How long do permits take in unincorporated Kitsap County, WA?

Data through September 2026 · updated 23 Oct 2026

The usual permit in unincorporated Kitsap County takes 104 days from issue to the county's final inspection; the middle half take 36 to 225 days. That is from 2,164 permits issued Oct 2024–Sep 2025 that reached a final. Plumbing permits are quickest at 22 days; new home permits take longest at 260 days. This is the time to finish the work and close the permit, not the wait for approval.

104days, usual issue to final
36–225days, middle half
66%finished
2,164permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the county to approve the plans. Ask the county for its current review times.

Finishing the work (measured here): issue → final. From the day the county issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedUsual days to finalMiddle half (days)
HVAC60951.4%3215–101
Remodels & repairs63166.2%8145–176
New homes32667.8%260187–347
Plumbing28058.2%229–44
Roofing13861.6%6834–139
Garages, sheds & shade structures18469.6%13862–223
Electrical10657.5%4631–95
Solar11078.2%6638–127
Other70680.2%16485–271

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the county's final.

How long does an HVAC replacement take in Kitsap County, from permit to final?

The usual HVAC permit in unincorporated Kitsap County takes 32 days from issue to final; the middle half take 15 to 101 days (313 permits with a final date, issued Oct 2024–Sep 2025). 51% of the 609 permits issued then have finished. Kitsap County HVAC permits →

How long does a remodel take in Kitsap County, from permit to final?

The usual remodel and repair permit in unincorporated Kitsap County takes 81 days from issue to final; the middle half take 45 to 176 days (418 permits with a final date, issued Oct 2024–Sep 2025). 66% of the 631 permits issued then have finished. Kitsap County remodel and repair permits →

How long does building a new home take in Kitsap County, from permit to final?

The usual new home permit in unincorporated Kitsap County takes 260 days from issue to final; the middle half take 187 to 347 days (221 permits with a final date, issued Oct 2024–Sep 2025). 68% of the 326 permits issued then have finished. Kitsap County new home permits →

How long does plumbing work take in Kitsap County, from permit to final?

The usual plumbing permit in unincorporated Kitsap County takes 22 days from issue to final; the middle half take 9 to 44 days (163 permits with a final date, issued Oct 2024–Sep 2025). 58% of the 280 permits issued then have finished. Kitsap County plumbing permits →

How long does a roof replacement take in Kitsap County, from permit to final?

The usual roofing permit in unincorporated Kitsap County takes 68 days from issue to final; the middle half take 34 to 139 days (85 permits with a final date, issued Oct 2024–Sep 2025). 62% of the 138 permits issued then have finished. Kitsap County roofing permits →

How long does a garage, shed or patio cover take in Kitsap County, from permit to final?

The usual garage, shed and shade structure permit in unincorporated Kitsap County takes 138 days from issue to final; the middle half take 62 to 223 days (127 permits with a final date, issued Oct 2024–Sep 2025). 70% of the 184 permits issued then have finished. Kitsap County garage, shed and shade structure permits →

How long does electrical work take in Kitsap County, from permit to final?

The usual electrical permit in unincorporated Kitsap County takes 46 days from issue to final; the middle half take 31 to 95 days (61 permits with a final date, issued Oct 2024–Sep 2025). 58% of the 106 permits issued then have finished.

How long does a solar installation take in Kitsap County, from permit to final?

The usual solar permit in unincorporated Kitsap County takes 66 days from issue to final; the middle half take 38 to 127 days (86 permits with a final date, issued Oct 2024–Sep 2025). 78% of the 110 permits issued then have finished.

How long does a demolition take in Kitsap County, from permit to final?

The usual demolition permit in unincorporated Kitsap County takes 91 days from issue to final; the middle half take 26 to 187 days (53 permits with a final date, issued Oct 2024–Sep 2025).

How Kitsap County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

How long permits take for other places in Seattle and Puget Sound. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Kitsap County DCD, Permit Activity DCD Permits (ArcGIS: Permit_Activity_DCD_Permits_view), read 23 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits Kitsap County Community Development issues for unincorporated land only: Silverdale, Kingston, Manchester, Hansville, Seabeck, Olalla, the county parts of the Port Orchard, Bremerton and Poulsbo growth areas, and the rural county. Bremerton, Port Orchard, Poulsbo and Bainbridge Island issue their own permits and are not in this file.

  • The county's file names no contractor, so there are no contractor lists, rankings or firm pages for this county.
  • Electrical permits in unincorporated Kitsap County come from the Washington Department of Labor & Industries, not the county, so electrical work (other than generators filed with gas piping) is not in this file.
  • The county files heating, cooling and plumbing under one mechanical-and-plumbing permit; we split it by the work described.
  • Solar permits are filed with the county fire marshal; a solar permit counts as a home when its parcel is residential.
  • The file has no expired status: a permit that lapsed without a final still shows as issued, so it counts as open here.
  • The file has no ZIP code, so there are no ZIP code pages.
  • Job value is the value declared on the permit. A final date is the county's finaled date.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in unincorporated Kitsap County, WA?", https://contractorrecords.com/kitsap-county/how-long-does-a-permit-take, data through September 2026, from Kitsap County Department of Community Development building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Kitsap County?From issue to final inspection, the usual permit takes 104 days (middle half 36 to 225 days), from 2,164 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the county for its current review times.
  • Which permits finish fastest in Kitsap County?Plumbing permits, at 22 days. The slowest are new home permits, at 260 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Kitsap County?66% of the 3,275 permits issued Oct 2024–Sep 2025 have finished; the rest are still open (the file doesn't mark permits expired).
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.