The usual Minneapolis permit takes 101 days from issue to the city's final inspection or closeout, across all 13 kinds of work on file (74,258 permits, October 2023 through September 2026). The usual plumbing permit, the biggest trade here, takes 113 days. Drain Tile & Waterproofing is quickest at 48 days; new home the slowest at 396 days. This is the turnaround to finish the work and close the permit, not the wait for approval.
“How long does a permit take?” can mean two waits. This page measures the second one.
Getting the permit (not measured): application → issue, the wait for the city to approve it. Minneapolis's file we read does not carry a usable application date, so we don't guess at it. Ask the permit office for its current review times.
Finishing the work (measured here): issue → completion. The day the city issued the permit to the day it recorded a final inspection or closeout. That is the contractor's part: doing the work and getting it signed off.
What “finished” means in Minneapolis: For contractors with at least 5 permits a year or more old, the share that were closed.
Speed: How long their permits take from issue to close, using the city's dates, compared with other Minneapolis contractors in the trade. Shown for firms with 10+ permits.
Usual is the middle permit: half finish sooner, half later. Finished is the share of permits a year or more old that the city closed out.
| Trade | Permits | Usual days to finish | Finished | Firms with 10+ permits |
|---|---|---|---|---|
| Plumbing | 20,012 | 113 | 71.3% | 238 |
| Roofing | 18,620 | 85 | 93.0% | 355 |
| HVAC & Gas | 18,180 | 85 | 76.0% | 151 |
| Remodel | 5,552 | 161 | 75.0% | 88 |
| Windows & Doors | 5,528 | 98 | 81.2% | 52 |
| Siding | 1,823 | 113 | 89.1% | 42 |
| Solar | 1,321 | 76 | 93.5% | 12 |
| Drain Tile & Waterproofing | 1,029 | 48 | 81.7% | 13 |
| Garage & Accessory | 706 | 143 | 93.3% | 4 |
| Deck, Porch & Stoop | 692 | 166 | 66.3% | 6 |
| Addition | 404 | 338 | 75.8% | 2 |
| New Home | 204 | 396 | 84.5% | 4 |
| Demolition | 187 | 151 | 86.0% | 5 |
Each trade on its own, from issue to the city's sign-off. The spread between the quickest and slowest quarter of firms is the part you can choose.
The usual plumbing permit in Minneapolis takes 113 days from issue to the city's final inspection or closeout (20,012 permits, October 2023 through September 2026). 71.3% of plumbing permits a year or more old have been closed out. The quickest quarter of firms usually finish in 1.5 months, the slowest quarter in 5 months. The wait for approval before issue is not in Minneapolis's file.
230 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis plumbing contractors →
The usual roofing permit in Minneapolis takes 85 days from issue to the city's final inspection or closeout (18,620 permits, October 2023 through September 2026). 93.0% of roofing permits a year or more old have been closed out. The quickest quarter of firms usually finish in 2 months, the slowest quarter in 3.6 months. The wait for approval before issue is not in Minneapolis's file.
352 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis roofing contractors →
The usual HVAC & gas permit in Minneapolis takes 85 days from issue to the city's final inspection or closeout (18,180 permits, October 2023 through September 2026). 76.0% of HVAC & gas permits a year or more old have been closed out. The quickest quarter of firms usually finish in 1 month, the slowest quarter in 5 months. The wait for approval before issue is not in Minneapolis's file.
145 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis HVAC & gas contractors →
The usual remodel permit in Minneapolis takes 161 days from issue to the city's final inspection or closeout (5,552 permits, October 2023 through September 2026). 75.0% of remodel permits a year or more old have been closed out. The quickest quarter of firms usually finish in 1.4 months, the slowest quarter in 5.2 months. The wait for approval before issue is not in Minneapolis's file.
81 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis remodel contractors →
The usual windows & doors permit in Minneapolis takes 98 days from issue to the city's final inspection or closeout (5,528 permits, October 2023 through September 2026). 81.2% of windows & doors permits a year or more old have been closed out. The quickest quarter of firms usually finish in 2.2 months, the slowest quarter in 3.4 months. The wait for approval before issue is not in Minneapolis's file.
50 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis windows & doors contractors →
The usual siding permit in Minneapolis takes 113 days from issue to the city's final inspection or closeout (1,823 permits, October 2023 through September 2026). 89.1% of siding permits a year or more old have been closed out. The quickest quarter of firms usually finish in 2.5 months, the slowest quarter in 4.2 months. The wait for approval before issue is not in Minneapolis's file.
42 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis siding contractors →
The usual solar permit in Minneapolis takes 76 days from issue to the city's final inspection or closeout (1,321 permits, October 2023 through September 2026). 93.5% of solar permits a year or more old have been closed out. The wait for approval before issue is not in Minneapolis's file.
The usual drain tile & waterproofing permit in Minneapolis takes 48 days from issue to the city's final inspection or closeout (1,029 permits, October 2023 through September 2026). 81.7% of drain tile & waterproofing permits a year or more old have been closed out. The quickest quarter of firms usually finish in 0.5 months, the slowest quarter in 1.8 months. The wait for approval before issue is not in Minneapolis's file.
13 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis drain tile & waterproofing contractors →
The usual garage & accessory permit in Minneapolis takes 143 days from issue to the city's final inspection or closeout (706 permits, October 2023 through September 2026). 93.3% of garage & accessory permits a year or more old have been closed out. The quickest quarter of firms usually finish in 3.7 months, the slowest quarter in 4.3 months. The wait for approval before issue is not in Minneapolis's file.
4 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis garage & accessory contractors →
The usual deck, porch & stoop permit in Minneapolis takes 166 days from issue to the city's final inspection or closeout (692 permits, October 2023 through September 2026). 66.3% of deck, porch & stoop permits a year or more old have been closed out. The quickest quarter of firms usually finish in 2.2 months, the slowest quarter in 19 months. The wait for approval before issue is not in Minneapolis's file.
6 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis deck, porch & stoop contractors →
The usual addition permit in Minneapolis takes 338 days from issue to the city's final inspection or closeout (404 permits, October 2023 through September 2026). 75.8% of addition permits a year or more old have been closed out. The quickest quarter of firms usually finish in 8.5 months, the slowest quarter in 12 months. The wait for approval before issue is not in Minneapolis's file.
2 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis addition contractors →
The usual new home permit in Minneapolis takes 396 days from issue to the city's final inspection or closeout (204 permits, October 2023 through September 2026). 84.5% of new home permits a year or more old have been closed out. The quickest quarter of firms usually finish in 8.9 months, the slowest quarter in 9.6 months. The wait for approval before issue is not in Minneapolis's file.
4 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis new home contractors →
The usual demolition permit in Minneapolis takes 151 days from issue to the city's final inspection or closeout (187 permits, October 2023 through September 2026). 86.0% of demolition permits a year or more old have been closed out. The quickest quarter of firms usually finish in 3.5 months, the slowest quarter in 6.1 months. The wait for approval before issue is not in Minneapolis's file.
5 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Minneapolis demolition contractors →
Source: City of Minneapolis construction permits (CCS). The window is October 2023 through September 2026; a permit filed after that isn't here yet.
A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.
Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.
Nobody paid to be on this page and nobody can. How the records work in Minneapolis →
Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX