How long do permits take in Edina, MN?

Data through September 2026 · updated 19 Oct 2026

The usual permit in Edina takes 43 days from issue to the city's final inspection; the middle half take 15 to 124 days. That is from 4,073 permits issued Oct 2024–Sep 2025 that reached a final. Plumbing permits are quickest at 23 days; demolition permits take longest at 93 days. This is the time to finish the work and close the permit, not the wait for approval.

43days, usual issue to final
15–124days, middle half
72%finished
4,073permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve the plans. Ask the city for its current review times.

Finishing the work (measured here): issue → final. From the day the city issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedExpiredUsual days to finalMiddle half (days)
Plumbing2,07369.6%0.0%238–87
HVAC1,39975.9%0.0%3014–112
Remodels & repairs1,29871.0%0.0%8542–146
Roofing36179.2%0.0%4116–91
Other25877.5%0.4%4520–133

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the city's final.

How long does plumbing work take in Edina, from permit to final?

The usual plumbing permit in Edina takes 23 days from issue to final; the middle half take 8 to 87 days (1,442 permits with a final date, issued Oct 2024–Sep 2025). 70% of the 2,073 permits issued then have finished and 0% expired. Edina plumbing permits →

How long does an HVAC replacement take in Edina, from permit to final?

The usual HVAC permit in Edina takes 30 days from issue to final; the middle half take 14 to 112 days (1,062 permits with a final date, issued Oct 2024–Sep 2025). 76% of the 1,399 permits issued then have finished and 0% expired. Edina HVAC permits →

How long does a remodel take in Edina, from permit to final?

The usual remodel and repair permit in Edina takes 85 days from issue to final; the middle half take 42 to 146 days (921 permits with a final date, issued Oct 2024–Sep 2025). 71% of the 1,298 permits issued then have finished and 0% expired. Edina remodel and repair permits →

How long does a roof replacement take in Edina, from permit to final?

The usual roofing permit in Edina takes 41 days from issue to final; the middle half take 16 to 91 days (286 permits with a final date, issued Oct 2024–Sep 2025). 79% of the 361 permits issued then have finished and 0% expired. Edina roofing permits →

How long does a demolition take in Edina, from permit to final?

The usual demolition permit in Edina takes 93 days from issue to final; the middle half take 59 to 179 days (59 permits with a final date, issued Oct 2024–Sep 2025).

How Edina compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

How long permits take for other places in the Twin Cities. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Edina Permit Finder, PIMS Permits table (ArcGIS Building/Permit_Finder FeatureServer layer 5), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits the City of Edina issues for houses, townhouses and two-family homes inside the city: building, remodel, reroof, siding, deck and addition permits, mechanical and plumbing permits, home sewer and water work, and solar. Commercial, institutional and apartment (3+ unit) permits, signs, driveways, grading and tree escrows in the same table are not counted. Minneapolis, Bloomington, Richfield and the other Hennepin County cities run their own permit offices and are not in this file.

  • The city's permit table names no contractor, so there are no contractor lists, rankings or firm pages for Edina.
  • The table has no electrical permits, so there are no electrical counts here.
  • The table has no status column. A permit with a final date counts as finished, one with a dead date as expired and one with a cancelled date is left out; all others are open.
  • The city files most furnace, air conditioner, water heater, softener and gas piping permits under one broad residential type. We sort them into HVAC and plumbing by their work description; a permit that names both counts under the trade it names first.
  • The value is the valuation on the permit. The ZIP code comes from the Metropolitan Council's 2025 parcel points for the permit's parcel.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in Edina, MN?", https://contractorrecords.com/edina/how-long-does-a-permit-take, data through September 2026, from the City of Edina Building Inspections building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Edina?From issue to final inspection, the usual permit takes 43 days (middle half 15 to 124 days), from 4,073 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the city for its current review times.
  • Which permits finish fastest in Edina?Plumbing permits, at 23 days. The slowest are demolition permits, at 93 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Edina?72% of the 5,629 permits issued Oct 2024–Sep 2025 have finished; under 1% expired without a final and the rest are still open.
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.