Building permits in 33843, unincorporated Polk County

Data through September 2026 · updated 20 Oct 2026

342 building permits were issued in ZIP code 33843 by the Polk County Building Division, October 2024 through September 2026: 2% of the 15,936 in unincorporated Polk County, the 18th busiest ZIP code. New home permits lead with 112. 180 permits in the last 12 months (Oct 2025–Sep 2026), 11% more than the 162 in the 12 months before. Permits from a city that runs its own permit office are not counted.

342permits in 33843
180last 12 months
96%for homes
85days, usual issue to final
Sep 2026records through

Permits in 33843 by kind of work

Share here is the part of the 342 permits in 33843; countywide is the same for all of unincorporated Polk County.

Kind of workPermitsShare hereCountywide
New homes11233%27%
Garages, sheds & shade structures7622%18%
Demolition3811%4%
Remodels & repairs3611%13%
Solar247%13%
Electrical206%5%
Pools & spas93%4%
Additions72%1%
Roofing3under 1%2%
HVAC1under 1%under 1%
Plumbing1under 1%under 1%
Other154%12%

Download this table (CSV)

Permits in 33843 by year

Permits issued in each calendar year of the window.

YearMonthsPermitsPer year
2024 (from October)335140
202512175175
2026 (through September)9132176

Download this table (CSV)

How permits in 33843 finish

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends.

Measure33843Countywide
Permits issued Oct 2024–Sep 20251628,322
Finished93.8%90.1%
Usual days, issue to final8583

Download this table (CSV)

How these numbers are made

Source: Polk County Property Appraiser, public FTP permit file (ftp_permit.zip, Appraisal Data), read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits the Polk County building division issues for unincorporated land only (Poinciana, Lakeland Highlands, Four Corners, Kathleen, Wahneta and similar places). Lakeland, Winter Haven, Haines City, Davenport, Bartow, Lake Wales and the other cities issue their own permits and are not counted here. The list comes from the Polk County Property Appraiser, which collects only permits that can change a property's taxable value.

  • The file names no contractor, so there are no contractor lists, rankings or firm pages for this county.
  • The Property Appraiser collects only permits that can change taxable value: new homes, additions, pools, solar, generators, garages and similar. Re-roofs, fences, driveways and most like-for-like repairs are left out, so those kinds of work are undercounted or missing.
  • A final date is the county's final inspection of a new building or addition. A permit the Property Appraiser marks completed without one counts as finished but adds no days.
  • The value is the estimated value on the permit.
  • The ZIP code is the parcel's site ZIP on the Property Appraiser's roll.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Building permits in 33843, unincorporated Polk County", https://contractorrecords.com/polk-county/zip/33843, data through September 2026, from the Polk County Building Division building-permit records.

Link to a table: By kind of work · By year · How permits finish.

Download the tables (CSV): Permits in 33843 by kind of work · Permits in 33843 by year · Permits in 33843: finished and days to final.

Common questions

  • How many building permits were issued in 33843?342 permits issued by the county in ZIP code 33843, October 2024 through September 2026: 112 new homes, 76 garages, sheds & shade structures, 38 demolition. 180 were in the last 12 months.
  • What is built most in 33843?New homes: 112 of the 342 permits (33%), against 27% countywide.
  • How long does a permit take in 33843?The usual permit issued here Oct 2024–Sep 2025 took 85 days from issue to final (120 permits with a final date), against 83 days countywide.
  • Who did the work in 33843?The county's file doesn't name contractors, so we can't say. Ask a contractor for the permit numbers of past jobs and check them with the county.