How long do permits take in unincorporated Pierce County, WA?

Data through September 2026 · updated 20 Oct 2026

The usual permit in unincorporated Pierce County takes 74 days from issue to the county's final inspection; the middle half take 21 to 169 days. That is from 5,187 permits issued Oct 2024–Sep 2025 that reached a final. Plumbing permits are quickest at 21 days; home addition permits take longest at 257 days. This is the time to finish the work and close the permit, not the wait for approval.

74days, usual issue to final
21–169days, middle half
69%finished
5,187permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the county to approve the plans. Ask the county for its current review times.

Finishing the work (measured here): issue → final. From the day the county issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedExpiredUsual days to finalMiddle half (days)
HVAC2,68361.8%37.0%2414–49
Plumbing1,41263.0%35.5%217–70
New homes1,38589.9%2.0%166142–208
Remodels & repairs58266.3%30.1%6529–152
Garages, sheds & shade structures29470.4%17.3%16887–284
Solar19184.3%15.2%4026–56
Other62068.4%22.9%13163–252

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the county's final.

How long does an HVAC replacement take in Pierce County, from permit to final?

The usual HVAC permit in unincorporated Pierce County takes 24 days from issue to final; the middle half take 14 to 49 days (1,659 permits with a final date, issued Oct 2024–Sep 2025). 62% of the 2,683 permits issued then have finished and 37% expired. Pierce County HVAC permits →

How long does plumbing work take in Pierce County, from permit to final?

The usual plumbing permit in unincorporated Pierce County takes 21 days from issue to final; the middle half take 7 to 70 days (890 permits with a final date, issued Oct 2024–Sep 2025). 63% of the 1,412 permits issued then have finished and 36% expired. Pierce County plumbing permits →

How long does building a new home take in Pierce County, from permit to final?

The usual new home permit in unincorporated Pierce County takes 166 days from issue to final; the middle half take 142 to 208 days (1,244 permits with a final date, issued Oct 2024–Sep 2025). 90% of the 1,385 permits issued then have finished and 2% expired. Pierce County new home permits →

How long does a remodel take in Pierce County, from permit to final?

The usual remodel and repair permit in unincorporated Pierce County takes 65 days from issue to final; the middle half take 29 to 152 days (386 permits with a final date, issued Oct 2024–Sep 2025). 66% of the 582 permits issued then have finished and 30% expired. Pierce County remodel and repair permits →

How long does a garage, shed or patio cover take in Pierce County, from permit to final?

The usual garage, shed and shade structure permit in unincorporated Pierce County takes 168 days from issue to final; the middle half take 87 to 284 days (207 permits with a final date, issued Oct 2024–Sep 2025). 70% of the 294 permits issued then have finished and 17% expired. Pierce County garage, shed and shade structure permits →

How long does a solar installation take in Pierce County, from permit to final?

The usual solar permit in unincorporated Pierce County takes 40 days from issue to final; the middle half take 26 to 56 days (161 permits with a final date, issued Oct 2024–Sep 2025). 84% of the 191 permits issued then have finished and 15% expired. Pierce County solar permits →

How long does a demolition take in Pierce County, from permit to final?

The usual demolition permit in unincorporated Pierce County takes 99 days from issue to final; the middle half take 28 to 154 days (57 permits with a final date, issued Oct 2024–Sep 2025). Pierce County demolition permits →

How long does a home addition take in Pierce County, from permit to final?

The usual home addition permit in unincorporated Pierce County takes 257 days from issue to final; the middle half take 197 to 374 days (58 permits with a final date, issued Oct 2024–Sep 2025). Pierce County home addition permits →

How Pierce County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

How long permits take for other places in Seattle and Puget Sound. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Pierce County Open Data, Permits - Pierce County (Permits_Pierce_County, from PALS Plus), read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, mechanical, plumbing, manufactured-home, demolition, pool and sign permits Pierce County Planning & Public Works issues for unincorporated land only: Spanaway, Graham, Frederickson, Parkland, South Hill, Lake Tapps, the Key Peninsula, Gig Harbor peninsula and similar places. Tacoma, Lakewood, Puyallup, University Place, Gig Harbor city, Bonney Lake and the other cities run their own permit offices and are not in this file. Engineering, sewer and fire-prevention permits are left out.

  • The county's open permit file names no contractor, so there are no contractor lists, rankings or firm pages for Pierce County.
  • The value is the building valuation the county works out to set the permit fee (largely from floor area and type of construction); mechanical and plumbing permits carry none. It is not a final cost.
  • The file has no property ZIP code, so there are no ZIP code pages for Pierce County.
  • Electrical permits in Washington are issued by the state Department of Labor & Industries, not the county, so electrical work does not appear here; rooftop solar appears only when it needed a county building permit.
  • Mechanical permits cover furnaces, heat pumps and air conditioning, and also gas piping, gas fireplaces and water heaters; those last are counted as plumbing when the description says so.
  • A final date is the county's final date; permits the county cancelled are not counted.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in unincorporated Pierce County, WA?", https://contractorrecords.com/pierce-county/how-long-does-a-permit-take, data through September 2026, from Pierce County Planning & Public Works building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Pierce County?From issue to final inspection, the usual permit takes 74 days (middle half 21 to 169 days), from 5,187 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the county for its current review times.
  • Which permits finish fastest in Pierce County?Plumbing permits, at 21 days. The slowest are home addition permits, at 257 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Pierce County?69% of the 7,529 permits issued Oct 2024–Sep 2025 have finished; 27% expired without a final and the rest are still open.
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.