Contractor Records
Home › Wake County › Solar

Solar permits in unincorporated Wake County and the towns of Knightdale, Wendell, Zebulon and Rolesville, NC

Data through September 2026 · updated 20 Oct 2026

420 solar permits were issued in unincorporated Wake County and the towns of Knightdale, Wendell, Zebulon and Rolesville, October 2024 through September 2026: about 210 a year and 4% of all permits. 202 solar permits in the last 12 months (Oct 2025–Sep 2026), 7% fewer than the 218 in the 12 months before. The busiest month is September. The usual one took 113 days from issue to the county's final. 27545 has the most, 72.

420permits issued
202last 12 months
Sepbusiest month
113days, usual issue to final
78%finished
$32,500usual declared value
Sep 2026records through

Solar permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 19Oct2024Nov 2024: 25Dec 2024: 9Jan 2025: 15Jan2025Feb 2025: 16Mar 2025: 10Apr 2025: 19May 2025: 14Jun 2025: 22Jul 2025: 12JulAug 2025: 23Sep 2025: 34Oct 2025: 23Nov 2025: 22Dec 2025: 15Jan 2026: 8Jan2026Feb 2026: 11Mar 2026: 16Apr 2026: 12May 2026: 19Jun 2026: 15Jul 2026: 21JulAug 2026: 18Sep 2026: 22
The same numbers as a table
MonthPermits
Oct 202419
Nov 202425
Dec 20249
Jan 202515
Feb 202516
Mar 202510
Apr 202519
May 202514
Jun 202522
Jul 202512
Aug 202523
Sep 202534
Oct 202523
Nov 202522
Dec 202515
Jan 20268
Feb 202611
Mar 202616
Apr 202612
May 202619
Jun 202615
Jul 202621
Aug 202618
Sep 202622

Download this table (CSV)

When solar permits are filed

By calendar month, 100 = an average month (the thin line). September is the busiest (160), January the quietest (66). A busy month at the permit counter usually means a longer wait for a contractor.

January: 66 (100 = an average month)February: 77 (100 = an average month)March: 74 (100 = an average month)April: 89 (100 = an average month)May: 94 (100 = an average month)June: 106 (100 = an average month)July: 94 (100 = an average month)August: 117 (100 = an average month)September: 160 (100 = an average month)160October: 120 (100 = an average month)November: 134 (100 = an average month)December: 69 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January66
February77
March74
April89
May94
June106
July94
August117
September160
October120
November134
December69

Download this table (CSV)

How long a solar permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 171 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025218
Finished78.4%
Expired1.8%
Usual days, issue to final113
Middle half, days49–348

Download this table (CSV)

What a solar permit is declared at

The value written on the permit at application, from 419 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$32,500
Middle half$18,681–$44,477

Download this table (CSV)

ZIP codes with the most solar permits

Counted at the property's ZIP code. Share is the part of the county's 420 solar permits.

ZIP codePermitsShare
275457217%
275916515%
275975313%
276034210%
27587266%
27606256%
27592246%
27540225%
27614195%
27613143%

Download this table (CSV)

How Wake County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Solar permits for other places in Raleigh–Durham. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Wake County Inspections, Development & Permits, Building Permits (ArcGIS MapServer, Wake County Open Data), read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building permits Wake County Permits and Inspections issues: unincorporated Wake County, plus the towns of Knightdale, Wendell, Zebulon and Rolesville, which use the county's inspections office. Raleigh and Cary run their own permit offices and have their own pages on this site; the few county-inspected parcels inside them are left out. Apex, Wake Forest, Garner, Holly Springs, Fuquay-Varina and Morrisville also issue their own permits and appear here only for a handful of county-inspected parcels.

  • The county's file has a contractor column but it is empty on every permit, so there are no contractor lists, rankings or firm pages for Wake County.
  • The county publishes building permits only: new homes, additions, alterations, accessory buildings, pools, decks and commercial work. Separate electrical, plumbing, HVAC and roofing permits are not in the file, so those kinds of work do not appear here.
  • The value is the construction valuation declared on the permit, which sets the fee. It is not a final cost.
  • Garages, sheds and decks are counted together. Home alterations are counted as remodels and repairs unless the description says solar or a reroof.
  • A final date is the date the permit was finaled.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Solar permits in unincorporated Wake County and the towns of Knightdale, Wendell, Zebulon and Rolesville, NC", https://contractorrecords.com/wake-county/solar-permits, data through September 2026, from Wake County Permits and Inspections building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code.

Download the tables (CSV): Solar permits by month · Solar permits by calendar month (index) · Solar permits: days to final · Solar permits: declared value · Solar permits by ZIP code.

Common questions

  • How many solar permits does Wake County issue a year?About 210 a year in unincorporated Wake County and the towns of Knightdale, Wendell, Zebulon and Rolesville: 420 permits issued October 2024 through September 2026, 202 of them in the last 12 months.
  • How long does a solar permit take in Wake County?The usual one took 113 days from issue to the county's final inspection, and the middle half took 49 to 348 days (171 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Wake County file the most solar permits?September (160 against an average month of 100); January is the quietest (66). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most solar permits in Wake County?27545, with 72 of the 420 (17%); then 27591 (65).