New home permits in the City of Arlington, TX

Data through September 2026 · updated 19 Oct 2026

1,110 new home permits were issued in the City of Arlington, October 2024 through September 2026: about 555 a year and 12% of all permits. 658 new home permits in the last 12 months (Oct 2025–Sep 2026), 46% more than the 452 in the 12 months before. The busiest month is August. The usual one took 215 days from issue to the city's final.

What this file covers: The city's public file holds building, fence, pool and sign permits only; electrical, plumbing, mechanical and roofing permits are not in it.

1,110permits issued
658last 12 months
Augbusiest month
215days, usual issue to final
94%finished
$253,134usual declared value
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 18Oct2024Nov 2024: 10Dec 2024: 36Jan 2025: 62Jan2025Feb 2025: 34Mar 2025: 31Apr 2025: 24May 2025: 8Jun 2025: 72Jul 2025: 30JulAug 2025: 79Sep 2025: 48Oct 2025: 23Nov 2025: 40Dec 2025: 66Jan 2026: 39Jan2026Feb 2026: 50Mar 2026: 42Apr 2026: 32May 2026: 94Jun 2026: 43Jul 2026: 67JulAug 2026: 70Sep 2026: 92
The same numbers as a table
MonthPermits
Oct 202418
Nov 202410
Dec 202436
Jan 202562
Feb 202534
Mar 202531
Apr 202524
May 20258
Jun 202572
Jul 202530
Aug 202579
Sep 202548
Oct 202523
Nov 202540
Dec 202566
Jan 202639
Feb 202650
Mar 202642
Apr 202632
May 202694
Jun 202643
Jul 202667
Aug 202670
Sep 202692

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). August is the busiest (161), October the quietest (44). A busy month at the permit counter usually means a longer wait for a contractor.

January: 109 (100 = an average month)February: 91 (100 = an average month)March: 79 (100 = an average month)April: 61 (100 = an average month)May: 110 (100 = an average month)June: 124 (100 = an average month)July: 105 (100 = an average month)August: 161 (100 = an average month)161September: 151 (100 = an average month)October: 44 (100 = an average month)November: 54 (100 = an average month)December: 110 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January109
February91
March79
April61
May110
June124
July105
August161
September151
October44
November54
December110

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 424 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025452
Finished93.8%
Expired2.9%
Usual days, issue to final215
Middle half, days148–293

Download this table (CSV)

What a new home permit is declared at

The value written on the permit at application, from 1,108 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$253,134
Middle half$214,000–$300,000

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Single-Family: New Construction1,07196%
Manufactured Housing: Remove/Replace232%
Two-Family: New Construction161%

Download this table (CSV)

How Arlington compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

New home permits for other places in Dallas–Fort Worth. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Arlington GIS, OpenData/OD_Property: Issued Permits (3-year view), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, fence, pool and sign permits the City of Arlington, Texas issues inside city limits. Not to be confused with Arlington, Virginia, which has its own pages on this site. Electrical, plumbing, mechanical and roofing permits are not in the city's public file, and neither are certificates of occupancy.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Arlington.
  • The city publishes only building, fence, pool and sign permits. Electrical, plumbing, HVAC and roofing permits are not in the file, so those kinds of work do not appear here.
  • The city keeps a rolling three-year view: older permits drop out of the file, so there is no history before late 2023.
  • The value is the construction valuation declared on the permit; sign permits carry none.
  • The file has no ZIP code, so there are no ZIP code pages.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in the City of Arlington, TX", https://contractorrecords.com/arlington-tx/new-home-permits, data through September 2026, from the City of Arlington Planning and Development Services building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits: declared value · New homes permits by permit type.

Common questions

  • How many new home permits does Arlington issue a year?About 555 a year in the City of Arlington: 1,110 permits issued October 2024 through September 2026, 658 of them in the last 12 months.
  • How long does a new home permit take in Arlington?The usual one took 215 days from issue to the city's final inspection, and the middle half took 148 to 293 days (424 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Arlington file the most new home permits?August (161 against an average month of 100); October is the quietest (44). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.