasher, dryer, water heater, range), HVAC disconnects and motors, electric heat by kW, and low-voltage devices. The fee follows those items; we could not find Metro's current electrical fee table online, so the amount is whatever Codes calculates at issue (615-862-6500).

The same form sets the clock: "work must start within six (6) months and must be completed within two (2) years of issue date", a permit becomes invalid if work is suspended for one year, and the director may grant 90-day extensions in writing.

Checking it afterwards

Search the address in ePermits or open the parcel in Metro's Parcel Viewer and choose Permit History. The electrical permit should carry your electrician's company and a passed final sign-off; the steps are in Nashville building permit search.

What 50,235 Nashville electrical permits show

Measure Nashville electrical
Permits on homes, September 2023 to September 2026 50,235
Firms 1,163
Firms with a permit in the last 12 months 764
Reached a final (permits a year or more old) 89.5%
Usual filed value $5,000
Middle half of firms' usual value $3,000 to $20,000
10th / 90th-percentile firm finished share (10+ permits) 71.4% / 100.0%
Firms with 5+ permits and none in the last 12 months 93
Busiest / quietest month February (114) / December (85)

Nashville electricians close their permits: 89.5% reached a final, and even the 10th-percentile busy firm got to 71.4%. The filed values matter for licensing. The middle half of firms usually file between $3,000 and $20,000, most of it inside the $3,000 to $24,999 home improvement band and under the $25,000 state line, so the Metro certificate is the credential that applies to most jobs. Filing is fairly flat across the year. Prices by job size are on Nashville electrical cost, and the totals by month on Nashville permit statistics.

See every Nashville electrician by permits finaled →

Before you hire

Ask whose master electrician's certificate the permit will be pulled under, and check the state license if the job is $25,000 or more; the steps are in Nashville contractor license lookup and the full checklist in hiring an electrician in Nashville. Compare firms on the Nashville electrician list. Other cities' rules are in do I need a permit for electrical work and panel upgrades; national prices in electrical work cost.

What this does not tell you

Our copy of Metro's permits has no final date we can time, so we cannot say how many days a Nashville electrical permit usually takes to close; ask the electrician when the final will be booked. Homeowner permits name the owner, not a firm. Metro's permit list was last revised in 2022; when in doubt, ask Codes before you start.

How we know this

The permit list, application terms and trade-permit rules are quoted from Metro Nashville Codes pages and forms read 23 October 2026; the examiners board and state license rules from Metro Codes and the Tennessee Board for Licensing Contractors, read 22 October 2026. Permit counts are Metro Nashville Codes electrical trade permits on homes in Davidson County, September 2023 to September 2026; "reached a final" uses permits a year or more old.

Numbers come from Metro Nashville (Davidson County) building and trade permits, data through September 21, 2026. Nobody paid to be on this page and nobody can.

Questions

  • Do I need a permit to add an outlet or move a light in Nashville?

    Yes. Metro Codes' permit list marks 'Electrical relocation of fixture, switch, outlet, etc.' as permit work for one- and two-family homes, along with new smoke detectors, attic fans, burglar alarms and a larger electrical service.

  • Can a homeowner pull an electrical permit in Nashville?

    Metro has a homeowner permit: its Mechanical, Plumbing, Electrical Examiners & Appeals Board 'shall also examine applicants for homeowner permits'. Homeowners cannot use the online system, which is only for licensed contractors with an ePermits account, so they apply in person at Metro Codes, 800 President Ronald Reagan Way.

  • How much is an electrical permit in Nashville?

    Metro's electrical application prices the permit by item (service size, sub-panels, outlets, appliances, HVAC disconnects), but we could not find Metro's current fee table online. Ask Codes on 615-862-6500 or see the fee on the permit when it is issued.

  • How long is a Nashville electrical permit good for?

    Metro's application says work must start within six months and be completed within two years of the issue date, and a permit becomes invalid if work is suspended for one year. The director may allow 90-day extensions in writing.

  • How do I check my electrician pulled a permit in Nashville?

    Search your address in Metro's ePermits (epermits.nashville.gov) or open the property in the Parcel Viewer and choose Permit History. The electrical permit should name your electrician's company, and its inspections should show a passed final.

Build your own list

Every firm with that kind of permit on record. Pick what you value. The list moves.