The usual permit in the City of Auburn takes 63 days from issue to the city's final inspection; the middle half take 23 to 184 days. That is from 1,343 permits issued Feb 2023–Jan 2024 that reached a final. HVAC permits are quickest at 34 days; new home permits take longest at 217 days. This is the time to finish the work and close the permit, not the wait for approval.
“How long does a permit take?” can mean two waits. This page measures the second one.
Getting the permit (not measured): application → issue, the wait for the city to approve the plans. Ask the city for its current review times.
Finishing the work (measured here): issue → final. From the day the city issued the permit to the day it recorded the final inspection. We count only permits issued Feb 2023–Jan 2024, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.
Permits issued Feb 2023–Jan 2024. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.
Each kind of work on its own, issue to the city's final.
The usual HVAC permit in the City of Auburn takes 34 days from issue to final; the middle half take 18 to 105 days (518 permits with a final date, issued Feb 2023–Jan 2024). 60% of the 867 permits issued then have finished and 2% expired. Auburn HVAC permits →
The usual plumbing permit in the City of Auburn takes 82 days from issue to final; the middle half take 13 to 188 days (255 permits with a final date, issued Feb 2023–Jan 2024). 79% of the 321 permits issued then have finished and 1% expired. Auburn plumbing permits →
The usual solar permit in the City of Auburn takes 44 days from issue to final; the middle half take 27 to 68 days (95 permits with a final date, issued Feb 2023–Jan 2024). 93% of the 102 permits issued then have finished and 7% expired.
The usual new home permit in the City of Auburn takes 217 days from issue to final; the middle half take 191 to 267 days (50 permits with a final date, issued Feb 2023–Jan 2024).
From our cross-city data studies: the same measure, read the same way, for every city we cover.
How long permits take for other places in Seattle and Puget Sound. Each permit office keeps its own file, so the numbers are not added together.
Seattle, WABellevue, WAKing County, WAEverett, WATacoma, WAPierce County, WAKitsap County, WA
Source: City of Auburn open data, Permits (Socrata fted-8bve), read 19 Oct 2026. We count permits issued February 2023 through January 2025; denied and withdrawn permits are left out.
Building, mechanical, plumbing, side-sewer, demolition, fire-protection and sign permits issued by the City of Auburn for property inside city limits, in both its King County and Pierce County parts (Lea Hill, Lakeland Hills, West Hill and downtown). Electrical permits are issued by the Washington State Department of Labor & Industries and are not in this file. Unincorporated King County permits (the separate King County page) and neighbouring cities such as Kent, Federal Way, Algona and Pacific are not in this file. Street, utility, storm, grading and right-of-way permits are left out.
Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →
Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:
Contractor Records, "How long do permits take in the City of Auburn, WA?", https://contractorrecords.com/auburn-wa/how-long-does-a-permit-take, data through January 2025, from City of Auburn Community Development building-permit records.Link to a table: By kind of work · Each kind of permit.
Download the tables (CSV): Days to final by kind of work.