Contractor Records
Home › Jackson County › Solar

Solar permits in unincorporated Jackson County, OR

Data through July 2026 · updated 20 Oct 2026

1,003 solar permits were issued in unincorporated Jackson County, August 2024 through July 2026: about 502 a year and 14% of all permits. 420 solar permits in the last 12 months on file (Aug 2025–Jul 2026), 28% fewer than the 583 in the 12 months before. The busiest month is October.

1,003permits issued
420last 12 months on file
Octbusiest month
99%finished
$2,500usual declared value
Jul 2026records through

Solar permits by month

Permits issued each month, August 2024 through July 2026.

Aug 2024: 57Aug2024Sep 2024: 45Oct 2024: 90Nov 2024: 56Dec 2024: 27Jan 2025: 25Jan2025Feb 2025: 47Mar 2025: 60Apr 2025: 59May 2025: 42Jun 2025: 35Jul 2025: 40JulAug 2025: 52Sep 2025: 54Oct 2025: 50Nov 2025: 36Dec 2025: 19Jan 2026: 27Jan2026Feb 2026: 29Mar 2026: 39Apr 2026: 34May 2026: 37Jun 2026: 31Jul 2026: 12Jul
The same numbers as a table
MonthPermits
Aug 202457
Sep 202445
Oct 202490
Nov 202456
Dec 202427
Jan 202525
Feb 202547
Mar 202560
Apr 202559
May 202542
Jun 202535
Jul 202540
Aug 202552
Sep 202554
Oct 202550
Nov 202536
Dec 202519
Jan 202627
Feb 202629
Mar 202639
Apr 202634
May 202637
Jun 202631
Jul 202612

Download this table (CSV)

When solar permits are filed

By calendar month, 100 = an average month (the thin line). October is the busiest (167), December the quietest (55). A busy month at the permit counter usually means a longer wait for a contractor.

January: 62 (100 = an average month)February: 91 (100 = an average month)March: 118 (100 = an average month)April: 111 (100 = an average month)May: 95 (100 = an average month)June: 79 (100 = an average month)July: 62 (100 = an average month)August: 130 (100 = an average month)September: 118 (100 = an average month)October: 167 (100 = an average month)167November: 110 (100 = an average month)December: 55 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January62
February91
March118
April111
May95
June79
July62
August130
September118
October167
November110
December55

Download this table (CSV)

How many solar permits get finished

Permits issued Aug 2024–Jul 2025, at least 12 months before the file ends.

MeasureValue
Permits issued Aug 2024–Jul 2025583
Finished99.3%
Expired0.3%

Download this table (CSV)

What a solar permit is declared at

The value written on the permit at application, from 958 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$2,500
Middle half$500–$17,220

Download this table (CSV)

The county's own permit types

How the county filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Residential ELEC54855%
Residential STR42342%
Commercial ELEC222%
Commercial STR10under 1%

Download this table (CSV)

How Jackson County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Solar permits for other places in the Rogue Valley. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Jackson County GIS, Property/Permits_Building (building permits), read 20 Oct 2026. We count permits issued August 2024 through July 2026; denied and withdrawn permits are left out.

Permits issued by Jackson County's own Building Safety office, which serves unincorporated Jackson County: White City, Applegate, Ruch, Prospect, Trail and the rural valleys. Medford runs its own building department and has its own pages on this site; Ashland, Central Point and the other cities that run their own building departments are not in this file.

  • The county's file names no contractor, so there are no contractor lists, rankings or firm pages for this county.
  • The file has no issue date. Permits are counted by the month the application came in, and only once the county issued them; applications still in review are left out. The window ends in July 2026 so that recent applications have had time to be issued.
  • The file records the date of a permit's last status change, not a separate final inspection date, so we show how many permits finished but not how long they took.
  • Each trade on a job gets its own permit: a new house usually has a structural or dwelling permit plus separate electrical, mechanical and plumbing permits.
  • The value is the estimated cost on the permit. Electrical and plumbing permits usually carry none.
  • Agricultural-exempt buildings, grading permits and the 2020 wildfire disaster-relief cases are not counted.
  • The file has no ZIP code for most permits, so there are no ZIP code pages.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Solar permits in unincorporated Jackson County, OR", https://contractorrecords.com/jackson-county-or/solar-permits, data through July 2026, from Jackson County Development Services, Building Safety building-permit records.

Link to a table: By month · Season · How many get finished · Declared value · Permit types.

Download the tables (CSV): Solar permits by month · Solar permits by calendar month (index) · Solar permits: finished share · Solar permits: declared value · Solar permits by permit type.

Common questions

  • How many solar permits does Jackson County issue a year?About 502 a year in unincorporated Jackson County: 1,003 permits issued August 2024 through July 2026, 420 of them in the last 12 months on file (to July 2026).
  • When do people in Jackson County file the most solar permits?October (167 against an average month of 100); December is the quietest (55). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.